“135. The total liquidated damages is£180,000 . 136. Sentosa is not entitled to deduct the sum of£180,000 or any other sum of liquidated damages from JPA. 137. Sentosa is entitled to claim the sum of£180,000 from JPA.”
“a) Where it follows logically from an adjudicator’s decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator’s decision, provided the employer has given proper notice (in so far as required). b) Where the entitlement to liquidated and ascertained damages has not been determined either expressly or impliedly by the adjudicator’s decision, then the question whether the employer is entitled to set-off liquidated and ascertained damages against sum awarded by the adjudicator will depend upon the terms of the contract and the circumstances of the case.”
“In a number of the authorities which I have cited above the point has been made that each case should turn on its own facts. Whilst I respectfully agree with that, it does seem to me that there are a number of clear principles which should always govern the exercise of the court’s discretion when it is considering a stay of execution in adjudication enforcement proceedings. Those principles can be set out as follows: a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. b) In consequence, adjudicators’ decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. c) In an application to stay the execution of summary judgment arising out of an adjudicator’s decision, the court must exercise its discretion under order 47 with considerations a) and b) firmly in mind (see AWG Construction Services Limited v Rockingham Motor Speedway Limited[2004] EWHC 888 (TCC) . d) The probable inability of the claimant to repay the judgment sum (awarded by the adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of order 47 rule 1 (1) (a) rendering it appropriate to grant a stay (see Herschel) e) If the claimant is insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues (Uk) Limited v Dahl-Jensen Limited[2000] BLR 522 and Rainford House) f) Even if the evidence of the claimant’s present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: i) The claimant’s financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschel); or ii) The claimant’s financial position is due, either wholly or insignificant part, to the defendants failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)” i) The claimant’s financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschel); or ii) The claimant’s financial position is due, either wholly or insignificant part, to the defendants failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)”