“.. the reason for extending the time limit for documenting buyers long term financing is that Havila Kystruten AS has to re-open the discussions with Bocomm, since the present term sheet is based on a different payment structure and not the "progress payment" as set out above. As of today we do not know the time required to have a revised term sheet approved by Bocomm, but Havila Kystruten AS is optimistic and really hope that it should be possible to have a reconfirmed term sheet based on a "progress payment" as set out above, much earlier than by the end of October 2018.”
“According to Article III, clause 3 the Buyer has an obligation to provide written confirmation from bank (s) and/or financial institution (s) to provide long-term financing of the Vessel for the purpose of enabling the Builder to reasonably satisfy himself that the Buyer has financial arrangements or resources to pay the instalments when due. The Buyer has in meetings informed the Builder that a term sheet has been signed with the lender providing the pre and long term financing arrangement for the Vessel ("Buyer's Financing"). The Builder hereby accepts that the statement of the Buyer concerning the Buyer's finance satisfies the financing requirements of the Buyer as set out in Article III, clause 3 of the Contract.”
“Q. And it's right, isn't it, that it was recognised by the structure of addendum number 1 that the execution of the loan documentation, scheduled to be finalised within 31 October, was the hinge upon which everything else rested because, until that happened, there couldn't be the CESCE counter guarantee and then there could be no refund guarantees. That's right, isn't it? A. No, that is not right, the way we understood it. At that time we were not aware of that CESCE -- ... We were not aware of that, that there was a requirement that the loan agreement should be executed in order to have this counter guarantee issue from CESCE. Q. Well, we looked at the scheme, Mr Pettersen, and the starting point is that the execution of the loan documentation is scheduled to be finalised within 31 October and that is the date which you have given the Yard as the likely date, and you then agree that, if anything more is required, then you will provide it by 15 November, and it is obvious -- A. That is correct. Q. May I finish my question. It is obvious from what you see in clause 2.3 that the potential requirement of further confirmation of the execution of the loan documentation is the potential requirement of CESCE. That's right, isn't it? A. Yes, it is right, but I will repeat and underline that, at that time, we did not know what was the requirement of CESCE, and I also underline and repeat that the 31 October was what I would say scheduled for having this loan documentation signed up and completed.”
“… please note that we are not aware of any issue with Cesce related to the execution of counter guarantees or insurance in favour of the Refund Guarantors. In any case please kindly note that the Builder takes that it is not for the Buyer to deal or make any action regarding Cesce and would therefore kindly request the Buyer and/or its advisors to avoid any dealing or contacts with Cesce.”
“Dear Stein, the Spanish ECA, CESCE, inside the process of fulfilling their insurance, is asking our financers and guarantors some information about you as shipowner under the contract. They need to know any things about your finance from BoComm like: Term, amounts, conditions... Could you provide us with it? If you prefer, directly to them?”
“… as of today we are not allowed to forward you a copy of the term sheet. We can provide you with a letter from Bocomm confirming the pre- and post delivery financing. Will that be to any help to you?”
“Documentation for HK’s financing - Letter from BoComm will be satisfactory.”
“At the request of the Buyer, we are hereby providing you with these confirmations 'We - Bocomm Financial Leasing Co, ltd, having the registered address 28'h Floor, 333 Lujiazui Ring Road, Shanghai, PRC and with business registration address 28ù Floor, 333 Lujiazui Ring Road, Shanghai, PRC ("Bocomm") hereby confirm that the Buyer and Bocomm have agreed upon a term sheet for the financing of the Vessels which has been signed on the2 August 2018 ("Term Sheet"). The Term Sheet includes pre - delivery and long-term financing of the Vessels ("Pre and Post Delivery Financing"), and Bocomm intends to provide the Buyer with a financing for each Vessels to the lower of EUR 82,8 million and 90% of the agreed original contract price of each of the Vessels. The Pre and Post Delivery Financing is subject to final documentation, and the approval of the board of directors of Bocomm. The documentation will include standard provisions for a loan transaction of this nature, and completion of the loan documentation is scheduled within 3l October 2018. We expect that this letter of intent meets your requirements and are looking forward to the cooperation with the Builder and the Buyer in this transaction.”
“A) As agreed yesterday on the phone, please find here below some comments (received from our banks/insurers) with regard to the bond insurance draft received from Alfredo Cabellos on the 15th January. Kindly please note that we take that the draft is a step backwards as you open new issues. There are also comments in your draft which make reference to matters that we had already agreed (at least on principles). These are the main issues: … - 10.- You wish to have the right to assign to any other party providing finance which is a new issue (and CESCE forbids). This had already been discussed and agreed; If you have any other party in mind this needs to be specifically stated (CESCE would need to approve it); - 11.- You request 60 calender days previous notice to be entitled to terminate in case of the inaccurate, false .. information which is a new issue and goes against CESCE policy (it leads to automatic termination) … C) Lastly, we would like to stress that we are very concerned about your feedback on the lack of progress of your financing talks with Bocomm. We see that this no progress with Bocomm leads to a dangerous delay with the issuance of the refund guarantees and, therefore, to the payment of the second instalment. You will no doubt agree that this is becoming a burden for the entire project (delivery dates included). We are glad to hear that you are working on European alternatives to Bocomm which could facilitate some aspects of the projects.”
“In line with the telephone conversation, we have had this morning, I would like to tell you that we have already consulted with CESCE about the possibility of including as beneficiary a bank other than BoCom, and its response has been positive, provided that it is perfectly identified. As you all know, the CESCE offers are valid until next 28 January (its extension already requested) and taking advantage of the fact that the extension will pass through their committees, they will include our request that the beneficiary of the guarantees may be a bank other than BoCom. Although they have stressed once again, and as it appears in the coverage conditions in point 6.6, that confirmation of the firm existence of sufficient financing is necessary for the execution of the entire project, so in order to materialise the CESCE coverage, closing a financing for the Shipowner is essential. Actual financing cannot be formalised without prior formalisation of the shipowner’s financing.”
“Sorry for the delay in answering but I was checking with CESCE; Cesce insurance would not enter into force until the condition that the shipowner has the funds to undertake the project is met, likewise we would not be able to issue a guarantee. Therefore, the way to justify it is either with a certificate from the financing bank of the Shipowner where they confirm the existence of said financing already formalised with amount and terms or provide us with a copy of the financing. For the signing of the financing, Astillero [the Yard] could do with the commitment of the financing bank of the Shipowner, but for the issuance it would already be necessary for said financing to be formalised.”
“24.01.2019 kl. 09:00 Meeting with Watson Fairley in London, Alfredo Lois. Barreras. Stein, Arild, Per. Spanish Tax Lease, Havila Kystruten. Stein [Mr Pettersen] informs about the status of Bocom and the problem with Spanish Tax Lease. Ownership during the lease period. Payment guarantee from Abanca with guaran- tee from these and other smaller guarantors. Abanca 60.6 - Barreras 3.0 = 57.6. Cesse 50%. Will get an overview of how the guarantees should be designed. 360 days per year for interest calculation. Discussion on the appointment card, many details that have been commented on. Summary. The meeting ends at 17:30.”
“Møte London. HK have received at new term sheet from Bocomm. There are some problem with implementing the tax-lease with the financing from Bocomm. HK is in discussion with 3 banks. We will sort this out within the next weeks. Discussion around the insurance bond and who is behind. - Documentation to Barreras that financing is in place - Clarify the company structure - Barreras to delivery an overview over the guarantee structure - Clarify if the interest is covered under the guarantees - Barreras to send ratings of the guarantors.”
“Q. … in circumstances where they were building the vessels and you weren't paying them for the work that they had done in accordance with the contract schedule, that was imposing a burden upon the Yard? A. I agree that the Yard need funding to complete the vessels. Q. And we heard Mr Pettersen, in his evidence yesterday, accept that the situation in January 2019 was not sustainable for the Yard. You would agree with that, wouldn't you? A. I agree that we -- all parties need to have necessary financing in place to be able to fulfil the projects. Q. If they don't have any cash, they can't build, can they? A. No, not over a long period.” … “Q. … And that [22 July 2019 ] was two months after the date that you recorded in addendum number 8 that you expected to have drawdown, isn't it? A. Yes, we expected to have financing in place.” as showing that Mr Myrvoll equated “financing in place” with the ability to draw down funds. Abarca’s thesis is thus that when Mr Myrvoll wrote “Documentation to Barreras that financing is in place” in his note at the24 January 2019 meeting, he was recording that the Yard had asked for proof of signed loan documents. However, it does not follow, from the fact that Mr Myrvoll on those occasions used the phrase in that particular sense, that Havila must in fact have been told at the 24 January meeting that something as specific as signed loan documentation was being sought. Q. If they don't have any cash, they can't build, can they? A. No, not over a long period.”
“Q. Do you take any notes when you attend meetings? A. Yes. Sometimes I do; sometimes I use my own memory. Q. And do you keep those notes when you take them? A. I don't have to keep them. Q. That wasn't my question. A. I'm not a lawyer so, you know, my method of working is different, you know. Q. I'm not asking about what you're obliged to do. I'm just -- I don't know you, Mr Fernández. I'm asking what you do— A. I'm a reinsurer. I'm a reinsurer. I underwrite risks upon the basics of the documentation I'm giving. That's ... Q. I'm just asking: do you take notes? Not do you have to or should you or is it wrong for you not to, but just do you? A. Yes, I take notes. Sometimes I take them. Q. And do you keep them? A. Yes, normally I keep them. Q. Right. And have you gone back to see if you took notes of any of the meetings that you attended in this case? A. My only notes in those meetings was that there was no finance. That was my note. Q. No, come on. Try and answer the question. Have you gone back to see whether you took any notes of those meetings that you attended -- the two meetings you say you attended, for which we're not sure about the dates? A. I find that irrelevant, to be honest. Q. Don't worry about what's irrelevant. The learned judge will tell us what's irrelevant and tell us what's irrelevant in due course. Have you gone back to look to see whether you took any notes of the two meetings you attended? A. No. Q. Were you asked to do that? A. By whom? Q. By lawyers. Anybody. Did anybody ask you to do that? A. You know, I remember things perfectly well, so I don't need notes for that.”
“Q. … There was a meeting on24 January 2019 in London, which I think you attended? A. Yes, I did. Q. And I think you were there because one of the topics on the agenda was the wording of the insurance bonds. A. Yes. Q. And you would be Abarca's lawyer on that issue. A. Exactly. That is right. Q. And did you take any notes? A. I probably did. Q. And have you gone back to find those notes? A. Not really because -- because, for preparation of the -- of the statement, I check the correspondence that I have. And also I checked the summaries that we did after the -- I think not this meeting but probably the other one. So, no, I don't think I came back to my notes. Q. But you take notes and you -- presumably, as a lawyer, you keep your notes? A. Yes, probably I have those notes. Q. But you say you didn't go back to check what they said? Isn't that a slightly strange thing to do? If someone asks you what happens in a meeting and you're going to come to court to talk about it you didn't go back to check your notes of the meeting? A. No. And I don't think that it is strange because I think that the themes that we were discussing at the meeting were very clear. As you said it was about the wording of the bonds, about the bonds providers. So I don't -- I don't think I need to check my notes to be honest. Q. That's a very strange thing to say to me Mr Fernández Santos. You're talking about a meeting now that happened three years ago. A. Yes. Q. More than three years ago. If I had attended a meeting three years ago and I wanted to know what had happened at that meeting or wanted to refresh my memory about that meeting, I would look at my notes. You really -- it didn't cross your mind to do that? A. Not really. I mean, I don't know what you will do. I can tell you what I did. And, to me, I have a clear recollection of the note -- sorry, of the meeting. And -- and -- to be honest, I don't come so often to London so as to forget the meetings that I have here. So, no, I didn't check my notes. I'm sorry. I have some recollection of the meeting and I didn't need to -- to check. Q. Do you think, sitting there now, that it would have been a better idea before you started expressing views about what you think you might have remembered from a meeting three years ago to have a look at your notes of that meeting? A. We can double-check what I said about the meeting and then we can see if I need the notes or not. Q. Well, do you -- you do understand it's quite an important -- quite a serious exercise, giving evidence to the English court. You know that, don't you? A. I am not joking. What I'm saying if you want to know, if I need to check my notes, what I am saying is that probably I need to review what I have said about that meeting. And then I can see if I need the notes or not. I mean, I didn't -- I didn't feel, at the time, that I need to double-check my notes.”
“The "goal" is to have the complete documentation (guarantees / tax lease documentation / buyers loan documentation) agreed and executed in due time before15 March 2019 . We suggest that we discuss a further working schedule in the meeting in Madrid on the 7 and8 February 2019 , securing a good progress on outstanding matters so that we meet this time limit.”
“As I have told to you at Madrid, it is no possible for HJB to take more risk on this projects until first security shall be issued. Havila has to take own risk to finance next month of the project.”
“07.02.2019 (day 1) Madrid Banca Marc is not in position to offer refund guarantees. Discussions around Insurance bond and Master agreement. Juan can inform that steel cutting is in progress. Keel laying in March. The Insurance bond is not an “on demand guarantee”
“As commented this afternoon we have proposed the following scheme in order to continue building the vessels 1710 & 1711 without delays on the construction plan: (a) Financial Guarantees on the first instalment already put in place are maintained but the amounts guaranteed will be reduced in the cash actually available in the project accounts, i.e. Euro [1,4M] for 1710 and Euro [2,1M] for 1711; (b) On payment of the second instalment from Havila Insurance Bonds in the terms discussed and to be closed tomorrow will be put in place for the second instalment plus the amount deducted on the financial guarantees. These bonds will not enter into force until Havila produces evidence that they have funds available for financing all the payments to be made in respect of the Vessels, which evidence can be produced by attaching a financing agreement for the relevant amount or other evidence reasonably acceptable to the Parties;”
“I do not think that there is a big disagreement between the parties about what was agreed in Madrid”
“In general, we are not clear on what it means to have financing. They seem to want to lead us to a mere confirmation from their bank (the old discussion of whether it is worth a TS). Honestly, I am not concerned much, I think it will force us to argue, but better to argue with part of the insured milestone with insurance than otherwise;”
“Q. Well -- and then you say: "Honestly, I am not concerned much, I think it will force us to argue, but better to argue with part of the insured milestone with insurance than otherwise". So do I understand that to mean you're saying: we may have to argue about this later, but let's get the money in first? A. Yes. What I'm trying to say is: okay, it is clear that we cannot close that discussion now. I was not intending to say that we were prepared to accept the term sheet, because we were clear on that. But it is clear that we don't know yet what they can provide. And because they have not told us. So I understood from Juan [Sr Gonzalez] that they need the money in order to -- sorry, to continue the building. So I say: okay, if that is the important thing, because this is what Juan says, then let's postpone this discussion. That we cannot close now and let's reconvene later. Q. Let's sign the addendum, get the money in, and argue about this later? A. Well, let me be clear on this. I mean, this is the decision of the yard to continue proceeding. It's not my decision, so ... … Q. I'm not saying you're making the decision. I'm saying that you're effectively saying to him: if that's your priority then sign the addendum, get the money in – A. He didn't want to postpone these discussion. Although the discussion is there, but he didn't want to postpone the discussion. If you are prepared to take that risk that they can propose something, which is not sufficient -- I didn't think at the time, I believe, that they would, again, raise the issue with the term sheet because we were clear on that, but they could propose something different. So that is what I am saying. If we are not able, at this time, to say: okay, what you need to provide is certainly this, then let's continue the building process because otherwise the project will collapse.”
“The words used [in a contract] may, and often do, represent a formula which means different things to each side, yet may be accepted because that is the only way to get “agreement” and in the hope that disputes will not arise. The only course then can be to try to ascertain the “natural” meaning. Far more, and indeed totally, dangerous is it to admit evidence of one party's objective — even if this is known to the other party. However strongly pursued this may be, the other party may only be willing to give it partial recognition, and in a world of give and take, men often have to be satisfied with less than they want. So, again, it would be a matter of speculation how far the common intention was that the particular objective should be realised.”
“First of all – the buyer is not trying at all to delay the process. Havila Kystruten AS is preparing for making the payment of the 2nd instalment tomorrow and to proceed accordingly with the remaining payments. We have the full understanding of the importance of the tax lease to you and value of the tax lease benefits to be paid to the yard. Our concern is that we do not reach to conclude the documentation in time if a complete documentation shall be a condition for issuing the insurance bond for 3rd instalment. Provided the insurance bond can be issued even though the tax lease documentation is not in place as of payment of the 3rd instalment the buyer can "live with that" and have the documentation completed on a later stage.” and Sr Gonzalez’s reply: “About the 3rd instalment. The both things have to be related. If I have understood, you are going to pay third instalment with finance, but if you would pay with own resources the CESCE policy should not be in force if you don’t confirm the existence of required finance to pay the project. I have proposed to you to solve this with: a declaration of Havila or the shareholders that they will finance the project or they have funds enough to do and to apply to it. But if both things are related on the contract, finance evidence and 3rd instalment, we can go on.”
“This is to confirm what we have discussed and agreed by phone earlier today with regard to your main concern on the projects C1710 and C1711: The need of Havila's finance in place and duly signed. We can accept not to claim for the payment on keel lying on both projects (installment 3rd “c” of each contract) until you confirm that Havila’s finance is in place or until next April, 30th, whichever occurs first. However this would be subject to your confirmation that we can delay the payments to Havyard until the collection of said installment (3rd “c”) and with no effect on Havyard’s obligations under the Supply contract between Havyard and Barreras. The following installments ( 4th “d” and 5th “e”, with a maturity date set 60 days after installment 3rd “c”), shall be paid as if the installment 3rd “c” would have been paid in the contractual date. So they will not be affected by the arrangement we are discussing here, considering Havila’s finance in place.”
“After further considerations I have made a small amendment to you email. Is that ok to you? It is almost midnight and I suggest that we proceed tomorrow morning, and try to complete the appendixes to the agreement.” with the slightly altered text for Sr Gonzalez’s second paragraph now reading: “We confirm not to claim for the payment on keel lying on both projects (installment 3rd “c” of each contract) until you confirm that Havila’s finance is in place or until next April, 30th, whichever occurs first. The reason for this is that such extension is already covered by the agreed Addendum No 7.”
“Q. … So what you record there [Addendum 7 § 2.5.1] in terms, don't you, is that you knew, you, the Buyer, knew, that the Yard needed evidence of financing in order to issue the documents listed there? A. Yes, that's stated in that clause. Q. Yes, and it ties in with what we saw in clause 2.2.2, which is only once you evidence your finance will the Insurer, Barents and CESCE, respond with the various security documents? A. Yes. Q. So you know, don't you, what the evidence -- what the purpose of you providing evidence of your financing is? A. Well, in a way you can say that. What I knew at that time was that we needed to provide evidence for the financing. I was not aware of what kind of evidence it should be or if there is a particularevidence which is not covered by a committed statement. So we used the word "committed statement" in the agreement and – Q. I'm not going to debate with you what the words "committed statement" mean – A. No, I don't expect that either.”
“Provided the Financing is approved by the relevant decision making bodies as set out above, it is our intention to conclude and close the documentation before mid June 2019. However, this will be dependent on that all Parties involved contribute to a smooth process and that we agree on satisfactory documentation. Consequently, drawing under the Financing should be possible within June 2019.”
“This Insurance Policy will not take effect until the financing of the purchase of the vessel by the importer is signed in terms satisfactory to CESCE. The Policy is conditioned on compliance with the aforementioned Condition Precedent, so that coverage will not be initiated, nor will there be any right to any possible compensation until it is fulfilled. …”
“The Yard is always very flexible with its customers, and we would never want to cancel a project, so this was something to be discussed rather than something we would look to use against a customer. It would also be bad for the yard’s reputation in the market. However, as I have said before, where a Buyer does not pay on time that becomes a problem in having funds available to pay for the work that needs to be done.”
“Q. And you told them at this point that you expected to be able to have cash from GTLK within July? A. I think we indicated by the end of July. I can't recall exactly but I think I have it in the notes from the meeting. Q. Is it right that by this point the Norwegian banks had fallen out of favour, as it were? A. No, I don't think so, but I think it much better that Arild Myrvoll gives details about that. … Q. … All I meant by that was your preference at this point was GTLK? A. Our preference was GTLK because it was higher leverage, meaning you could lend more money, and I think also the terms were rather good. Q. Yes. So you told them that you expected to be able to have cash from GTLK within July at this meeting, but the Yard wasn't persuaded by your promises because they wrote to you on 21 June, just after this meeting, informing you of their intention to terminate under clause 2.5.1, because you hadn't confirmed their financing, didn't they? A. That is correct.”
“Mr Myrvoll informed the Yard’s representatives, Mr González, Mr López and Mr Pérez, the Yard’s Spanish lawyer, that HKAS had now obtained a committed term sheet from GTLK. This fact was later recorded in Clause 2.1 to Addendum no. 9 to each SBC. In fact, I recall that I offered to show Mr González of the Yard a copy of the GTLK term sheet with the commercially sensitive terms redacted out. Indeed, Mr Myrvoll showed the redacted copy in his hand to Mr González across the table, but Mr González refused to look at it in detail and declined to keep a copy.”
“Since the buyers pre and post-delivery financing now has been confirmed – as advised to you in the meeting in Amsterdam – we hope that we should be able to conclude the outstanding matters and sign up an Addendum No 9 while we are in Amsterdam next week.”
“In order to meet the timeline which we are working under in respect of the documentation for the buyers financing, we need to complete the Addendum No 9 tomorrow so that we can submit the revised payment schedule as discussed in the meeting on the 27 and28 June 2019 to GTLK in order to prepare for the payment of EUR 24,6 million [i.e. the 3rd instalment] within31 July 2019 on each of the contracts for NB 1710 and NB 1711, respectively.”
“The Parties agree that by entering into this agreement, the Parties have complied with the obligations to negotiate in good faith according to the terms and conditions of clause 2.5.1 of the Addendum No 7 (as amended by Addendum No 8), and no further negotiations as set out in clause 2.5.1 of the Addendum No 7 are required for the Builder to be entitled to cancel the Current Contract according to clause 2.5.1 of the Addendum No 7 (as amended by Addendum No 8). The Parties agree that fourteen (14) days negotiation period referred in Clause 2.5.1 of Addendum No. 7 (as amended by Addendum No 8) have elapsed without satisfactory arrangement for the Parties in order to find a satisfactory solution today for both Parties.”
“We really hope that the postponement of the board approval of STLC does not cause a delay in the documentation of the loan. We ned to have the documentation ready and signed /executed so that we can draw on the loan in the week commencing with29 July 2019 .”
“By and between Havila Kystruten AS (as borrower) and GTLK Europe DAC (as lender) a term sheet dated26 June 2019 has been entered into for the financing of the vessels NB 1710 and NB 1711 to be delivered from Barreras to Havila Kystruten AS according to the terms and conditions as set out in two separate shipbuilding contracts dated24 April 2018 (as from time to time amended by addenda thereto), said term sheet hereinafter referred to as the "Term Sheet" and the transaction as described therein as the "Transaction". According to my legal capacity as the company CEO of GTLK Europe DAC, I (the undersigned) hereby confirm that the Term Sheet has been approved by the Board of Directors at GTLK Europe DAC and that the Term Sheet is binding upon the lender according to terms and provisions as set out therein. The approval of the Term Sheet is only subject to satisfactory documentation of the Transaction.”
“Your claim to be entitled to cancel the Contract seeks to rely on Clause 2.5.1 of Addendum no. 7 to the Contract. Clause 2.5.1 does indeed contain a right of cancellation of the Builder where the Buyer cannot confirm the pre- and past-delivery financing of the Vessel by30 April 2019 (a date thereafter extended to31 May 2019 by Addendum no. 8). However, and among others, the Builder's right is subject to a number of conditions precedent including that the Buyer and the Builder must meet physically “in order to consider and to negotiate in good faith alternative arrangement[s] in order to avoid termination and/or cancellation of the Contract” and, further, that they must have concluded after a 14 day negotiation that “there is no alternative financial arrangement” available. Meetings took place in Vigo on 17 to19 June 2019 , and in Amsterdam on the 27 and28 June 2019 and on 9 and10 July 2019 . Your11 July 2019 letter, in which you refer to the parties’ meetings in Amsterdam, does not mention that, at these meetings, we confirmed that we now had obtained a committed term sheet for financing that we expected to be drawn down by31 July 2019 — or within7 August 2019 as agreed in the meeting on11 July 2019 as payment of the next instalment. We attach, for your ease of reference, a confirmation from GTLK Europe DAC (Ireland) which we have obtained in order to confirm the financing. If required we can also provide you with a redacted copy of the term sheet dated26 June 2019 . Accordingly, the position is that we have now confirmed that the required financing is in place, even if we did not do so before31 May 2019 . The documentation will only deviate from a previous financing with the same financier concerning the 2 vessels which are under construction in Turkey, in terms of including the Spanish tax lease entered into for your benefit on21 March 2019 . For our part, we therefore fully intend to perform the Contract, and we have a committed offer of finance in place. Consequently it is clear that the conditions precedent to any right to cancel under Clause 2.5.1 have not been satisfied …”
“Following various meetings in Vigo on 17 to 19 June, and in Amsterdam on 27 and28 June 2019 and on 9 and10 July 2019 , and various subsequent exchanges, the Parties decided to meet again in good faith to address design issues faced by the project of the Vessels. The technical discussion entails the need to also discuss the financial and timing consequences of the potential solutions. The overall solution is to be documented in an Addendum No 9 to the Contracts (“Addendum no 9”). Barreras and Havyard present several solutions to Havila.”
“[The Yard] states that nowadays no financial arrangement has been agreed by [the Yard] and [Havila] and that only by signing the expected finance communicated by [Havila] concerning GTLK’s financing is not enough to be considered a valid alternative financial arrangement. [Havila] disagrees with and rejects such statement.”
“We just finished the meeting with the Norwegians. We have reached a basic agreement. [The Yard] will not assume more than one-third of the cost of modifying the project caused by its technical office (estimated impact on [the Yard] due to loss of profitability about 3.5-4.5 million). The remaining two-thirds will be assumed between the shipowner and its technical office. Havila will have its financing ready on 8 August. GTLK Europe DAC Bank. From that day on, they will be able to pay us the 45.2 million that they owe. On Friday, next week, we have arranged to meet in Oslo to close the rest of the complementary matters in addendum 9 that leads us to the full perfection of the contract, collection of outstanding amounts and normalised construction. Therefore, I confirm that we would need the extension of the CESCE policy valid for one month before we go on holidays. I have informed CESCE of all this. CESCE has told me that there are many things I didn’t know because it hadn’t been informed, for example, the name of the shipowner’s new bank (GTLK). I had told them in June! …”
“On the one hand, I would like to inform you that CESCE, as I had told you over the phone, asked us to make a global assessment of the risk increase, this is the total situation of the Shipyard, not only of the Havila projects in particular and our assessment in this regard as a Bank, which response they require to be before tomorrow at 10 a.m. so that the extension can be processed. On the other hand, I confirm that CESCE HAD been informed of the new bank, I don't know who you're talking to about it, but I assure you that we had informed it and attached you will find a screenshot of the email from 2 July where you can check that it is like that.”
“Finally – and with reference to the discussions yesterday concerning the confirmation of GTLK of the pre- and post- delivery financing of the vessels as contacted by Havila Kystruten AS at Barreras, we attach for sake of good order a new copy of the confirmation of GTLK as of16 July 2019 .”
“As far as concerns the clarifications – please be advised that technical clarification meetings are going today and tomorrow and that a conference call is scheduled for Monday26 August 2019 . I will assume that we will know more after the call on Monday when we can expect to finalize the technical evaluation and have the discussions with Barreras completed and be ready for drawing under the Facility Agreement”
“Please note that the payment of the Second Additional Payment as per the draft Addendum No 9 (1 x EUR 5,000,000 per vessel) is subject to that the construction of the vessels is being restarted immediately. Please therefore prepare for such restart of the construction of the vessels.”
“4.2 September 2019 : Relevant information outstanding (if any) to be provided by Havyard Design & Solutions AS and forwarded to Barreras for review of the Havyard Alternative. 5.4 September 2019 : Lifting of the board approvals in the Addendum No 9 and the Addendum to the Supply Agreement. 6.5 September 2019 : Delivery of the insurance bond to be issued for Second Additional Payment to Watson Farley & Williams in Madrid. 7.6 September 2019 : Payment of the Second Additional Payment to Barreras. 8.9 September 2019 : Required confirmation for insurers, reassures, refund guarantors and CESCE to be provided to Havila Kystruten AS. (Approval of Addendum No 9, extension of the expiry date of the insurance bond / refund guarantees). 9.9 September 2019 : Satisfactory insurance bond including cut-through agreement to be provided for 3rd Instalment (EUR 24,600,000) in respect of both vessels (NB 1710 and NB 1711). 10.12 September 2019 : Payment of the 3rd instalment for both vessels (NB 1710 and NB 1711). (Please note that we have maintained this date in the attached draft Addendum No 9, but due to providing the confirmation from the insurers / CESCE as set out in item 9 above, we maybe have to amend the payment date till15 September 2019 . Let us discuss that tomorrow). 11.14 September 2019 : Conclusion in respect of technical solutions to be applied (Barreras Alternative or Havyard Alternative). 12.21 September 2019 : Final date for agreeing / concluding the Havyard Alternative (if finally chosen by Havila Kystruten AS). 13.21 September 2019 : Suggested date for all conditions / approvals to be fulfilled (Target Date or Long Stop Date).”
“We refer to our discussions this morning and your request to provide a confirmation from GTLK stating that we have agreed upon the loan documentation and that we are ready to draw subject to fulfilment of conditions precedent. We have discussed the matter with GTLK in a conference call today, and although they find the request somewhat strange based on the confirmation provided as of16 July 2019 , they can be willing to issue the requested confirmation if that can speed up the required approval of the Addendum No 9 by the insures [sic] / CESCE. Based on this we suggest the following wording which we kindly request you to consider and respond to…”
“By and between Havila Kystruten AS (as borrower ) and GTLK Europe DAC (as lender) a term sheet dated26 June 2019 has been entered into for the financing of the vessels NB 1710 and NB 1771 to be delivered from Barreras to Havila Kystruten AS according to the terms and conditions as se out in two separate shipbuilding contracts dated24 April 2018 (as from time to time amended by addenda thereto) ("Shipbuilding Contracts"), said term sheet hereinafter referred to as the "Term Sheet" and the transaction as described therein as the "Transaction". By our letter dated16 July 2019 , we confirmed that the Term Sheet has been approved by the relevant committees of GTLK Europe DAC and State Transport Leasing Corporation and that the Term Sheet is binding upon the lender according to terms and provisions as set out therein. The only remaining subject was satisfactory documentation of the Transaction. With reference thereto we further confirm that the Havila Kystruten AS / Havila Holding AS (as obligors) and GTLK Europe DAC (as lender) have agreed upon the facility agreement and the security documents appurtenant thereto, and that we have the require funding available for the drawing of the next payment (3rd instalment) being EUR 24,6 million to be paid under each of the Shipbuilding Contracts. The only outstanding matters as for now is completion of the conditions precedent as set out in the facility agreement, which includes (i) the notice of assignments to be made to the insurers / reinsurers and refund guarantors providing the refund arrangement, (ii) insurance companies providing the insurance of the vessels under construction and (iii) Barreras in respect of the assignment of the Havila Kystruten AS` rights and benefits under the Shipbuilding Contracts.”
“We have conveyed the comments to GTLK, and here is the revised draft of the notices/acknowledgement. In terms of the first comment, as mentioned, this notice will be delivered on closing – that is the earliest we can deliver it - and it needs to be effective on the date delivered because otherwise the agreements to pay to the Assignee would not be effective. In parallel, we also need comments, if any, to the attached notices: one relates to the assignment of rights under the SBC (comments should come from Barreras) and the other under the tax lease (comments should come from Luis Mingo/BM).”
“Also note that unless the outstanding matters be solved within 15,00 CEST of today the 4th September and Addendums 9 be executed within said timing, we shall consider that the Parties have not been able to reach an acceptable Agreement as stated in the Current Contract. As per our phone call earlier today, an unambiguous Owner's and GTLK ’s confirmation of the availability of the pre and post delivery financing is paramount to further proceed with the projects as contractually agreed. Insurers have just requested this evidence as a condition to approve the issuance of the insurance bonds. In this regard, please also note that this confirmation is also needed within today.”
“First of all we would like to pass to you all Havila that we are extremely disappointed and frustrated by the Havila Kystruten AS' response to several weeks of intense discussions and negotiations aimed to solve the current situation. It was our understanding that the Buyer and the Builder had agreed in the Addendum n. 9 how to further proceed with the vessels construction with an acceptable solution for all the parties. We would also like to state that the only reason why the parties are facing the current situation is due to the fact that Havila Kystruten AA has not been able to honor its payment obligations under the Current Contract and confirming the pre and post delivery financing of the Vessels as per the agreement between the parties. This failure by Havila Kystruten AS to fulfill its payment obligations has caused the projects coming to a halt and serious damages to Hijos de J. Barreras SA. With regard to the Design responsibility, please note that Hijos de J. Barreras SA has always undertaken the control of the Buyer’s parent company Havyard Design & Solutions AS design and also made repeatedly Havila Kistruten AS (and the Designer) aware of the deficiencies, errors and increased risk relating to such design which HJB discovered. Furthermore the Builder has clearly shown its willingness to find and contribute to solve the technical challenges derived from such designs issues. But it seems -unfortunately- that Havila Kystruten AS disregards the above mentioned facts. We do to see that the matters set out in your email can be neither accepted nor timely implemented within the end of the week (bearing in mind all the financial and technical issues to be considered and related to Havila’s last minute requests) and, therefore, kindly please note that Hijos de J. Barreras SA’ s position is that the parties have concluded that there is no alternative financial arrangement to be provided by Havila Kystruten AS to the Builder in order to avoid the cancellation of the Current Contract. All Builder’s rights are expressly reserved.”
“I am confident that we are in a phase of resolving the last few challenges. I am forwarding you the text with a modification. Please print it on corporate paper and send it signed to us to complete the file.”
“HIJOS DE. J. BARRERAS S.A. Dear Sirs, We refer to the shipbuilding contracts dated24 April 2018 (as from time to time amended by addenda thereto) entered into by and between Hijos De J. Barreras S.A. ("Builder") and Havila Kystruten AS ("Buyer") for the vessels NB 1710 and NB 1711 (the "Vessels" and the "Shipbuilding Contracts”, respectively). According to an Addendum No 9 which is under negotiation between the Builder and the Buyer, a total amount of EUR 130,360,000 is going to be paid to the Builder for each of the Vessels, in the terms and conditions of the Shipbuilding Contracts (including said Addendum No 9, when it enters into force). We as Buyer have as of today paid up the 1st and the 2nd Instalment under each of the two Shipbuilding Contracts for a total amount of EUR 16,400,000 for each of the Vessels. A total amount of EUR 26, 420,000 is going to be settled for each of the Vessels through Spanish financial structures. As a result, a total of EUR 87,540,000 payable by the Buyer ("Remaining Outstanding Amount") will be outstanding under each of the Shipbuilding Contracts. In addition to GTLK `s confirmation of16 July 2019 , we hereby confirm that we have the sufficient funding and are able to settle the Remaining Outstanding Amount according to the payment plan as being incorporated in the Addendum No 9 by the aggregate of (i) the pre- and post-delivery financing to be drawn in due course from GTLK and (ii) our own available funds (equity). We hope you find this confirmation satisfactory. Fosnavåg10 September 2019 Havila Kystruten AS Per Sævik (Chairman of the board of directors)”
“But consider that this shall be not enough to confirm the finance to Reinsurers, Financers and CESCE, in the correspondent moment. We refuse your previous comments about the sufficiency of the said letter from GTLK of16 July 2019 as an evidence of a committed statement from the bank. And we aware you that to issue the Cutthrough, to have CESCE policy in place and issue RG’s, shall be not enough, as per the contract, only the two letters. For that, we kindly ask you, also, to send to us the refered Term Sheet as stated in the attached letter and the confirmation from the bank that all the subsequent conditions of the letter (satisfactory documentation …) have been lifted.”
“3.2 The Buyer shall pay to the Builder, an additional cash amount of EUR 5,000,000 (Euros five million 00/100) one (1) Banking Day after the Insurance Bond for this payment has issued and delivered to Watson Farley & Williams in Madrid ("Second Additional Payment” and “Second Additional Payment Date”, respectively), see clause 3.3 of the Addendum No. 9. Upon the Buyer's payment of the Second Additional Payment, the Builder undertakes to "re-start" the construction and building of the Vessel immediately subsequent to two (2) Business Days after the Buyer's payment to the Builder of the Second Additional Payment. In this respect “re-start” of the construction and building of the Vessel shall be regular and as considered to be normal for the shipbuilding industry for such a vessel under construction as NB 1710, in the current circumstances. 3.3 [i] Provided that the board approvals are being granted, the Second Additional Payment shall be made against Insurance Bonds as issued for the First Additional Payment (see Appendix 1 hereto) (with logical amendments), however, without the obligation to provide a Cut-Through Agreement if the final financing cannot be drawn by the Buyer as of the Second Additional Payment Date. The Insurance Bond shall be assignable to the Lender and / or security trustee under the Buyer's pre and post- delivery financing of the Vessel. [ii] The original copy of the Insurance Bond for the Second Additional Payment shall be delivered to Watson Farley & Williams in Madrid not later than on18th September 2019 . [iii] If the Builder cannot provide and hand over the Insurance Bond as security for the Second Additional Payment on the Second Additional Payment Date, the payment of the Second Additional Payment shall be postponed correspondingly. If the payment of the Second Additional Payment is not being made on the Second Additional Payment Date (as extended according to this clause 3.3 of the Addendum No 9) the provisions of clause 9.3 [sic. 9.4] of the Addendum No 9 concerning the cancellation of the Current Contract, shall apply”
“I also want to explain briefly the reasons for agreeing with ABARCA to issue the insurance bonds without the confirmation of financing by Havila. First, it was our understanding throughout that Havila would obtain pre and post-delivery finance, which would then activate the CESCE Policy and the Policy of Issue of Guarantees and Insurance Bonds. It was never envisaged that Havila would be unable to do so. The message that was relayed to us by the Yard (which I think, was their reasonable expectation) is that Havila would obtain finance. However, at no point did the Yard inform us that Havila actually did have financing in place.”
“Except for the matters outstanding in respect of the notice of assignment we should be more or less ready to execute the documentation for the loans to be provided. We therefore have to put pressure on finalizing outstanding matters. As far as concerns the matters outstanding in respect of the notices etc. we prefer to deal with this by ourselves together with Alfredo Cabellos of Watson Farley & Williams, and will therefore follow up this matter together with him.”
“1. The conditions as set out in clause 12 of the Addendum No 9 shall be fulfilled within the time limit as set out therein – ref. clause 12.6, second paragraph. However, we have to consider whether some of the time limits have to be slightly amended due to the fact that the board approvals are being lifted later than what was originally intended / expected when the agreement was executed. 2. The agreement to be entered into by and between Barreras and Havyard Design & Solutions AS concerning the Addendum No 2 to the Supply Agreement and the sharing of the compensation to be paid to Havila Kystruten AS in respect of NB 1710 and NB 1711, respectively, - shall be approved by Havila Kystruten AS. …”
“Addendum No 2 to the Supply Agreement to be entered into by Barreras and Havyard Design & Solutions AS is now agreed between the parties thereto and also approved by Havila Kystruten AS. This is formally communicated, for the purposes of lifting the conditional Havila’s board approval and proceed forward with Addendum No 9.”
“Following our conversation on Friday and the confirmation of the lifting of Havila’s board approval, payment of the 5 million euros per vessel (1710 and 1711) is ready to be made this morning, with today’s value date. But the issue both yard and Havila are facing is formal. A number of time limits in Addendum No 9 have been exceeded, and this should be fixed before or in parallel, for the benefit of all parties. In that respect, could you please confirm that the parties are still working within Addendum No 9 and the following revised dates? • Clause 12.2 - Approval of the Addendum No 9 by insurers / refund guarantors: Two (2) Banking Days prior to20 September 2019 (already passed or exceeded). New / extended time limit: Two (2) Banking Days prior to3 October 2019 . • Clause 12.3 - Expiry date of insurance bond / refund guarantees: Two (2) Banking Days prior to20 September 2019 (already passed or exceeded). New / extended time limit: Two (2) Banking Days prior to3 October 2019 . • Clause 12.4 - The approval of the revised payment plan as et out in Addendum No 2 to the Supply Agreement: Within16 September 2019 – extended by exchange of email till18 September 2019 (already passed or exceeded). However, this should be fine, pending the singing by Havyard Design & Solutions AS only. • Clause 12.5 – Intercreditor Agreement: Two (2) Banking Days prior to20 September 2019 (already passed or exceeded). New / extended time limit: Two (2) Banking Days prior to3 October 2019 . Please confirm this works in your end at your earliest possible convenience.”
“We, on behalf of HJB, confirm that -subject to the due cash payments as per clause 3 of Addendum be made this morning with today’s value date, as per your email- the Addendum No 9 shall deemed to be in force and effective and that the revised/extended dates of clauses 12.2 (two (2) Banking Days prior to3 October 2019 ); 12.3 (two (2) Banking Days prior to3 October 2019 and 12.5 (two (2) Banking Days prior to3 October 2019 ) shall be applicable to the Addendum No.9 between HJB and Havila.”
“Below is the translated version of todays newspapers in Vigo. This is no good reading, and it seems that you are far away from a conclusion. Do you have any comments on this? We have agreed with Barreras around a new Addendum to the ship building contract, but we don’t want to do further payments before we see a total solution for the yard.”
“Q. …What was said at this meeting that certainly involved Barents, and I think involved you. The buyer said: "We will fulfil the contract. We are ready to pay and have the financing in place." But what they were looking for, this is right, isn't it, was a global solution to the shipyard's problems? Do you remember that? A. No. How can I remember something about somebody else's notes, which is not Barents' notes? Q. Well, I'm asking you whether you remember that from the meeting. Don't -- I don't have anything better to offer you. You didn't look to check if you had got any notes; so I can't offer you your own notes. What I'm asking you is: do you have any recollection of these things from the meeting? And I'm asking you to cast your mind back and see if you remember a discussion where the buyer said that they were going to fulfil the contract, they were ready to pay and had the financing in place, but they wanted a global solution? A. I said before, these are -- these were recurrent issues so this is not adding any value to. You know, we – Q. Do you have any recollection of that or not? A. Any recollection of somebody else's notes? I cannot say – Q. Do you have any recollection of those things being said at the meeting or not? A. No. No, because these are not my notes. MR JUSTICE HENSHAW: You're being asked about your recollection, just to be clear. A. My recollection speaks about the questions we made and the answers we received. That was all, my Lord. And this is what I'm saying in my statement. It's nothing else.”
“Payment of the Second Additional Payment (EUR 5,0 million on each of the Vessels) was scheduled to take place on23 September 2019 . Due to the fact that the Buyer during the weekend up until23 September 2019 and23 September 2019 , gradually received information about the challenges the Builder was facing, the Buyer decided to halt the payment of the Second Additional Payment, pending more clarification of the situation involving the yard and the order book of Barreras. Consequently, payment of the Second Additional Payment has not been made as of today. However, the Buyer is ready to transfer the payment to the Builder as soon as a satisfactory solution is reached and signed by all relevant parties.”
“Havila Kystruten AS is of the opinion that, at this stage and in the current yard circumstances, the confirmation already provided is satisfactory evidence for the financing of the Havila Project, and that was also accepted by the parties in the Addendum No 9 to the shipbuilding contracts for NB 1710 and 1711, respectively ("Contracts"). For various reasons Havila Kystruten AS is not willing to once more approach GTLK in this matter until there is more visibility on the projects, in the terms we are now discussing. However, rest assured that we will be working in parallel to our negotiations with the bank to make the necessary adjustments to the finance documentation – as we assume you will be doing the same with your financiers and insurance/refund issuers – so that drawdown is made on closing. As you will know, the restart of the project as being discussed between the parties for the time being, will require a number of conditions precedent to be fulfilled. With reference thereto Havila Kystruten AS is fully aware of that effective contracts will require a new addendum to the Contracts, and that agreed conditions have to be fulfilled – including but not limited to payments to be provided by Havila Kystruten AS. Consequently Havila Kystruten AS is prepared to provide and updated reconfirmation of the financing - including the pre-and post-delivery financing (as already provided) as a condition precedent to be fulfilled. Further - as far as concerns fulfilment of conditions precedent under the facility agreement with GTLK, we expect the full cooperation from Barreras to the extent required, so that drawing under the facility agreement is not being delayed due to conditions precedent to be fulfilled by Barreras or its financiers (for example, acknowledgement of notices of assignment). Finally - whilst we appreciate your concern, we are strong on that the confirmation already is in place and only need an updated reconfirmation.”
“It is very hard for us to understand Havila’s continuous reluctancy to provide supporting evidence of its financing. We would recall that the Buyer’s delay with its financing and the failure to make agreed payments has already caused serious constraints to the projects. You have also had the opportunity to hear that all counterparties relevant to the financing structure of Havila’s NB vessels state the need to have appropriate confirmation as soon as possible. As you know, it is a fairly standard procedure for banks to issue commitment letters and confirmation of availability of funds letters. So, we do not understand that your insistence that a termsheet (or a simple letter from the Buyer) is equivalent to a formal commitment or to a confirmation of availability of funds letter when it is obviously not equivalent. Precisely because of the yard´s situation we, and as clearly stated in the 7th of November call, all other parties involved in the financing of Havila's vessels (tax lease and insurance bonds/refund guarantee providers), need confirmation of financing. As previously stated this can include condition precedents such as the assignment to GTLK that you mention in your email. …”
“We hope that this be a clear signal of Havila’s willingness and determination to arrive to an agreement for the re-starting of the [Vessels]. The fact is that there has been very little progress with you over the last few weeks and this gives particular cause for concern as to your commitment and intentions. We hope fervently that we are wrong and we look forward to further discuss and meeting asap.”
“1. By this letter we give you notice that the SBCs are terminated pursuant to Addendum No. 7 Clause 2.5.1 on the basis that: a) You could not and did not provide confirmation of the pre and post delivery financing of the Vessel by30 April 2019 or thereafter by a written statement from a bank or financial institution set out in Addendum No. 7 Clause 2.4.1 b) We informed you in writing on21 June 2019 of our intention to terminate and/or cancel the SBCs on that basis within 14 days written notice. c) We physically met following our21 June 2019 notice and negotiated in good faith alternative arrangements to avoid termination. d) We have concluded that there is no other alternative financial arrangement to be provided by you to avoid termination and/or cancellation of the SBCs. 2. You said in your letter dated18 October 2019 your position is that Addendum No. 9 did not enter into force or effect. If, however, Addendum No. 9 has entered into force or effect, we have an additional (or alternative) right to terminate the SBCs as a result of your failure to pay the Second Additional Payment as defined in Addendum No. 9. Further or alternatively, and without prejudice to the above, and only if the SBCs have not been terminated as above, we give you notice that the SBCs are terminated pursuant to Addendum No. 9 Clauses 3.3 and 9.4 on the basis of your failure to pay the Second Additional Payment by the agreed due date or at all. 3. Further or alternatively, and without prejudice to the above, and only if the SBCs have not been terminated as above, we give you notice that the SBCs are terminated pursuant to the agreement between us that the sum of EUR 5,000,000 would be paid within one banking day of18 September 2019 or thereafter and you have failed to pay that sum by the agreed date or at all. 4. Further or alternatively, and without prejudice to the above, and only if the SBCs have not been terminated as above, we give you notice that we accept the repudiatory and/or renunciatory breach of the SBCs arising as result of the totality of your conduct as terminating the SBCs. All our rights under the SBCs and at law are fully reserved.” a) You could not and did not provide confirmation of the pre and post delivery financing of the Vessel by30 April 2019 or thereafter by a written statement from a bank or financial institution set out in Addendum No. 7 Clause 2.4.1 b) We informed you in writing on21 June 2019 of our intention to terminate and/or cancel the SBCs on that basis within 14 days written notice. c) We physically met following our21 June 2019 notice and negotiated in good faith alternative arrangements to avoid termination. d) We have concluded that there is no other alternative financial arrangement to be provided by you to avoid termination and/or cancellation of the SBCs. All our rights under the SBCs and at law are fully reserved.”
“We therefore hereby (i) accept your continuing repudiatory and/or renunciatory breaches of the Contracts as discharging us from any responsibility to perform the Contracts; and/or (ii) cancel the Contracts in reliance on the above and in particular on your application for your judicial dissolution (under Article XII.3 of the Contracts) and the fact that it is obvious that the Vessels, construction of which you have now abandoned for well over 7 months, will never be completed within 180 days of their Delivery Dates (under Article IV.1(d)).”
“By the nature of things, where negotiations are difficult, the parties’ positions, with each passing letter are changing and until the final agreement, though converging, still different. It is only the final document which records a consensus. If the previous documents use different expressions how does construction of those expressions, itself a doubtful process, help on the construction of the contractual words?”
“The negotiations of a contract can often be a compromise. it is dangerous to make the assumption that one party intended to have something supplied or provided for by the contract, or that the other party intended to have something else supplied or provided by the contract. Contracts are negotiated and ultimately each may think that he has what he wishes, but it is for the Court to interpret the language of the contract.”
“ …the Buyer acknowledge that the Builder needs evidence of the Buyer’s pre and post-delivery financing in order to be able to provide the Insurance Bond, the Cut-Through Agreement, the Bank Guarantees and the CESCE Counter Guarantee, except for the Amended 1st Instalment Bank Guarantee and likewise the 2nd Insurance, Bond which is going to be issued and delivered to the Buyer on the Closing Day …”
“Pursuant hereto the Parties have agreed that the Buyer’s alternative pre and post-delivery financing of the Vessel shall be confirmed to the Builder no later than on the30 April 2019 . The confirmation shall be provided by a written, committed statement from the bank/financing institution financing the Buyer (pre and post-delivery financing), to be submitted to the Builder.”
“[i] The Buyer has provided the Builder with information about the Buyer’s present pre and post-delivery financing of the Vessel to be arranged by BoComm Financial Leasing Co. Ltd (“BoComm Financing”). [ii] The Parties acknowledge that the implementation of the BoComm Financing into the Tax Lease (such Tax Lease to be provided by the Builder) is complicated and shall take time to implement it due to circumstances not attributable to any of the Parties. Consequently, the Buyer has informed the Builder that the Buyer will obtain alternative financing for the pre and post-delivery financing of the Vessel, and that has been accepted by the Builder.”
“… if the Buyer cannot confirm and provide evidence that the pre and post-delivery financing of the Vessel is in place at30 April 2019 (at the latest) by a written statement from a bank or financial institution as set out in clause 2.4.1 of the Addendum No 7, the Builder shall be entitled to terminate and/or cancel the Contract according to the terms and provisions of the Contract, provided (i) the Buyer is being informed in writing about the Builder´s intention to terminate and/or cancel the Contract for such reasons with fourteen (14) days written notice, (ii) the Buyer and the Builder have been meeting physically subsequent to the Buyer’s receipt of such notice in order to consider and negotiate in good faith alternative arrangement in order to avoid termination and/or cancellation of the Contract and (iii) the Parties after fourteen (14) days negotiation have concluded that there is no other alternative financial arrangement to be provided by the Buyer in order to avoid termination and/or cancellation of the Contract”
“where with knowledge of the relevant facts a party acts in a manner which is only consistent with his having chosen one of the two alternative and inconsistent courses of action then open to him… he is held to have made his election accordingly. It can be communicated to the other party by words or conduct…in clear and unequivocal terms…Once an election is made, however, it is final and binding…”
“[T]he Court should not adopt an unduly technical approach to deciding whether the injured party has affirmed the contract and should not be willing to hold that the contract has been affirmed without very clear evidence that the injured party has indeed chosen to go on with the contract notwithstanding the other party’s repudiation. In my view, the Court should generally be slow to accept that the injured party has committed himself irrevocably to continuing with the contract in the knowledge that if, without finally committing himself, the injured party has made an unequivocal statement of some kind on which the party in repudiation has relied, the doctrine of estoppel is likely to prevent any injustice being done. Considerations of this kind are perhaps most likely to arise when the injured party’s initial response to the renunciation of the contract has been to call on the other to change his mind, accept his obligations and perform the contract. That is often the most natural response and one which, in my view, the Court should do nothing to discourage. It would be highly unsatisfactory if, by responding in that way, the injured party were to put himself at risk of being held to have irrevocably affirmed the contract whatever the other’s reaction might be, and in my judgment he does not do so. The law does not require an injured party to snatch at a repudiation and he does not automatically lose his right to treat the contract as discharged merely by calling on the other to reconsider his position and recognize his obligations.”
“It does not follow from this analysis that the innocent party may in all cases change his mind after affirming the contract. If, after he had affirmed it, the repudiating party's conduct suggested that he proposed to perform after all, then the previous party's repudiation is spent. It has no further legal significance. If on the other hand, the repudiating party persists in his refusal to perform, the innocent party may later treat the contract as being at an end. The correct analysis in this case is not that the innocent party is terminating on account of the original repudiation and going back on his election to affirm. It is that he is treating the contract as being at an end on account of the continuing repudiation reflected in the other party’s behaviour after the affirmation. (Safeway § 66) following which the judge below continued: “Once the innocent party has affirmed, he must go on performing. He must then be able to point to behaviour that amounts to a repudiation after the affirmation either by way of some fresh conduct amounting to repudiation or by way of the continuing refusal to perform amounting to repudiation.”
“[a provision] under which the coming into existence of (for example) an obligation, or the duty or further duty to perform an obligation, is dependent upon the fulfilment of the specified condition”: see The Good Luck[1992] 1 AC 233 (Lord Goff). A “condition subsequent” is “a condition of the agreement’s continuing; and if it is not performed the agreement comes to an end”: Wickman Machine Tool Sales Ltd v Schuler (L) AG[1972] 1 WLR 840 at 859 (Stephenson LJ). Lewison on “The Interpretation of Contracts”, 7th edn § 16.03 cites the statement of Sackar J in Yule v Smith [2013] NSWSC 209 at §§ 25 and 26 that: “As mentioned, where a contract contains a condition precedent, the non-fulfilment of the condition precedent results in either there being no contract (i.e. a condition precedent to contract), or alternatively no obligation to perform (i.e. condition precedent to performance). Which of the two actually occurs in a given case depends on the intention of the parties … The expression ‘condition subsequent’ refers to an event the occurrence of which terminates either an existing contractual relationship, or the obligation of one or more parties to perform. However, as noted by various text writers, the distinction implied by the words ‘precedent’ and ‘subsequent’ is largely semantic, as most conditions precedent can be expressed as conditions subsequent (and vice versa).”
“3. Effect of Default: (a) If any default by the BUYER occurs as provided hereinbefore, the Delivery Date shall be automatically postponed for a period of continuance of such default by the BUYER. (b) If any default by the BUYER continues for a period of fifteen (15) days, the BUILDER may, at its option, rescind this Contract by giving notice of such effect to the BUYER by telefax. Upon receipt by the BUYER of such notice of rescission, this Contract shall forthwith become null and void and any of the BUYER’s supplies shall become the sole property of the BUILDER. In the event of such rescission of this Contract, the BUILDER shall be entitled to retain any Installment or Installments theretofore paid by the BUYER to the BUILDER on account of this Contract which shall be subject to Paragraph 4 of this Article.”
“… the SAJ Form standard wording specifically provides that the contract shall become “null and void” upon the builder’s rescission. However, as previously indicated, this language cannot be meant to have literal effect, and it seems unlikely in practice that the buyer would succeed in contending that upon rescission it is excused by reason of this language from previously accrued obligations to pay instalments of the contract price.”
“3.2 The Buyer shall pay to the Builder, an additional cash amount of EUR 5,000,000 (Euros five million 00/100) one (1) Banking Day after the Insurance Bond for this payment has issued and delivered to Watson Farley & Williams in Madrid ("Second Additional Payment” and “Second Additional Payment Date”, respectively), see clause 3.3 of the Addendum No. 9. Upon the Buyer's payment of the Second Additional Payment, the Builder undertakes to "re-start" the construction and building of the Vessel immediately subsequent to two (2) Business Days after the Buyer's payment to the Builder of the Second Additional Payment. In this respect “re-start” of the construction and building of the Vessel shall be regular and as considered to be normal for the shipbuilding industry for such a vessel under construction as NB 1710, in the current circumstances. 3.3 [i] Provided that the board approvals are being granted, the Second Additional Payment shall be made against Insurance Bonds as issued for the First Additional Payment (see Appendix 1 hereto) (with logical amendments), however, without the obligation to provide a Cut-Through Agreement if the final financing cannot be drawn by the Buyer as of the Second Additional Payment Date. The Insurance Bond shall be assignable to the Lender and / or security trustee under the Buyer's pre and post- delivery financing of the Vessel. [ii] The original copy of the Insurance Bond for the Second Additional Payment shall be delivered to Watson Farley & Williams in Madrid not later than on18th September 2019 . [iii] If the Builder cannot provide and hand over the Insurance Bond as security for the Second Additional Payment on the Second Additional Payment Date, the payment of the Second Additional Payment shall be postponed correspondingly. If the payment of the Second Additional Payment is not being made on the Second Additional Payment Date (as extended according to this clause 3.3 of the Addendum No 9) the provisions of clause 9.3 [sic. 9.4] of the Addendum No 9 concerning the cancellation of the Current Contract, shall apply.”
“… Pursuant hereto – and during the period commencing by signing of this Addendum up till and including30th September 2019 (the "Target Date") the Builder shall not exercise any right of cancelation according to the Current Contract, except if (i) the Buyer fails to make the Second Additional Payment, or (ii) the Buyer fails to make the payment of the 3rd Instalment pursuant to Addendum No 9 other than for a cause attributable to the Builder, Banca March or the insurance bond issuers or refund guarantors, and by default in any of these two cases the Builder shall have the right to cancel the Current Contract by written notice to the Buyer as set out in the Current Contract. Notwithstanding the above, if this Addendum is not effective on 30thSeptember 2019 as per clause l2 below, the Builder shall from that date be entitled to exercise any right of cancellation to which it would be entitled before signing this Addendum No. 9, as if this Addendum has never been entered into.”
“If one or more of the conditions are set out in clause 12.2 to and including 12.6 of this Addendum 9 is not being fulfilled within the time limit as set out therein, then this Addendum no 9 becomes null and void and shall be deemed to be as non-written.”
“On discharge of a contract of this kind a buyer who has paid the whole or part of the price in advance is entitled, in the absence of any agreement to the contrary, to recover what he has paid by reason of a total failure of consideration. He therefore has a right to recover in restitution any payments he has made in respect of the price, a right which is quite distinct from any right he may have (if he is the injured party) to recover damages for the loss of his bargain. In the present case the parties made specific provision for the repayment of instalments and Gearbulk could not, of course, recover both under the contract and in restitution; to do so would result in double recovery. In fact, however, Gearbulk is not seeking to recover the advance payments since it has already done so. There is no inherent inconsistency, however, in recovering instalments of the price under article 10 and recovering damages for loss of bargain at common law.”
“If he has paid money under the contract to the party in default, he will be entitled to recover it by an action for money had and received, but only if the consideration for the payment has totally failed.” (Chitty on Contracts (30th edn) §24-050). I take this to be established law. It seems to me that it would undermine the requirement that there be total failure of consideration before the innocent party could recover his money, if the same result could be achieved in every case (save where it was shown that he had made a bad bargain) simply by claiming the money as wasted expenditure instead. I do not think this can be right. 131. As Mr Haque points out, McGregor deals with the principle of reliance loss under the rubric: “An alternative measure: recovery for expenses rendered futile by the breach”
“In Howard-Jones v Tate[2011] EWCA Civ 1330 , [2012] 1 P. & C.R. 11 it appears that a claim seeking reimbursement of the purchaser’s payment and expenses, made after he had terminated the contract because of the vendor’s non-performance of a post-completion obligation to install water and power, was denied on the basis that there had not been a total failure of consideration; but, with respect, it is hard to see why recovery by way of damages should be refused so long as (a) any benefits received by the purchaser before termination are taken into account; and (b) the purchaser was not put into a better position than he would have been in if the contract had been performed. The measure of damages awarded (the cost of making good the vendor’s obligations to install water and power) seems appropriate only on the assumption that, despite having the right to terminate the contract, the purchaser had not done so.”
“If it can be established beyond any reasonable doubt that the Vessel will be delayed for more than 180 days as per paragraph (b) above, or be delayed for more than 270 days as per paragraph (c) above, the Buyer shall have a right forthwith to cancel the Contract.”
“If proceedings are commenced by or against the Buyer or Builder for winding up, dissolution or reorganisation (except in case of merger or solvent internal reorganizations) or for the appointment of a receiver, trustee or similar officer, or if bankruptcy is opened, the party who is not subject to such proceedings shall have the right to cancel this Contract.”
“Article 8 Supplementary nature of the Civil Procedure Law The provisions of the Law of Civil Procedure shall apply additionally to the voluntary jurisdiction files in everything not regulated by this Law.” “Article 14 Initiation of proceedings 1. The proceedings shall be initiated ex officio, at the request of the Director of Public Prosecutions or on application made by an authorised person, which shall include the details and circumstances identifying the applicant, with the indication of an address for the purpose of notifications. It shall then set out clearly and precisely what is requested, together with a statement of the facts and legal grounds on which it is based. It shall also be accompanied, where appropriate, by the documents and opinions that the applicant considers to be of interest to the proceedings, and as many copies as there are interested parties. 2. The application shall include the identification details and circumstances of the persons who may be interested in the proceedings, as well as the address(es) at which they may be summoned or any other information that may enable them to be identified. 3. If the intervention of a Solicitor and Court Agent is not required by law, the Judicial Office will provide the interested party with a standard form to make the application, in which case it is not necessary to specify the legal grounds for the application. The application may be submitted by any means, including those provided for in the regulations on citizens' electronic access to the Administration of Justice.” “Article 16 Ex officio assessment of lack of jurisdiction and other defects or omissions 1. Once the application to initiate proceedings has been lodged, the clerk of the court shall examine of his own motion whether the rules of objective and territorial jurisdiction have been complied with. … 4. The Court Clerk shall also examine the existence of possible defects or omissions in the applications submitted and shall, if necessary, give a period of five days in which to remedy them. If this is not carried out within the period indicated, it shall consider the application as not having been submitted and shall archive the proceedings in those files that fall within its competence. Otherwise, it shall be reported to the judge, who shall decide as appropriate. Article 17 Admissibility of the application and summoning of interested parties 1. The clerk of the court shall decide on the application and, if he considers that it is not admissible, he shall issue a decree closing the file or shall inform the judge, when he is the competent judge, so that he may decide what is appropriate.” “Article 125 Scope of application The procedure laid down in this Chapter shall apply to the judicial dissolution of a company in cases where it is required by law. Article 126 Competition, legitimacy and application 1. Jurisdiction to proceed with the judicial dissolution of a company shall lie with the Commercial Court of the company’s registered office. 2. Directors, members and any interested party are entitled to initiate the judicial dissolution of the company. 3. The intervention of a lawyer and a solicitor shall be mandatory in the processing of these files. Article 127 Processing 1. The proceedings shall be initiated by means of a document stating that the legal requirements for the judicial dissolution of the company have been met, accompanied by the documents on which the application is based. When the petition is submitted by a legal entity other than the directors, it must be proven that the request for dissolution has been notified to the company. 2. The Court Secretary will serve notice of the brief to the directors, if they have not initiated the file, and will call an appearance summoning them and the other interested parties who, according to the law, must intervene in the file. Article 128 Resolution 1. The judge shall decide the case by way of an order within five days of the end of the hearing. 2. In the event that the judge declares the company dissolved, the order shall include the appointment of the persons who are to act as liquidators, and a copy of the order shall be sent to the relevant Commercial Register for registration.” “Article 143 Effects of admission The presentation with subsequent admission of the request for conciliation shall interrupt the prescription, both acquisitive and extinctive, in the terms and with the effects established by law, from the moment of its presentation. The limitation period shall start to run again from the date of the decree of the Court Clerk or the order of the Justice of the Peace terminating the case.”
“Article 19 Litigants’ right of disposal. Transaction and Suspension … 4. Likewise, the parties may request the suspension of the proceedings, which shall be agreed by the Legal Adviser of the Administration of Justice by means of a decree, provided that it does not harm the general interest or third parties and that the period of suspension does not exceed sixty days.” “Article 179 Procedural momentum and adjournment of proceedings by agreement of the parties … 2. The course of the proceedings may be suspended in accordance with the provisions of Article 19(4) of this Act and shall be resumed at the request of either party. If, on expiry of the period for which the stay was ordered, no one requests, within the following five days, that the proceedings be resumed, the Legal Secretary for the Administration of Justice shall order the case files to be provisionally filed and they shall remain in that situation until such time as the continuation of the proceedings is requested or the instance lapses.” “Article 410 Start of lis pendens The lis pendens, with all its procedural effects, arises from the filing of the action, if it is subsequently admitted.”
“The trial will begin with a claim, in which, having recorded in accordance with the provisions of Article 155 the data and identification details of the claimant and the defendant and the domicile or residence at which they can be summoned, the facts and the grounds of law will be set out numbered and separated, and what is requested will be clearly and precisely set forth.”
“The distinction between the two decisions is of some interest from the point of view of the effects of lis pendens (such as, for example, the interruption of the statute of limitations), since, as a general rule, all the effects of lis pendens are produced as soon as the action is brought, provided that it is subsequently admitted[FN]. Thus, the order of inadmissibility of the claim excludes in any case any of the effects of lis pendens, because the proceedings never started. The dismissal order, on the other hand, assumes that there was a pending proceeding, since the claim was admitted and, therefore, the effects of lis pendens will have been produced. The abstention decision may be issued before the admission of the claim or once the proceedings are pending, hence, depending on the case, the effects of lis pendens will or will not be produced. Finally, the decision to reject the application does not raise any question of lis pendens, because it is not final: either an order of inadmissibility follows, or the defect is cured and the proceedings continue. [FN] This is the case for all the procedural effects of lis pendens, as provided for in Article 410 LEC. However, some of the material effects of lis pendens do not occur until after the claim has been filed and then admitted (this is the case, for example, of the claim of a claim and its litigious status, since Article 1535 CC postpones this effect of lis pendens until the time of the answer to the claim).”
“FACTUAL BACKGROUND … ON 26.11.2019, HIJOS DE BARRERAS SA, requested, under the Voluntary Jurisdiction Law in force, the judicial dissolution thereof. On 03.02.2020, the request for approval of the restructuring agreement that gave rise to the order of 17.02.2020, published in the BOE and bankruptcy public registry, was sent to this court. In the aforementioned request, it is requested, by means of Addendum 1, that once the restructuring agreement has been approved, the request for judicial dissolution of HIJOS DE BARRERAS S.A. be rejected. LEGAL GROUNDS … Once the restructuring agreement has been homologated, the judicial dissolution proceeding has become devoid of subject matter and is therefore inadmissible. PROVISIONS AGREEMENT: The inadmissibility of the voluntary jurisdiction proceeding requested by the members of the board of directors of HIJOS DE BARRERAS S.A. regarding the judicial dissolution of this entity due to lack of purpose. The applicant's attorney in voluntary jurisdiction shall be notified of the document herein, against which an appeal for review may be filed, subject to a deposit of 25 Euros. I agree and sign it. I attest.”
“The Buyer expresses the sincere hope that the Builder will come to its senses and will revoke its cancellation so that both parties can proceed with the SBCs. If and to the extent the Builder does so, the Buyer, for its part, will not seek to rely on the Builder’s application for its dissolution to the Spanish courts in order to cancel the SBCs itself, provided of course, that such application is withdrawn or otherwise that no such dissolution proceeds. The Buyer therefore invites the Builder to reflect thoroughly and carefully upon its purported cancellation of the SBCs, which is entirely without merit and repudiatory and to confirm to the Buyer or to us within a period of 7 calendar days that the cancellation is revoked. For this purpose, and pending the Builder’s response. The Buyer affirms the SBCs. All the Buyer’s remaining rights under the SBCs, and generally, are strictly reserved.”
“To conclude, we reject all of the allegations and false assertions made in your letter. The Buyer continues to affirm the SBCs and again calls on the Builder to revoke its purported cancellations. We understand that representatives of the parties will be meeting in Amsterdam tomorrow and we express the since hope that good sense will finally prevail and that the project will get back on track.”
“1. The Insurer hereunder irrevocably undertakes in the event that (a) one of the following events occurs: (i) termination of the SBC due to the default of the Policyholder under Article XII (1) of the SBC or termination of the SBC under its applicable law (as long as the termination of the SBC under its applicable law raises the obligation of the Policyholder to return the Relevant Instalments plus interest accrued thereon at the rate set out in the SBC); and/or (ii) termination of the SBC resolved by the court decision in accordance with the provisions of Articles 61 and 62 of the Spanish Bankruptcy Law (Ley Concursal) following the declaration of insolvency proceedings of the Policyholder; and (b) provided that in both cases (i) and (ii) the Policyholder fails, within the period of 15 days, to reimburse the Insured an amount equal to the Relevant Instalments plus interest accrued thereon at the rate set out in the SBC (the occurrence of the events mentioned in paragraphs (a) and (b) of this paragraph, hereinafter a or the “Loss”), to pay the Insured, as monetary compensation for the damage suffered as a result of the occurrence of the Loss, an amount equal to the amount that the Policyholder has not reimbursed in respect of the Relevant Instalments and other amounts in respect thereof which the Policyholder was obliged to reimburse pursuant to Article XII (1) paragraph 3 of the SBC up to Euro eleven million, three hundred and eighty three thousand, three hundred and forty two (€11,383,342 ) (the total amount of Relevant Instalments and the rest of the amounts which the Policyholder is obliged to pay pursuant to Article XII (1) paragraph 3 of the SBC in respect of the Relevant Instalments, up to the referred amount, the “Total Insured Amount”), provided always that the Insurer has not been able to comply with the obligations of the Policyholder to deliver the Vessel in time and form in the event that the Insurer has been allowed by the Insured in writing to do that instead of paying the amount due in respect of the Loss in the terms of Clause 3 below. For clarification purposes, in the event that the dispute refers only to a part of the corresponding Relevant Instalments owed by the Policyholder, the uncontroversial or non-disputed part shall be paid by the Insurer in accordance with this Insurance Bond. For further clarification purposes, any amount received by the Insured from Banco de Sabadell, S.A (“Sabadell”) pursuant to a financial guarantee issued by Sabadell in respect of the Instalment paid under Article III. 3(a) (the “Financial Guarantee”) shall be considered, for the purposes of this Clause, as paid by the Policyholder and, as such, shall reduce the obligations of the Insurer accordingly. 2. The amounts guaranteed by this Insurance Bond shall be paid in EUROS within twenty (20) Business Days from the date on which the Insured has supplied the necessary documents in accordance with the provisions of Clause 4 below for making a claim and such payment shall be made to the Insured’s account at DNB Bank ASA number NO0712506214376 or such other account which is notified in writing by the Insured to the Insurer at least 15 days in advance of such payment being payable. In this Insurance Bond, Business Day means any day on which banks of Madrid (Spain), Vigo (Spain) and Oslo (Norway) operate, except for Saturdays, Sundays and statutory holidays in Madrid (Spain), Vigo (Spain) or Oslo (Norway). … 4. Following a Loss, in order to be paid pursuant to the cover established in this Insurance Bond, the Insured must submit to the Insurer a claim stating that the Loss has occurred (including the express declaration that it has not received the amount that it is entitled to receive as a consequence of the occurrence of any of the events described in section (a) of Clause 1 of this Insurance Bond) and accompanied by any of the following documents: (i) a written confirmation by the Policyholder (it being understood that in the case of cancellation pursuant to Clause 1(a)(ii), the Policyholder might act through an insolvency administrator or insolvency judge) that the Policyholder will not be able to complete the construction of the Vessel in accordance with the SBC within the agreed term in breach of its obligations under the SBC and certifying that the SBC has been terminated as a result of the occurrence of any of the events described in subsection (a) of Clause 1 of this Insurance Bond without the Policyholder having paid the amounts due to the Insured as a result of such termination; or (ii) the Insured’s confirmation that, within 20 Business Days from the notification of the cancellation of the SBC as a consequence of the occurrence of any of the events described in paragraph (a) of Clause 1 of this Insurance Bond, the Policyholder has not made the notification provided for in Clause 4 paragraph (i) above, nor has it raised any objection to such cancellation commencing legal proceedings in accordance with Article XIX of the SBC (and the Insured has not been notified in writing by the Insurer, the Policyholder or any other third party that a dispute on such cancellation has been submitted to the Policyholder’s bankruptcy court); or (iii) notification from the Insured that (a) the cancellation of the SBC as a consequence of the occurrence of any of the cases described in section (a) of Clause 1 of this Insurance Bond has been rejected and submitted to the jurisdiction of the courts according to Article XIX of the SBC (or, if applicable, has been submitted to the Policyholder’s bankruptcy court, if the dispute were to be settled before it), and that in the corresponding final and non-appealable decision duly certified by a court certifying officer, or judicial decision of the bankruptcy court, a copy of which must be attached to said notification, it is stated that the Insured has validity terminated the SBC as a consequence of the occurrence of any of the cases described in section (a) of Clause 1 of this Insurance Bond and it is, therefore, entitled to obtain the return of the Instalments (including, inter alia, the Relevant Instalments) paid (together with the other amounts payable pursuant to Article XII(1) paragraph 3 of the SBC, if applicable) and (b) that such amount has not been reimbursed by the Policyholder.” (i) a written confirmation by the Policyholder (it being understood that in the case of cancellation pursuant to Clause 1(a)(ii), the Policyholder might act through an insolvency administrator or insolvency judge) that the Policyholder will not be able to complete the construction of the Vessel in accordance with the SBC within the agreed term in breach of its obligations under the SBC and certifying that the SBC has been terminated as a result of the occurrence of any of the events described in subsection (a) of Clause 1 of this Insurance Bond without the Policyholder having paid the amounts due to the Insured as a result of such termination; or (ii) the Insured’s confirmation that, within 20 Business Days from the notification of the cancellation of the SBC as a consequence of the occurrence of any of the events described in paragraph (a) of Clause 1 of this Insurance Bond, the Policyholder has not made the notification provided for in Clause 4 paragraph (i) above, nor has it raised any objection to such cancellation commencing legal proceedings in accordance with Article XIX of the SBC (and the Insured has not been notified in writing by the Insurer, the Policyholder or any other third party that a dispute on such cancellation has been submitted to the Policyholder’s bankruptcy court); or (iii) notification from the Insured that (a) the cancellation of the SBC as a consequence of the occurrence of any of the cases described in section (a) of Clause 1 of this Insurance Bond has been rejected and submitted to the jurisdiction of the courts according to Article XIX of the SBC (or, if applicable, has been submitted to the Policyholder’s bankruptcy court, if the dispute were to be settled before it), and that in the corresponding final and non-appealable decision duly certified by a court certifying officer, or judicial decision of the bankruptcy court, a copy of which must be attached to said notification, it is stated that the Insured has validity terminated the SBC as a consequence of the occurrence of any of the cases described in section (a) of Clause 1 of this Insurance Bond and it is, therefore, entitled to obtain the return of the Instalments (including, inter alia, the Relevant Instalments) paid (together with the other amounts payable pursuant to Article XII(1) paragraph 3 of the SBC, if applicable) and (b) that such amount has not been reimbursed by the Policyholder.”
“The Insurer hereunder irrevocably undertakes in the event that … one of the following events occurs: (i) termination of the SBC due to the default of the Policyholder under Article XII(1) of the SBC or termination of the SBC under its applicable law (as long as the termination of the SBC under its applicable law raises the obligation of the Policyholder to return the Relevant Instalments plus interest accrued thereon at the rate set out in the SBC) …”
“143. The same conduct may be such as to give rise to a contractual right to terminate and a common law entitlement to accept a repudiatory breach. This will typically be so if (i) the guilty party has failed to make the payments stipulated by the contract, (ii) that failure either amounts to a repudiation or is, by the terms of the contract, to be treated as such, and (iii) there is a contractual right to terminate which is applicable to the circumstances giving rise to the breach. In such a case the innocent party can exercise either his contractual or his common law right of termination. Prima facie he can rely on both. He is not disentitled to rely on the latter on the ground that recourse to the former constitutes an affirmation of the contract since in both cases he is electing to terminate the contract for the future (ie to bring to an end the primary obligations of the parties remaining unperformed) in accordance with rights that are either given to him expressly by contract or arise in his favour by implication of law. If he can rely on both there is no reason in principle why, if he terminates the con- tract without stating the basis on which he does so, he cannot be treated as doing so under any clause which entitles him to do so and in accordance with his rights at common law. ‘‘Termination’’ is capable of meaning both a termination pursuant to a contractual clause and the acceptance of a repudiation: Aktieselskabet Dampskibsselskabet Svendborg v Mobil North Sea Ltd[2001] 2 Lloyd’s Rep 127 . Even if he refers to a particular clause upon which he relies, that would not inevitably mean that he was only relying on that clause. If that were so an innocent party who, in the face of a repudiatory breach, terminated the contract by reference to a clause which was in fact inapplicable, might, on that account, find himself disentitled to terminate at all. 144. The fact that service of a contractual notice of termination is not inconsistent with the acceptance of a repudiation does not, however, mean that in all cases such a notice amounts to such an acceptance. If the notice makes explicit reference to a particular contractual clause, and nothing else, that may, in context, show that the giver of the notice was not intending to accept the repudiation and was only relying on the contractual clause; for instance if the claim made under the notice of termination is inconsistent with, and not simply less than, that which arises on acceptance of a repudiation: United Dominions Trust (Commercial) Ltd v Ennis[1968] 1 QB 54 , 65, 68. In the present case markedly different consequences would arise according to whether or not there was a termination under clause 14.4 or an acceptance of a repudiation. … In those circumstances it should take effect in, and only in accordance with its express terms, namely as a determination under clause 14.4.”
“44. It must be borne in mind that all that is required for acceptance of a repudiation at common law is for the injured party to communicate clearly and unequivocally his intention to treat the contract as discharged: see Vitol SA v Norelf Ltd[1996] 2 Lloyd’s Rep 225 ;[1996] AC 800 , pages 810G to 811B per Lord Steyn. If the contract and the general law provide the injured party with alternative rights which have different consequences, as was held to be the case in Dalkia Utilities v Celtech, he will necessarily have to elect between them and the precise terms in which he informs the other party of his decision will be significant, but where the contract provides a right to terminate which corresponds to a right under the general law (because the breach goes to the root of the contract or the parties have agreed that it should be treated as doing so) no election is necessary. In such cases it is sufficient for the injured party simply to make it clear that he is treating the contract as discharged: see Dalkia Utilities v Celtech, para 143 per Christopher Clarke J. If he gives a bad reason for doing so, his action is nonetheless effective if the circumstances support it. ... 45. In the present case the parties accept, and indeed the arbitrator has found, that the breaches on the part of the yard which entitled Gearbulk to terminate the contracts were in each case sufficient to amount to a repudiation. … in its letters of7 November 2003 and4 August 2004 Gearbulk purported to terminate the contract pursuant to article 10.1(b) and (c) and not under the general law, but each of the letters made it clear that it was treating the contract as discharged and in those circumstances each was sufficient to amount to an acceptance of the yard’s repudiation. In its letter of30 November 2004 Gearbulk sought to rely on both. Mr Dunning said that letter was equivocal as between reliance on the terms of the contract and reliance on the general law. Perhaps it was, but it was quite unequivocal as to Gearbulk’s intention to treat the contract as discharged and that was all that was necessary.”
“The test whether an event has this effect or not has been stated in a number of metaphors all of which I think amount to the same thing: does the occurrence of the event deprive the party who has further undertakings still to perform of substantially the whole benefit which it was the intention of the parties as expressed in the contract that he should obtain as the consideration for performing those undertakings?”
“It is expressly stated that no further direct claim nor any claim for compensation of any consequential losses and/or damages suffered by the Builder and/or any third party, can be addressed or submitted to the Buyer if termination and/or cancellation of the Contract is being exercised by the Builder according to clause 2.5 of the Addendum No 7.”
“The quantum of the Yard’s claim for wasted expenses, pleaded at paragraph 72 of its Particulars of Claim in Claim No CL-2020-000559 (the “Wasted Expenses Claim”), is to be determined after trial and judgment has been given on all other issues of liability and quantum in Claim No CL-2020-000559 and CL-2020-000246. All issues of further disclosure, security for costs, and directions for trial of the quantum of the Wasted Expenses Claim are to be dealt with after judgment has been handed down in the main hearing in July 2022.”