“Each [SPV] shall procure delivery to the Agent [i.e. BLB] of: … a certified true copy of each Final Acceptance Certificate within ten (10) Business Days of issue.”
“to procure for the Employer a modern, functional, well-designed solar power plant capable of continuous, efficient and reliable operation with minimum maintenance. The equipment supplied shall be of proven, robust and reliable design incorporating protective systems and devices with adequate factors of safety and maintainability built-in.”
“4.1 Contractor’s General Works Obligations The Contractor shall design, execute, install, test, Commission and complete the Works in accordance with this Contract, and shall remedy any defects in the Works, in each case: a) in accordance with Good and Prudent Practice; b) in accordance with all relevant Standards and codes of practice to which the Contractor would be expected to have regard; c) in accordance with the Employer’s Construction Requirements and the other terms and conditions of this Contract; d) in compliance with all applicable Laws and Permits; and e) in a manner that is not likely to be injurious to health or cause damage to property. When completed, the Works shall meet the requirements as set out in paragraph 2.4 of Schedule 1 (Employer’s Construction Requirements) and in the Contractor warrants that it has designed the Works to have a minimum design operational life of 25 years under the operational conditions set out in the Employer’s Construction Requirements, provided that the same are operated and maintained (and where relevant, replaced) in accordance with the operational and maintenance manuals received in accordance with Clause 5.7 (Operation and Maintenance Manuals) and provided that the individual component parts sets out in Clause 4.5 (Key Sub-Contractor) shall only be warranted for the periods set out in that Clause 4.5. The Contractor shall provide the Contractor’s Documents specified in this Contract, and all Contractor’s Personnel, Goods, consumables and other things and services, whether of a temporary or permanent nature, as are required in and for the design, execution, installation, testing, Commissioning and completion of the Works and remedying of defects, in each case in accordance with this Contract. The Works shall include any work which is necessary to satisfy the Employer’s Construction Requirements, or is implied by this Contract, and all works which (although not mentioned in this Contract) are necessary for stability or for the completion, or sale and proper operation, of the Works. …” “5.3 Contractor’s Undertaking The Contractor undertakes that the Contractor’s Documents, the design, execution, installation, testing, Commissioning and completion of the Works, the remedying of defects and the Works when completed will be in accordance with: a) all applicable Laws, Permits, licences and approvals; b) the documents forming this Contract, as altered or modified by any variations; c) Good and Prudent Practice; d) the technical specification and requirements of the Connection Agreement; e) the requirements to the register on the Ofgem Renewables and CHP Register and to qualify for Renewable Obligations Certificates and shall be free and clear of all liens, charges and encumbrances of any kind. 5.4 Technical Standards and Regulations The Contractor undertakes that the Contractor’s Documents, the design, execution, installation, testing, Commissioning and completion of the Works, the remedying of defects and the Works when completed will comply with the applicable technical standards (as described in the Employer’s Construction Requirements(s) the “ Applicable Standards ” and all applicable building, construction and environmental Laws’ Laws applicable to the product being produced from the Works (as applicable), and other standards specified in the Employer’s Construction Requirements, applicable to the Works, or defined by the applicable Laws. Where there is any conflict between any of the standards or Laws specified in the preceding paragraph, the highest of the conflicting standards or Laws shall apply, unless otherwise agreed by the Employer in writing (as its absolute discretion). All these Laws shall, in respect of the Works, be those prevailing when the Works are taken over by the Employer under Clause 10 (Employer’s Taking Over). References in this Contract to published standards shall be understood to be references to the edition applicable on the Base Date, unless stated otherwise.”
“116. As each site has in the order of 140 inverters and up to 20,000 solar panels, the complexity of analysing the electrical behaviour of the networks is beyond that which can be reliably, or efficiently, done by hand calculations. As a result, it is usual to use commercial software programs to carry out the analysis. 117. In terms of the ac electrical system behaviour, a detailed analysis of the 5 most heavily loaded sites has been carried out using a market leading power system analysis suite called “ERACS” and produced by RINA Ltd, formerly ERA Technology Ltd. The whole of the ac network was modelled including all cabling and protection devices. 118. The circuit topology and component data were entered by a company called PSE2 on my instruction. I have carried out detailed checks on the circuit topology and data entry and I confirm that they are correct. 119. The resultant network drawings, either with or without results, are too complex to be presented in this report in a useful form. However, the complete networks, including the detailed results, will be provided to the Claimants’ experts following submission of this report. Anybody involved in the case can review the network topology, data, and results using viewer software available free of charge via https://www.eracs.co.uk/demo-request. Power system analysis summary results Loadflow studies 120. The general term “Loadflow” covers the steady state operation of an electrical power system. The calculation predicts the voltage profile across the network and the currents flowing in the individual components. The results allow the easy identification of any parts of the network that might be overloaded. 121. To carry out the calculations, the boundary conditions of the network are defined. The base boundary condition for the solar park studies was taken as maximum power from every inverter, at unity power factor, with the voltage at the point of connection at 100%. In other words, the base condition was for normal operation. 122. Once the base condition had been determined, variants in terms of the power factor required by the DNO and the voltage at the point of connection were explored.”
“125. For the four most heavily loaded sites the following loadflow studies were carried out: (1) Case 0 (base case) (a) Inverters at full power. (b) Unity power factor at the inverters. (c) Nominal voltage (100%) at the point of connection to the DNO. (2) Case 1 (realistic base case): (a) Inverters at full power. (b) Inverter power factors adjusted to give unity power at the grid (which is different to 1(b) above since the inverters have to be adjusted to take into account for the fact that the transformers will consume Reactive Power). (c) Nominal voltage (100%) at the point of connection to the DNO. (3) Case 2(a) (worst case scenario with a lagging power factor): (a) Inverters at full power. (b) Inverter power factors adjusted to give power factor 0.95 lagging at the grid. (c) -6% voltage (94%) at the point of connection to the DNO. (4) Case 2(b) (worst case scenario factoring in remedial steps taken by the operator): (a) Inverters at full power. (b) Inverter power factors adjusted to give power factor 0.95 pf lagging at the grid. (c) -6% voltage (94%) at the point of connection to the DNO. (d) Transformer tap adjusted by 5%. This gives the worst case that could ever be required by the DNO but includes the appropriate remedial action by the site operator. (5) Case 3 (worst case scenario with a leading power factor): (a) Inverters at full power. (b) Inverter power factors adjusted to give power factor 0.95 pf leading at the grid. (c) +6% voltage (106%) at the point of connection to the DNO.”
“For any given real power output, the highest inverter current will be given by the lowest inverter voltage. The inverter voltage depends on both the voltage at the point where the solar farm is connected to the network and also the voltage drop or voltage rise through the transformer. The voltage drop or rise through the transformer depends on the current and the power factor. The worst-case is with leading power factor, as this causes the voltage rise through the transformer meaning that the inverter output voltage must be reduced to compensate.”
“[Dr Lockwood]’s approach offers nothing to assist in relation to design methodology. It is very much an after the fact assessment of capacity and provides no assistance as to how a transformer designer, without the benefit of software intervention with its data-base behind it, and without knowledge of the performance behaviour of the network beyond the parameters stipulated in the Connection Agreements would actually go about carrying out design. Putting matters another way there is no evidence from Dr Lockwood as to how the ordinary solar farm designer (without ERACS and without a performance history of the solar farms) would be able to identify, let alone take into account, the performance behaviour of the network beyond the stipulations set out in the Connection Agreements.”
“[Q] For rating the equipment between the inverter and the grid should we be using a current of 48A or 43.3A? Are we right to assume 43.3A is the guaranteed figure for a fixed set of conditions but the current could be up to 48A depending on temperature, power factor etc?” “[A] You should take into consideration the maximum output current which is 48A.”
“That’s what the email says and it’s what any manufacturer would say in the absence of knowledge of the application. If an inverter’s got capability of 48 amps in specification terms, but is put into an application where it can’t reach 48 amps, the application dominates, not what the manufacturer says in terms of the maximum.”
“Q. So in determining what the solar park’s relevant maximum capacity is you need to look at its characteristics including as we discussed the layout of the park, the number of panels and the DNO connection agreement? A. I would say the way - having been involved in a number of renewable projects and doing design of the infrastructure, the size of your infrastructure, you effectively take your connected power, the maximum power the solar farm or wind farm can produce and you calculate that at point 94 volts and point 95 power factor and that’s the worst-case that you have to design for, that’s the worst case of the conditions you need to comply with and if you do that your infrastructure will be sized correctly.”
“The inverters are currently being capped as the transformers are not able to take the rated maximum output for the ‘PV System’, and is so therefore a defect that is under the EPC liabilities”
“Q. So bearing in mind the information you now know, the internal considerations by Wirsol's design engineering, in particular Mr Turner, what Huawei say, and your own work most recently this month, would you accept that a good and prudent practice or a conservative good and prudent practice would design on the basis of 48 amps supplied from the inverters? A. Not just on that one figure with that analysis, no, I would not accept it. Q. Do you accept at least that that is one of the design approaches that is valid for an ordinarily competent engineer to take into account? A. I wouldn't call it a good and prudent approach, no. Q. Why not? It's the approach that all the Wirsol engineers referred to at the time when analysing the transformers. A. It doesn't include looking at the whole site.”
“It's specified in terms of it's a hard limit in the specification and when you look at the manual it indicates that the limit is 48 amps. Modern power electronic equipment is very, very sensitive to over-currents, and the manufacturers are very careful to prevent such hard current limits being exceeded.”
“32. In my original expert report (item 1, paragraph 76 [G/3/23]), I analysed the report of a trip of transformer 2 at Widehurst solar farm at 13h30 on5 April 2018 . The measured busbar current at the time of the trip was 3096A on two phases and 3089A on the third phase. There are a total of 54 Huawei 36KTL inverters connected to transformer 2. It would follow that the average current per inverter was 57.3A. 33. Calculations using the methods set out by Mr Halladay in paragraph 5.3.1 [G/2/27] and appendix 3 [G/2/73] of his expert report suggest that for the trip to have taken place it would have required the network voltage at Widehurst to be substantially below nominal, and likely close to the lower limit, for 4 to 5 minutes.”
“Q. Now here obviously we have inverter current of 57.3 amps. That's the average current at the time of tripping. A. Yes. Q. So in those circumstances, Dr Lockwood, either case Q4 is in play, which is up to 57.6 amps; yes? A. Go ahead. Q. Or your model is wrong and the values stated in here are understated. A. Or there's another difference and the inverters at Widehurst have a slightly different control strategy I understand than the ones in the other sites. Q. But you have presumably taken that into account in providing the outputs for this model? A. I didn't look at -- as these are steady state I must admit I did not take that into account in calculating these numbers. Q. So you would accept that at least so far as Widehurst is concerned, this calculation fails to take into account a relevant factor? A. Failed to take into account a relevant factor ... yes. Q. But it also demonstrates, doesn't it, this particular outage, that the maximum inverter current does get indeed very close to the maximum that is specified on the datasheet by Huawei? A. On this condition -- on this day, yes, it did. Q. And so any prudent designer would need to take into account and base its design on the maximum current specified by Huawei, as indeed Huawei have said? A. Either that, or use clipping or something similar to prevent these very exceptional circumstances from causing over currents. My understanding is that it didn't actually get to the limit, and the tripping stopped when they readjusted the protection settings. Q. But you accept that it got very close to the maximum inverter current on5 April 2018 ? A. Yes, I do. Q. And that ought to have been reflected in the design, oughtn't it? A. The logic follows it should be considered in the design, yes. Q. And so we are -- and if you did the recalculations, we would be in the territory of case Q4 even if not quite at Q4? A. What we don't know about the conditions on that day was the network voltage and the network voltage could have been very low on that day. Q. Yes, but indeed you provide for that in your cases, in all four of your alternative cases that is exactly the scenario that you are considering? A. Yes, true.”
“Q. Taking all of that into account, in particular the Widehurst experience – … Q. Taking all of these points into account, do you accept now on reflection that good ordinary design practice is to use the maximum inverter current as the basis of design and therefore to assess whether the proposed transformers have adequate capacity? A. As I've clearly indicated, the last piece of evidence I do not think is at all relevant. So taking everything that you've said into account, that would negate that point.” and finally: “Q. Can I ask you, we discussed Widehurst already, Widehurst requires a leading power factor of 0.98 lead. A. Yes. Q. And we explored, didn't we, the scenario which took place at tripping on5 April 2018 ? A. Yes. … Q. So in those circumstances, you remember we looked at the average amps per inverter being at 57.3 amps? A. Yes. Q. So turning to your schedule 2, one has to be in a scenario where there is a leading power factor in fact in the fifth column and the final column of your schedule, G/33/2. A. Either that or the voltage fell at that time. Q. Well, the voltage must be very low, I think you accepted that, in order to be at the scenario where the current from the amps is at that figure. It will only be in that scenario. A. Yes.”
“Overview of the U.K.’s electrical infrastructure 61. The U.K.’s electrical infrastructure has evolved over many decades and comprises: (1) Major sites of power generation from fossil and nuclear fuels. (2) A national high voltage transmission network (i.e. the National Grid). (3) Regional electrical distribution companies currently called distribution network operators (“ DNOs ”). (4) The introduction of small renewable generation sites, such as wind and solar. 62. The introduction of small renewable generation sites is a recent development. For cost, geographical, and technical reasons, generally these sites are not connected directly to the National Grid but are embedded in the medium and low voltage networks operated by the DNOs. 63. The connection of a renewable energy site in a DNO network gives rise to serious operational and safety issues. It can also affect the DNO’s ability to satisfy its own regulatory obligations. As such, the connection of a renewable generation site, such as a solar park, is governed by a set of strong regulations and requirements. DNOs 64. The DNO has an obligation to ensure that other customers connected to their network do not suffer damage to their installations nor unacceptable disturbances to their electrical supplies. Such damage or disturbances can be caused through fluctuating voltages. Whilst voltages constantly fluctuate, significant fluctuations are problematic for the safe operation of the network. Therefore, the DNOs have a responsibility to ensure that the voltage in their network is within plus and minus 6% of its nominal value (Electricity Safety, Quality and Continuity Regulations (ESQCR). 65. There is a mismatch between the standards applying to DNOs, and the standard covering the voltage capability of transformers. The relevant standard for transformers is IEC 60076-11 (clause 8.4) which says that a transformer shall be capable of service without damage of overvoltage by no more than 5%. However, for the purposes of this report, I have applied the 6% figure. 66. In order to manage the potentially disruptive effects of having a solar generation site connected in the network, the DNOs impose rules and requirements on the site operation under the terms of a connection agreement. 67. Connection agreements have standard forms and content. By way of example, the connection agreement for the Outwood site is exhibited at Schedule 4. Generation, transmission, and distribution of electricity 68. For technical and commercial reasons, the bulk of electrical power is generated, transmitted, and distributed in the form of alternating current (ac) rather than direct current (dc). 69. In dc systems the calculation of power is simply voltage multiplied by current. 70. The calculation of power is more complex in ac systems due to the ‘tidal’ flow of energy into electrostatic and electromagnetic storage in the load network. That causes the “ Apparent Power ” calculated by voltage multiplied by current to be greater than the actual useful power transmitted, termed “ Real Power ”
“The Customer is required to operate the generation plant in a constant power factor mode within the range 0.95 lead to 0.95 lag. To cater for times where there is an operational need [the DNO] and National Grid plc. reserve the right to request you to operate at a specific power factor that are within the capability of your plant.”
“Q. Well, let’s come to the terms in a moment but as a practical matter you’ve never seen a voltage network operating at 94 per cent of nominal where the DNO requested a leading power factor of point 95, have you? A. There is operational experience, my Lord, that suggests that two of the solar farms which are operating at point 98 lead are experiencing voltage significantly below nominal. Q. We’ll come to those, don’t worry. But just as a sequencing point I think what you are saying is they were operating at point 98 lead, not point 95 and in fact experienced voltage below nominal, but if the DNO’s network is operating below nominal, say it operates on average at 97 per cent, the DNO is not then going to request a leading power factor, is it, because that would make the current situation worse not better? A. The DNO, my Lord, are entitled to do so under the terms of the connection agreements. Q. But you’ve never seen it done? A. I’m afraid I can’t recall.”
“Q. But going back to this issue of changing of taps, I think what you are saying is it's only in the circumstances of longer term variations as you describe them that you might change the taps? A. Longer term variations within the plus or minus 6 per cent, which is part of a connection agreement. Q. Your view on taps more generally is that their use should be avoided, isn't it? A. It is. Q. And perhaps we could go to -- A. Sorry can I qualify that? Q. While you are qualifying could we get up K11/2043. A. If you have taps on a transformer you can use them in my view, you might as well. Because all of the risks of having a transformer with taps are physical risks within the transformer. Taps add complication to the design and in particular to the construction of transformers, and I have been saying for a long time it will be best if systems were designed, particularly in the UK where the voltage hardly ever varies, transformers should be designed without taps to avoid the reliability and complexity issues that come with having transformers with taps. Q. Yes, your view is that you should really try to avoid these use of manual taps -- A. Not the use -- Q. -- as much as possible. A. If you've got them use them. If you are designing a system if at all possible design the need for them out. Q. And that's because tap connections are the single biggest cause of failure in transformers? A. That's widely accepted. Q. They rarely serve a useful purpose? A. In the UK they rarely serve a useful purpose.”
“The voltage at the inverters is known to vary on a daily basis at some sites by up to 9 per cent but that's not the same as the network voltage varying by that amount because of, you know, voltage drops or rise through cables and the transformers but the voltage variation on the system is at some of the sites certainly not of the order of 1 per cent. Q. What do you say it's of the order of? A. My estimate based on that experience will be 5 to 6 per cent. Q. Well, I'd suggest to you, well, there's obviously no data on this, I don't think the claimants have provided any although they are in control of the sites, but I suggest to you that is excessive, it is in the order of 1 to 2 per cent, perhaps either side of nominal -- A. I have to say that I don't think that that's the experience at some of the sites. I will add a further caveat that it will depend quite a lot on what the network is like around the site. A big smelting plant is obviously going to affect things quite a lot.”
“Q. But if the tap is set at minus 2.5, because conditions are in general circumstances what that suits long-term sustained voltage, that voltage in itself can move up and down, can't it? A. In the short-term by a smaller amount; in -- but not by, for example, going from minus 6 to plus 6 per cent. Q. But it might go minus 6 or it might go plus 6, that's in the range of what is required both by the connection agreement and by regulation? A. It would not do so in the short-term. You would have time to change the taps. And you must remember that in operation, in terms of connection to the DNO, longer term movements in voltage and the requirements of the DNO for reactive power, go hand in hand. If the voltage was low in a sustained manner, the DNO might -- would tend to request a lagging power factor to help compensate for the low voltage; if the voltage was sustained high the utility might ask for a leading power factor to help lower the voltage. But you just don't get plus and minus 6 per cent swings in the short-term.”
“8.1 General The manufacturer shall assign ratings to the transformer, which shall be marked on the rating place, see Clause 9… 8.2 Rated Power The transformer shall have an assigned rated power for each winding which shall be marked on the rating plate. The transformer shall be fully rated when supplied in an enclosure. The rated power refers to continuous loading. This is a reference value for guarantees and tests concerning load losses, temperature rises and short-circuit impedance. NOTE A two-winding transformer has only one value of rated power, identical for both windings. When the transformer has rated voltage applied to the primary winding, and rated current flows through the terminals of that winding, the transformer receives the relevant rated power for both windings. The rated power corresponds to continuous duty; nevertheless, dry-type transformers complying with this standard can be overloaded and guidance on overloads is given in IEC 60905.”
“Q. If you bring that down even by a decimal point of a percentage point, on this analysis both these transformers lack capacity; yes? A. If -- Q. Prudently regarded as lacking capacity. A. In terms of steady state rating, I agree that with the evidence we've gone through then that -- that row or those two rows actually, I think no, just one row, would need to be changed. Q. Thank you.”
“Please see attached datasheet, although it does not directly state 1600kVA-2240kVA as per other manufacturers or 11kV version from Imefy. Basic rating is 1600kVA (AN) 2240kVA is achievable by (AF)”
“ The power rating, when operating the fans can be increased 15% above the nameplate rating. This equates to 2875 kVA when operating within a 40C ambient max and 30C average in a day .”
“The range of climatic conditions to be used as the basis for the design…of plant is summarized in the following table….Maximum Ambient Temperature: 45˚ C”
“Unless otherwise stated, the service conditions in 4.2.2 to 4.2.6 apply. When transformers are required to operate outside the normal service conditions, de-rating in accordance with 11.2 and/or 11.3 applies.”
“Reduced temperature rises for transformers designed for high cooling air temperatures or special air cooling conditions. When the transformer is designed for service where the temperature of the cooling air exceeds one of the maximum values specified in 4.2.3, the temperature rise limits shall be reduced by the same amount as the excess. The values shall be rounded to the nearest whole number of K. Any site conditions that may either impose restrictions on the cooling air or produce high ambient air temperatures should be stated by the purchaser.”
“It is possible to use a transformer dimensioned for a maximum ambient temperature of 40˚C even with higher temperatures: in this case, the power will have to be reduced, as indicated in the following table.”
“The transformer lifetime particularly depends on the duration of its insulation, which is, in turn, strictly connected to the load cycle to which it is subject. However, some overloads are allowed and they do not compromise the operation and life of the transformer, if they are compensated by a normal load lower than the nominal power.”
“Even putting aside the real and proper doubts as to Dr Lockwood’s relevant expertise, independence and impartiality, his assumption as to the meaning of the EPC contracts led him into assuming the finishing point of the analysis, that the transformers have adequate capacity, and to in-fill his reasoning to that pre-determined conclusion.”
“Over the last couple of years, Rob and myself have tried to up the settings to their highest possible. I believe the last push was to try these settings (Below) and this seems to have been ok and we are no longer seeing shutdowns for overcurrents due to the undersized TX’s. Inverter Limited Outwood Newton Five Oaks TX1 94% 92% 100% TX2 100% 100% 94% …”
“Neither Party shall be liable to the other Party for loss of use of any Works, loss of profit, loss of any contract, loss of revenue or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with this Contract, other than under [ clauses not applicable to the present claims ]. This Sub-Clause 17.6 shall not limit liability in any case of fraud, bribery, corruption, deliberate default (including abandonment), gross negligence or reckless misconduct by the defaulting Party.”
“Not sure how warranties can be voided when they state 2240. They are not operating at 100% and they are or should be designed to operate at 100%. Lets also bear in mind that these transformers, for the majority of the time, do not run anywhere near 100%. I think we need to either push back on Burnells and get them to commit to their design or get them to update the transformers …”
“ideally we would have had the larger transformers - but I understand from Jim that this will extend the lead times? One point Jason in cc made was that we would like the Woodward limit set to 3100A if possible to stop them tripping under normal condition”
“Q. But 33kV are experts? A. As your high voltage experts. So their expertise is in connecting to the grid. They have -- they are senior authorised personnel within their team. Kevin Hann used to work for SSE, he knows the grid very well. Their expertise, and that's what they were engaged with us to do the harmonic distortion, flicker and voltage reports and various earthing reports, that's their expertise. Their expertise was the umbilical cord from the site, the DNO substation to the grid.” and: “Their experience is not in solar. They're connecting -- they're connecting a solar park one day, a gas peaking system another day, a factory another day, that's what they do. They connect high voltage up to 33KV and they've subsequently got accreditation up to 32KV to grid. That's what they do.”
“As Rob has mentioned, Fundamentally there is too many inverters connected to the transformer, or the transformer is undersized for the design. (Whichever way you want to look at it.) There is many reasons for this, mostly based around costs and lead times and so the decision was made during the design stage to accept the lower rated transformer and just limit the inverters where needed. The limiting of the inverter only has an effect when the output reaches the limit and has no effect when the inverter power is less than the set limit.”
“7.4.1 The performance ratio for power plants shows actual output compared to theoretical output. A lower performance ratio leads to lower output. It is therefore a good indicator of overall losses caused by the defects. Mr Kirk notes the example of Five Oaks, with a performance ratio c3% below what was expected over the year from31 July 2017 . … 7.4.3 I have received from Toucan a summary from their performance reporting software showing the difference between 8 plants built by Wirsol and 8 plants of a similar size built by others for the full year from June 2019-May 2020. The screenshots are shown as Exhibit 1. What can be seen is that the performance ratio for the Wirsol sites is 80.9% and for the non-Wirsol sites is 84.9%, a difference of 4.0%. 7.4.4 I consider 4.0% as a reasonable estimate of annual losses as a result of the issues described above…”
“… the PR is determined by a wide range of site-specific features, including the characteristics of the electrical components utilised, their age, the layout deployed, the physical topography of the site and the degree of shading… each of which can influence a site’s specific PR and by up to 3.67%.”
“A. … I think the performance ratio is the relationship between the amount of irradiance, the sunlight, and the level of generation that is achieved. So – Q. But it doesn’t matter – Mr Justice Henshaw: Can we have the rest of that answer please? A. So it follows that the calculation has already taken account of that.”
“A. The actual losses, my understanding of the process was that there was other experts who do the quantum losses. Q. So you would expect to see another expert performing an analysis similar to Dr Lockwood's. That's what you were anticipating, were you? A. Yes.”
“The documents forming this Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence: the Contract Agreement; the Conditions of Contract; Schedule 1 (Employer’s Construction Requirements); The remaining Schedules other than Schedule 8 (Contractor’s Proposals); and Schedule 8 (Contractor’s Proposals).”
“The Parties have agreed the details of the Contractor’s scope of works and specification and other documentation contained in the Contractor’s Technical Proposal and the Parties agree and acknowledge that, subject to necessary design development and the provision of all works, plant and materials necessary to enable the works as described in the Contractor’s Technical Proposal to be constructed and completed, the documents forming the Contractor’s Technical Proposal set out the agreed scope of works and specification of the Works to be provided by the Contractor. Subject to the requirements of the preceding paragraph where the Contractor’s Technical Proposal does not address a particular requirement set out in these Employer’s Requirements (which is not a requirement under English Laws (as such term is defined in the Conditions of Contract) and compliance with such requirement would cause the Contractor to incur additional cost or cause delay to the Works, then the Parties shall seek to agree (acting reasonably) whether based on the negotiations between the Parties and the scope of works and specification as set out in the Contractor’s Technical Proposal and the fact that the Contractor is an experienced contractor in solar photovoltaic installations the requirement is one which the Contractor should reasonably be expected to comply with having regard to specific site conditions and requirements. If the Parties agree that the Contractor should reasonably be expected to comply with the relevant requirement then the Contractor shall comply with such requirement. If the Parties agree that the Contractor should not reasonably be expected to comply with the relevant requirement then he shall not be bound to comply with the same and the relevant requirement shall be disregarded unless the Employer instructs a Variation with regard to such compliance. Any dispute or failure to agree shall be referred for determination in accordance with clause 20 of the Conditions of Contract. If the failure of the Contractor’s Technical Proposal to address a particular requirement set out in these Employer’s Requirements is not discovered during the carrying out of the Works the principles set out in this paragraph shall apply to determine whether the Contractor is liable under this Contract in respect of the failure to comply with the relevant requirement of the Employer’s Requirements. In the event of any inconsistency between the Contractor’s Proposals and these Employer’s Requirements, these Employer’s Requirements shall prevail.”
“ All transformers will be of the three phase with one LV winding for each inverter - vector group Dy11y11, of the specification attached in Schedule 8 and supplied and manufactured by the same approved subcontractor as listed in Schedule 12.”
“All dry-type transformers shall be mounted indoors and shall be installed in purpose designed and built housings. Housing shall be designed to allow adequate ventilation of the transformer but to prevent inadvertent contact will live metalwork. As a minimum the protection class of transformer housing shall be IP32. All dry type transformers shall be designed for natural air cooling.”
“… before a written contract may be rectified on the basis of a common mistake, it is necessary to show either (1) that the document fails to give effect to a prior concluded contract or (2) that, when they executed the document, the parties had a common intention in respect of a particular matter which, by mistake, the document did not accurately record. In the latter case it is necessary to show not only that each party to the contract had the same actual intention with regard to the relevant matter, but also that there was an “outward expression of accord”- meaning that, as a result of communication between them, the parties understood each other to share that intention.”
“Mr Justice Henshaw: Well, I think he is asking, if I’ve understood correctly, do you agree that indoor dry type forced air cooled transformers are widely used in the market? A: It would appear that they are widely used - it would appear that they are used, especially it would appear by Burnell if we are to believe Dr Lockwood’s evidence.”
“Transformers with forced air cooling are less efficient than transformers of similar design and construction with natural air cooling. This is partly owing to the energy consumed by the fans but mainly owing to the inherent characteristics of transformers.”
“The use of fans increases the complexity of the system and this has the potential consequence of reduced reliability and availability. Assuming this protection is functioning correctly, it should minimise the consequences for any fan failures for equipment life and also any risk of fire.”
“Please be advised that there is still a major concern by us regarding the cooling of these transformers, you are correct in that we have set up the fans on substation 2 and this has gone some way in reducing the transformer temperatures however the bigger issue that appears to be being overlooked is that you are not getting the correct airflow to the transformers and as per our report this is because the bag filters need changing and the additional fan cowls need removing and the proper fan cowls need to be fitted this is detailed in the last paragraphs of our report, until these actions are carried out you will continue to see a reduced airflow which will result in high temperatures on the transformers.”
“We reiterate that we are very concerned about the lack of knowledge or the correct operation of the equipment, the lack of maintenance and general cleanliness of the substations…”
“The use of forced ventilation may result in some additional ingress of dirt and other fine solid contamination via the air intakes compared with what might otherwise have been expected.”
“Indoor climate conditions shall be established e.g. by adequate cooling, heating, dehumidifying, ventilation or by adequate design of the building. It is preferable to use natural ventilation for transformer rooms.”
“7.5.7 Air conditioning and ventilation Indoor climate conditions shall be established e.g. by adequate cooling, heating, dehumidifying, ventilation or by adequate design of the building. It is preferable to use natural ventilation for transformer rooms. Forced ventilation systems (permanent or mobile) shall be designed to take into consideration smoke removal from the building. Monitoring of the operation of a permanent fan is recommended. Ventilation openings shall be designed so as to prevent any dangerous proximity to live parts and any dangerous ingress of foreign bodies. Coolants and heat transfer media shall not contain mechanical impurities or chemically aggressive substances in quantities or qualities which may be hazardous to the correct function of the equipment in the installation. Filters or heat exchangers shall be provided, if necessary. Mechanical ventilation systems shall be so arranged and placed that inspection and maintenance can be carried out even when the switchgear is in operation.”
“151. As the substation ventilation system runs all the time there is a continuous influx of outside air into the substation. To avoid condensation, particularly during changes in temperature, it is necessary to keep the temperature inside the substations above the exterior air temperature. The margin between the interior temperature and the exterior should be 5°K or higher. 152. There are three main sources of heat within the substations. Two of those are temperature-controlled fan heaters similar to domestic fan heaters, the other being the transformer losses. 153. When running, transformers generate heat in two ways. There are power losses associated with the cyclic changing of the magnetic flux in the transformer. Those losses are primarily created in the transformer iron core and are commonly called or “ No-Load Losses ” (or sometimes iron-losses). Under load, the current creates losses in the windings due to the resistance of the conductors. These are called “ Load Losses ” (or sometimes copper losses). 154. No-Load Losses are effectively constant while the transformer is energised. Load losses are proportional to the square of the current. It follows that the transformer losses are lowest when the solar park is not generating; that is at night. 155. The transformers in this case have No Load losses of around 2.2 kW to 2.5 kW. The fan heaters are each rated at 2 kW so the total heating in the substation at night would vary from a minimum of 2.2 kW if the substation temperature was above the fan thermostat setting to a maximum of 6.2 kW if the room was colder than the thermostat setting. 156. The substations have three zones down their length: the HV switchgear zone, the transformer zone, and the LV switchgear zone. The separators between the zones are formed of a coarse wire mesh as can be seen in Figure 7. That mesh offers negligible impediment to air flow. 157. The fan heaters are wall-mounted in an attitude in which the warm air is propelled downwards (Figure 7). Figure 7 : HV switchgear zone showing location of the heater 158. One heater is positioned in the HV switchgear room, as in Figure 7 and the other is in the LV switchgear room at the far end of the substation. Therefore, each zone in the substation has in the order of 2 KW heating when needed. 159. Mr Ryder carried out calculations aimed at identifying by how much heating would increase the air temperature in the substation (§5.20 and his Exhibit 5-9). He concluded that: “Making reasonable assumptions it can be shown that the temperature of the transformer room will be between 2.8K to 4.6K higher than the outdoor ambient temperature. A temperature difference of at least 5K is normally considered to be necessary to avoid condensation.” 160. For reasons Mr Ryder does not explain, he did not include the 4 kW contribution of the fan heaters. He had earlier said that his opinion was that the heaters were mounted too high on the wall (I disagree on that point) but I do not think that that is sufficient excuse to neglect their presence. 161. As noted above, he arrived at the figure of 2.8 °K to 4.8 °K (i.e. lower than the 5 °K required to avoid condensation). 162 When the calculations are repeated factoring in the heaters they show clearly that the temperature rise would be 8 °K which would be more than sufficient to prevent condensation. I have included my calculations alongside Mr Ryder’s calculations in Exhibit 2 (calculations documents).”
“A. What I did, my Lord, when I prepared the calculation is initially I prepared a calculation for the whole substation building, so two heaters, three fans, one air inlet, plus whatever gets lost through the walls. And if I looked at the substation as a whole I got one answer which did not seem to explain what was the substation and seeing for example there's a very large busbar assembly which is separating the transformer room from the LV room, and actually quite a large HV switchgear assembly which largely blocks the entrance between the high voltage room and the transformer room, I decided to break the substation into three rooms and analyse each one independently. Q. That's a fascinating answer. So you originally did a calculation that treated the substation as a single room and you say you didn't get an answer that explained what was happening. Does that mean that your answer would suggest that substation as a whole would be sufficiently warmer than outside? That it would not in fact experience condensation while the transformer was switched on, is that what you meant? A. My Lord, that is exactly what I meant. What I felt was that as my calculation was clearly not calculating what was being experienced operationally there must be something wrong with my calculation. I suppose the alternative is there's something wrong with the operational experience. Q. I am going to suggest to you, Mr Ryder, that that is the exact position, that in fact you have misinterpreted the operational experience and we'll come to that. But that actually your first approach, which properly took into account the heaters and the fact that actually there's no significant impedance on airflow between the three parts of the substation was correct and you got the right answer? A. I understand why counsel has suggested that, my Lord, but the reason I changed my mind and I changed my calculation was precisely because I felt that the results of my calculation were not reflecting operational experience, and I felt as a good practical engineer it was my responsibility to calculate what was happening, and to fit my -- if you like to fit my calculation to what I was observing, and not my observations to what I was calculating. Q. So your calculation was intended -- was -- I don't mean to put this pejoratively -- retrofitted on to operational experience. It wouldn't have any, I suggest to you, independent validity if in fact your analysis of the operational experience was mistaken, because you changed your view in order to try to make sure the two matched up. Is that fair? A. My Lord, I think it is fair to say, it is fair for counsel to suggest to me that I changed my mind in the light of operational experience and I agree I changed my mind in the light of operational experience.”
“Q. Right. Well, I'd suggest to you that absent the fans pulling air in through the cable entries, cold humid air from outside is not in fact going to rise into the warmer substations. That's a basic point of thermodynamics, isn't it? A. (Pause) I'm just considering my answer, my Lord. It is true that large amounts of condensation have been observed in the HV cable entries. It may be that my understanding or my explanation of the mechanism through which it's caused is a little clumsy. Q. Okay, well we'll come to the cable entries themselves. The point I'm making to you is that absent any sensor data, absent any cogent reason to think air that is humid and cold is rising through the cable entries there's no reason to assume and indeed no basis for suggesting that humid air is entering the HV area of the substation via that route? A. Mm ... in which case -- yes, in which case presumably the condensation must have a slightly different course. Q. Well we'll come to whether there's actually any condensation but are you accepting that proposition? A. For the time being, yes.”
“TX 1 7.0° @95.8% Relative Humidity - wet puddle under sub TX2 6.7° @ 90.2% Relative Humidity - Dry sand under sub”
“ The switchgear was very damp internally this may have been because there was no power within the substation for over a week and might have absorbed moisture within the cable box and switchgear ” and “ The termination cable box incoming from WP D and from the Transformer were very condensated and dirty within ”
“ it is clear at this point the transformer had suffered an internal failure ”
“There was a significant enough heat which damaged the above transformers L2 core resulting in core failure. The result of the damage caused the delta winding to fail and open circuit. The compounding effect of this caused severe imbalance in the delta MV transformer winding this then caused very high currents which caused significant heat stress on the connecting power connections and copper bus-bars. The result of this then caused the Power Protection to trip. All 3 windings have failed. •It was found the transformer had suffered severe damage from the resultant heat and moisture. … •The conclusion reached by both parties, the transformer delta winding was damaged from excessive heat.” and: “Johnson & Phillips established the transformer issue was due to a poor design assembly causing severe heat & moisture this influence was beyond the client control. Our tests concluded a breakdown or disruption in the delta partition of the transformer. This caused a severe imbalance and introduced high and excessive neutral current to the Star Point LV partition of the transformer leading to failure.”
“183 Also, during the visit at Woodhouse, I had the opportunity to enter a substation just minutes after it had been switched off. I entered at 16:43, the day was heavily overcast with cloud and levels of energy production were very low. The air temperature was slightly less than 20 °C. The external surfaces of the transformer windings were at approximately 40 °C, that is slightly warm to the touch. However, the core was so hot that I could only touch it for a fraction of a second. That indicates that the core temperature was in excess of 60 °C. However, the core had slight signs of surface rust (Figure 10). … 184. Even if one argues that the winding temperature formed the ambient around the core, the core was still at least 20 °C higher than its local ambient. As transformer core losses do not increase greatly with load, it can be seen that the transformer would be noticeably warm even on a cold damp night. The observed rust could not form on the surface of a transformer core whose temperature was at least 20 °C above ambient. Indeed, when energised for sustained periods, transformer cores typically run at 20°C to 40°C higher than the ambient temperature. 185. It follows that the transformer had been exposed to humid conditions for a sustained period when the substation was not energised. Unless a substation is supplied by an auxiliary electrical supply while deenergised, condensation will occur and corrosion could take place. 186. It is my firm opinion that the Woodhouse substation had been left unheated on one or more occasions and it was in such a period or periods that the observed corrosion had taken place. 187. I have been informed by Defendants that all the sites in the case were de-energised for sustained periods shortly after the EPC and O&M Contracts were terminated. This suggests that auxiliary generators were not supplied for the period of when they were out of service. Alternatively, Woodhouse was deenergised at another point in time, again without the required auxiliary generators being provided. 188. All of the substations are fitted with a connector which allows a mobile generator to be connected when needed. The purpose of that socket is to provide what is called ‘hotel-load’ to the substation; that is heating, lighting, and power for instruments and communications. The site operator should deliver such a generator to site within a few hours of the substations becoming de-energised for any reason. Therefore, it would not be problematic to install auxiliary generators. 189. In short, I have not identified a specific defect with the design of the substation which means that it is subject to excess humidity. There do, however, appear to have been operational issues which have caused rust on the transformer cores. This is unfortunate. Solar parks need to be well-maintained to ensure that they operate effectively.”
“No signs of corrosion on any metal parts, and this is the only sign of moisture ingress potentially from under the substation (there was historical water marks under the ventilation filters, but not related to this issue). Exposing about an inch gap at the LV end … it was clearly evident that there is approx.. 250mm of water present underneath the substation (at 40ft, a substantial amount), concluding that there has been insufficient backfill of sand applied. With the cable pit having a lower finished surface than the surrounding land, it will always fill with water when the land around is saturated, as was found. … After conversing with Jim Young of Burnells, suppliers of the substations, whilst this is indeed not desirable and needs rectification for longevity of the plant, there are no immediate concerns over functionality. My initial concerns over moisture inside the switchgear cabins was alleviated when he explained they are effectively outside units with a different casing over them, as they now need no protection from rain, being installed inside. I questioned over the recent VT failure being moisture related which he believed was very unlikely, although the manufacturer report is still pending.”
“178. On the3 July 2020 , I made a site visit to Woodhouse. I inspected the equipment and substations very carefully and I can say that there is no evidence at all that humidity or free water caused the failure. That view is supported by an interview I had with the first engineer to inspect the site on the day after the failure (Mr Nigel Bird of Electrical Infrastructure Services). Mr Bird described the scene of the failure and stated that there were not any signs of dampness. I inspected the failed unit, and the switchgear of which it was a component. There were not any indications of dampness such as rusting, white deposits, watermarks or any of the other usual consequences of dampness, condensation, or of free water ingress. 179. Voltage transformers can fail due to excessive moisture. In all the cases I have seen where moisture was the cause, the failures occurred as surface tracking in which small spark discharges carved tracks over the surface of the insulation. There were no such tracks on the failed unit I examined. 180. That unit had suffered an internal arcing failure that had generated so much heat that it had shattered the thick case of the voltage transformer. The evidence of burning and melting was remote from the points where the connections entered the epoxy encapsulation. The summation of the evidence pointed clearly to it being an internal malfunction and not caused by moisture ingress (see Schedule 1). 181. To put the matter beyond doubt, I suggested to the Claimants’ experts that the damaged equipment be taken to a specialist laboratory for inspection. This request was refused.”
“A. The narrow answer to the question is I put Dr Lockwood's request to the claimants, and the claimants declined. So I am not able -- the claimants didn't provide me with a very clear explanation about why they declined.”
“A. My Lord, while it seems to be an obvious answer, I am concerned that it would impede the blast relief of the switchgear and be a safety challenge. I think a safety -- sorry defect -- I think it might ... I think I'll leave that. I think I'll leave that there.”
“Electrical equipment which may reasonably foreseeably be exposed to– (a) mechanical damage; (b) the effects of the weather, natural hazards, temperature or pressure; (c) the effects of wet, dirty, dusty or corrosive conditions; or (d) any flammable or explosive substance, including dusts, vapours or gases, shall be of such construction or as necessary protected as to prevent, so far as is reasonably practicable, danger arising from such exposure.”
“Q. And is it right that since Wirsol were removed in 2018, you have done nothing in order to attempt to reduce water ingress into these substations? A. We installed some cowls. It would need drastic work to prevent water getting into substations. Q. You say drastic work. It is simply a matter isn't it of installing large enough cowls and adequate seals on the doors. I am distinguishing humidity from water ingress. That's not beyond the ken of man, is it? A. No.”
“This part of IEC 62271 specifies the service conditions, rated characteristics, general structural requirements and test methods of high voltage/low voltage or low voltage/high voltage prefabricates substations, which are cable-connected, to be operated from inside (walk-in type) or outside (non-walk-in type) for alternating current or rated voltages above 1kV and up to and including 52 kV on the high voltage side, and for one or more transformers for service frequencies up to and including 60Hz for outdoor installation at locations with public accessibility and where protection of personnel is provided.”
“From my experience of substation fires, there is only one circumstance where the plywood flooring might be consumed by a fire. That is if the cast resin transformer itself burns. The resin encapsulation of the transformer is typically loaded with powdered aluminium trihydrate. That material is chosen for its fire suppression qualities. However, there are circumstances where a fault in the transformer can persist for long periods without it being detectable by the protection devices. Very occasionally that leads to the aluminium of the transformer windings being ignited. Once ignited, aluminium burns very readily with resultant very high temperatures. If that rare occurrence happened in a substation with a plywood floor, that plywood would almost certainly be consumed. However, its contribution to the total energy released would negligible.”
“In terms of combustible material in the substation, the transformer resin encapsulation does not burn readily as it is usually loaded with Aluminium Trihydrate which has fire suppression properties. It seems probable that the primary source of fuel for the fire was the marine ply floor and this was sufficient to maintain the combustion of the transformer cast resin encapsulation.”
“I saw a site in the south-west of England where a transformer had completely burnt out, including the cast resin encapsulation and … it had burnt out. And I concluded that the primary source of fuel in that case was actually the aluminium of the transformer. Aluminium burns quite readily if you can get the temperature high enough, and I know that it was not plywood floor because the sister substation, which … was identical, same manufacturer, same construction, et cetera, did not have any plywood on the floor. It was a metal -- a steel floor. So the plywood could not have been contributory in that case, there was no other significant … material that could burn. So the fire in that case was purely the transformer, and reflected back to my previous experience at Magnetar I now do not believe that the Magnetar case of the plywood was the primary fuel.”
“Q. Now, the issue there, I mean that can be treated easily enough, couldn't it? You could remove fungal growth with any number of different treatments at which point the plywood isn't going to deteriorate any further, is it? You say it's irreversible but not untreatable? A. I think I must agree with counsel that it would be possible to, for example, cut out the deteriorated patch and replace it either with fresh plywood or with GRP, for example -- sorry, glass reinforced plastic mesh which is widely used as flooring in substations. It might be possible to apply some sort of chemical treatment to it. I'm not expert enough in chemical treatments for wood to be able to comment on that suggestion. Q. To the extent this particular issue has arisen it is treatable one way or other? A. At this location, I think I have to agree with counsel.”
“Include protective relays and systems to detect all credible faults on each item of plant and equipment and their primary interconnections, and arranged so that on functioning only the faulty apparatus is removed from the circuit.” ii) Employer's Requirements § 4.4.9: “Switchboards shall be sectionalised through the provision of a bus section circuit breaker”. and: “HV switchgear shall be…in accordance with the equipment manual attached in Schedule 8 - specifically of 2-field 36kV type with circuit breaker (CB-C)”. iii) Employer's Requirements § 4.4.10, which provides that HV circuit breakers shall have their own control compartment with protection relays and other protection devices for the discrete protection of its switchgear. iv) Employer's Requirements § 4.4.11: “Each LV main switchboard shall sectionalised using a bus section breaker.” v) Clause 4.5.5 of the electrical specification: “A coordinated protection system shall be provided to cover all electrical equipment. The protection system shall be designed to rapidly detect faults on electrical systems and to accurately determine their location so as to facilitate isolation of the fault whilst minimising disruption to the rest of the plant.” vi) Section 1 of the Contractor’s Proposals, detailing the requirements for the HV Switchgear: “2 x 33kV Customer Switchgear in concrete box full equipped…2 x 630A PV Box Feeders with G59 protection relays…” . vii) Clauses 4.1, 5.3 and 5.4 of the Conditions of Contract and Employer’s Requirements § 2.11, which require the design to comply with all laws and regulations. The Electricity atWork Regulations 1989 , regulation 5 requires that “ No electrical equipment shall be used where its strength and capability may be exceeded in such a way as may give rise to danger .”
“Q. We’ve agreed the switchboard needs to be replaced. That could be replaced within the existing substation, couldn’t it?”
“…it is implicit that the site of the putative LV circuit breakers would be between the LV terminals of the transformer and the switchgear busbars and that a suitable protection relay would be fitted to detect fault conditions and command the putative LV circuit breaker to open… The busbars feed multiple cables, each fitted with 250A fast acting fuses. Therefore, the addition of LV circuit breakers would add an additional zone of protection limited to the LV busbars.”
“If HV circuit breakers are installed this would allow an LV fault at Substation TX1, for the LV busbars and the Main LV Switchboard up to the outgoing fuses, to be cleared without shutting down the entire site.”
“ It is an additional and unnecessary point at which faults can take place and to reduce this risk ought to be removed .”
“The fault levels at the points of installation of some of the MCBs exceeds the rating of the currently installed…units. As a result, these devices will need replacing. If the MCB operates above it[s] rated fault level there is a risk of a catastrophic failure of the MCB and fire at the respective combiner box.”
“As indicated in the areas of agreement, there is a number of locations where the MCB breaking capacity might be exceeded. Defendants’ expert [Dr Lockwood] will be presenting a list of those locations in his expert report. …”
“Without a detailed fault study report for each site, I cannot accurately determine the number of miniature circuit breakers that need to be replaced. It will be necessary for detailed fault studies to be completed to allow this assessment to be made. …”
“6.2.6.3 Dr Lockwood has provided absolutely no analysis, results, information, documentation or verification of the analysis and results, nor any details of which MCBs he now considers have fault levels in excess of the 25kA rating which are referred to in paragraphs 345 and 346. In table 6 of my expert report dated24 June 2020 , the fault level at all sites are listed. At all sites the fault level is above the 25kA rating of the existing fitted MCBs. Based on these results and acting prudently all sites require the MCBs to be replaced. … 6.2.6.5 There was no further information provided on MCB fault levels in the letter from Enyo dated21 July 2020 . On this basis this does not impact/ alter my views stated in paragraphs 6.2.6.2 and 6.2.6.3 above and I do not regard the information provided as being “sufficient and complete ” as stated by Dr Lockwood in his letter dated27 July 2020 .”
“In order that the Works and Contractor’s Documents shall be in the condition required by this Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall perform: (a) any work which is outstanding on the date stated in a Taking-Over certificate, as a condition precedent to certification of the final Payment Milestone under Sub-Clause 14.4 (Milestone Payments); (b) all work required to remedy defects or damage (including damage caused by the defect and damage arising from the investigation or repair of the defect or damage), as may be notified by the Employer or of which the Contractor is otherwise aware on or before the expiry date of the Defects Notification Period; and (c) any work required to remedy a Systemic Defect. Each Party shall notify the other Party in writing and, (if requested) the Independent Engineer as soon as reasonably practicable after becoming aware of the existence of a defect or damage occurring as a result of a defect or a Systemic Defect. The Contractor shall execute all work referred to in paragraphs (a) and (b) above in accordance with this Contract as soon as reasonably practicable subject to (i) complying with any relevant provisions of the Agreement for Lease, (ii) providing prior written notice of the time of such works to the Employer and (iii) with minimum disruption to the operation of the Facilities and the performance of services provided to the Facilities. If there is a Systemic Defect, the Contractor shall execute all work referred to in paragraph (c) to ensure that the Systemic Defect is rectified by the replacement of all the components in the Works subject to Systemic Defect.”
“The system must be capable of (but not limited to) processing: Voltage of string Output current of string Output (wattage) of string …”
“Q. One of the problems here was that there was no remote monitoring of fans to allow for informed quick maintenance, was there? A. I believe that is the case. Q. But in any event you would also agree that it provides an additional maintenance cost, both in terms of monitoring and the costs of monitoring those fans, but reacting when an alarm is set out or when a fan or controller fails, it isn't associated with a natural air cooled transformer? A. There are potential costs, and, yes, there are disadvantages to using air cooled transformers in these terms. There are distinct advantages to having air forced transformers. Q. And if for example there is no monitoring, and the fan or their controllers fail, it's only if the ambient temperature monitoring or the transformer temperature monitoring is working that you might then catch a real risk -- a risk to equipment life and a risk to fire? A. You used the term "and" in a logical argument. For there to be a risk of problems you would need both the transformer core temperature measurement -- sorry the winding temperature measurement -- systems, plural, to go wrong, and the substation monitoring systems to go wrong. It's not either one goes wrong and you're in trouble, both have to go wrong and be left unattended for there to be any danger issue.”
“The plant shall be automated and require minimum operator intervention for normal operation. It shall be possible to start the plant and the 33kV switchgear shall have the capacity to auto re-close following an event of a grid disconnection to bring the plant to full capacity without operator intervention. The degree of automation provided shall ensure the plant can be safely and reliably re-started, and will shut down by interface with the DNO grid voltage and G59/2 requirements which are capable of being monitored from an off-site location. The Contractor shall design and provide everything necessary so that all operations including startup and shutdown can be operable remotely, including the reboot for the inverter’s shutdown, the safe auto re-closing of the G59 relays and the SCADA for the meteo station. The Contractor shall also design and provide everything necessary for: · all process and equipment alarm status to be remotely monitored; · all process and individual equipment failure and tripping status to be monitored by a sequence of events monitoring system; and · all Front End Monitoring Systems to be open access and non-propriety”
“… the Contractor warrants that it has designed the Works to have a minimum design operational life of 25 years under the operational conditions set out in the Employer’s … Requirements, provided that the same are operated and maintained (and, where relevant, replaced) in accordance with the operational and maintenance manuals received [under the contract] and provided that the individual component parts set out in Clause 4.5…shall only be warranted for the periods set out in that Clause 4.5”
“The Works shall be designed for a minimum operating life of a period of at least 25 years, taking full account of proximity to coastal environment and ground type (PH). …”
“The use of fans increases the complexity of the system and this has the potential consequence of reduced reliability and availability. It is therefore usual to have systems to detect defects in cooling in order to protect the transformer from damage. All of the transformers have winding temperature measurement and protection. Assuming this protection is functioning correctly, it should minimise the consequences of any fan failures for equipment life and also any risk of fire.”
“ One could, for example, end up with different kinds of equipment at different stages in their lives having different maintenance requirements…with the implication that required maintenance would be increased or that the required maintenance frequencies for different pieces of equipment in the same substation would be different, meaning that more maintenance outages would be necessary .”
“we are taking equipment which has already suffered from some deterioration or aging in service, and trying to restore it to an as new condition and that this might not be possible or we might not be successful in doing so .” v) Overall, a patch repair, remove and reinstall alternative would simply and rather obviously leave the Claimants with a “Heath Robinson” set of installations, not in accordance with Good and Prudent Practice, nor meeting the express obligations placed upon Wirsol that they shall provide “ a modern, functional, well-designed solar power plant capable of continuous, efficient and reliable operation with minimum maintenance. The equipment supplied shall be of proven, robust and reliable design incorporating protective systems and devices with adequate factors of safety and maintainability built-in ”, and Works that are “ new, proven and safe…designed for high availability, reliability, and efficiency ”
“Q. … The claimants' remedial scheme is much simpler from a project management perspective than your combined remedial solutions. Or indeed any of the solutions. Because it merely involves a prefabricated new substation, new external transformer and then cable diversion works over a four week programme involving a 13 day outage that we referred to earlier? A. Yes.”
“Q. But for a scheme which involves the work being done off-site, at a factory, prefabricated and therefore inherently with less project management, you've come back with -- you've agreed a figure with Mr King of 222,000. I'm putting to you that this combined remedial solution scheme or indeed any of the range would be at least that much and probably a multiple of that 222,000 figure. A. Yes, well, I don't agree, and the reason for that you're saying that the claimants' remedial scheme is prefabricated off site. It's inherently more convoluted and problematic from a project management point of view because of the very fact of having to organise all of the different bases to be procured and then for the actual switchgear housing to be delivered and installed and then for the individual pieces of equipment to have been installed, delivered and installed and then all to be re-cabled in different locations in a different set-up and then in some of the solutions in the claimants' remedial scheme you're taking the LV switchgear and actually moving it back across into the new substation. So my opinion is that's a much more complicated premise in terms of the project management -- Q. We need to move on.”
“… I know from experience that if you do work on a brownfield site to carry out modifications and do that it takes probably two to three times longer than it would do as a new installation”
“ In general any material downtime is best organised for November, December and January when expected output is low and not offset by the higher wholesale power prices ”
“If at the Contractor’s risk, the insurance cover must be sufficient to include the full cost of reinstatement, all increases in cost, professional fees and any consequential costs such as demolition. The average provision for fire risk is 0.15% of the value of the work after adding for increased costs and professional fees.”
“In point of principle a plaintiff who carried out the best and most economical repair which can be devised to defective property but is left at the end with an asset for which purchasers in the market are not prepared to pay as much as for one which never had the defects has plainly lost both the money expended on the repair work and the residual difference in value.”
“16. Mr Singer accepts that in principle it is possible for a court to award damages for a residual diminution in value of property following the satisfactory completion of remedial works if it is satisfied that such a residual diminution in value has been proved on the evidence. In my judgment he is right to make that concession… If the evidence supports the conclusion that the proper carrying out of remedial works to a residential property will nevertheless result in there being a residual diminution in the value of the property, then I cannot see in principle why the claimant should not be awarded damages to reflect that diminution in value. 17. … I wish to emphasise that is only right to award damages under that head if there is cogent evidence of a residual diminution in value…”
“…even after the specific remedies as set out by the technical and quantity surveying experts have been carried out, there is expected to continue to be a loss in value of the solar parks as a result of the alleged issues suffered and the history of the parks (APOC 51.2A). The extent of that loss at the date of judgment will in part be dependent on the court’s determination of what defects exist and which defects require remedy.”
“The extent of any blight on the solar portfolio is dependent on the court's findings on the extent of any defects with the assets and breaches of warranties by the defendants. The loss to the Claimants' in the case where no material defects or breaches are identified with no long-term impact on the performance of the portfolio would be negligible. The loss to the Claimants' in the case where material defects are identified and remedied would likely only have short-term impacts on the performance of the portfolio, and no long-term impacts on the Claimants once a reasonable operating history for the portfolio is re-established. The loss to the Claimants would not be substantial in such a case. The loss to the Claimants' in the case where material defects are identified but not remedied could have long-term impacts on the physical and financial performance of the portfolio. Only in such case could the loss to the Claimants be substantial. In light of the significant difference of opinions expressed by the defects experts in their Joint Memorandum it has not yet been possible to quantify the loss in each of the above cases. I anticipate that there will be substantial overlap between the valuation of the loss for blight and loss claimed in respect of Topco shares which will need to be addressed in assessing the total claim so as to avoid double counting.”
“9.3.1 This claim is in relation to the impact on the valuation of the solar power plants of the alleged defects. In a shorthand manner this has been referred to as blight. That is caused by a mix of: (i) the past history of the site, which has a significant impact on the current value of the company; (ii) the impact of the financial issues that the company has faced and will continue to face and the increased risk that poses; (iii) the period for which the plant is expected to continue before full remediation is achieved; and (iv) the ongoing extent of risks related to the original breaches that have not been remedied.”
“9.3.3 The experts have agreed that even after the specific remedies as set out by the technical and quantity surveying experts have been carried out, there is expected to continue to be a loss in value of the Solar Parks as a result of the alleged issues suffered and the history of the parks (APOC 51.24). The extent of that loss at the date of judgment will in part be dependent on the court's determination of what defects exist and which defects require remedy. 9.3.4 We disagree however as to how and when that loss is to be considered. Mr Slark in the joint statement indicates that if material defects are identified and remedied that “would likely only have short-term impacts on the performance of the portfolio, and no long-term impacts on the Claimants once a reasonable operating history for the portfolio is re- established. The loss to the Claimants would not be substantial in such a case.” 9.3.5 I consider that we have to assess the loss of value now, at the time of judgement, not what it might be in the future if : (i) an appropriate remediation programme is successfully completed; and if (ii) a reasonable operating history for the portfolio is then established; refinancing is achieved as assumed; and if (iii) no greater risk than normal for future operating parameters is perceived (beyond what would be typical for such a plant); and if (iv) no risk is perceived of a lower useful life as a result of the impact of the defects having existed for several years and any impacts of that on other parts of the plant. 9.3.6 If all of the requirements happen then in those circumstances, several years in the future the valuation might increase from where it is now. Equally if: (i) the remediation programme is not of a suitable scope or is not successfully completed; or if (ii) there continue to be operational issues post remediation; or if refinancing is not achieved as assumed; or if (iii) a greater risk than normal for future operational parameters is perceived; or if (iv) any risk is perceived of a lower useful life than originally expected then the valuation might decrease from where it is now. 9.3.7 When looking at the value now, before any of these are fully known, we have to consider the risks that would impact on valuation. The difference between the upside in valuation and the downside is notable. Mr Slark seeks to apply what could theoretically be the case at some stage several years into the future if investors are fully satisfied in all the above respects. I do not consider that that is an appropriate approach. 9.3.8 Looking now toward the future, the current value will be lower than it was originally expected to be precisely because all of those risks still apply and the greater the difference in perception of risk, the greater the difference in value I will explain more from a potential investor’s perspective on each below: (i) Operating parameters: To date the plants have suffered from reduced output as a result of the “clipping” need described above, as well as repeated tripping of plants causing outages. If a comprehensive remediation plan is implemented then after that date operating parameters should return to what was originally expected. However, until tested for an extended period, this cannot be confirmed and investors are not going to simply assume it will all go to plan. The remediation plan in itself is a risk even if expected to return operating parameters to where they should have been; (ii) Risk of catastrophic failure: One plant (Balcombe) has already suffered a fire. The concerns with operating several plants at greater than the recommended rating for transformers, the lack of certain circuit breakers and the failure to correctly manage humidity (particular condensation) in substation housings lead to increased risk of a substantial incident both prior to remediation and still (to a lesser extent) afterwards. Investors will be cognisant of such a risk and even post remediation some doubt is likely to remain in investors’ minds; (iii) Useful economic life: Increased trips and running at a rating higher than recommended are both recognised as leading to an increased risk of the plant not being able to deliver for the full economic life originally expected. Even if some components of the plant are replaced in a suitable remediation scheme, any new purchaser would need to be completely comfortable that there are no impacts on economic life arising from the prior running patterns; and (iv) Refinancing: I talk of extra refinancing costs below assuming a slightly increased interest rate but assuming that refinancing happens with no further issue. However, because of its history and the risks above, although I assume refinancing at only a slightly elevated interest rate, that may not be the case. Lenders get paid relatively little so accept correspondingly little risk and the fact that refinancing was achieved in 2018 does not guarantee it in what may be a very different world in 2023. 9.3.9 The other point to note in terms of valuation is that for an operating plant with a good operating history there is an ability to sell the plant to secondary market investors who take less risk (so will only take plants that do not have significant risk issues) and ask for less return precisely because they are taking less risk. This is a valuation upside for a project owner such as Toucan. That no longer applies in this case as given its history low risk investors would not be interested in it.”
“Q. … Well, I'd suggest in circumstances where any alleged defects are remedied, there would be no basis for believing there to be reliability issues at that point, would you agree with that? 797. A. But that's a different point in time. One of the basic tenets of valuation is you look at what is the position at the time at which you're carrying out the valuation. So if I were carrying out a valuation after certain things had been remedied and then on the basis of that I was carrying out a valuation, that's a different basis from where I am here.”
“Q. Okay. Well, I'd suggest in circumstances where any alleged defects are remedied, there would be no basis for believing there to be reliability issues at that point, would you agree with that? A. But that's a different point in time. One of the basic tenets of valuation is you look at what is the position at the time at which you're carrying out the valuation. So if I were carrying out a valuation after certain things had been remedied and then on the basis of that I was carrying out a valuation, that's a different basis from where I am here.”
“Once the reputation of the developer (Wirsol) is tainted by common problems on multiple sites, I consider that it is harder to convince an investor that although multiple sites have problems, the rest are fine… The plants were constructed and designed by the same company, over the same period.”
“Now I understand that point as regards the Wirsol sites but it's wrong as regards the Abakus sites isn’t it? A. Yes, that is misstated in which case it would be 15 out of 19. Q. Just to check what you're agreeing with, so that I don't bank more than you've offered, you're accepting I think that the blight would only apply to the sites Wirsol is the constructor for? A. Yes.” and in re-examination: “Q. So if Abakus is a third party contractor you're content these sites would not be blighted? A. If it's completely independent, yes.”
“[a]n investor may look at the sites individually but they will still be looking at the developer in terms of who is actually behind them. If you look at individual sites you do not ignore who the manufacturer is”
“8.8.2 I find that the Claimants’ position on a 1% (or greater) increase in its required rate of return is untenable, when placed in the appropriate context of the risks of a solar park. Except in their exposure to wholesale electricity price volatility (an aspect that is not relevant to this claim) solar parks are inherently low risk, and so any change in risk premia to reflect a change in circumstances, such as loss of warranties, if found to be justified, would be of the order of a few basis points (where a basis point is one hundredth of a percentage point). I can find little to support an increase in the required rate of return above 0.125%, suggesting that the present value of any loss would be unlikely to exceed£509,438 . 8.8.3 There may be considerable merit in revisiting the assessment of this claim after the court provides its findings on remediation and on other aspects of the various claims.”
“By early July 2018 Wirsol… had rejected a vast majority of the [SPVs’] EPC claims that the solar park was defective. Whilst the defects were not significantly impacting short term cash flows, the [SPVs] faced significant work over the longer term and I considered this would increase substantially the likelihood that the Banking Facilities (which were 18 years) suffered a default. Further BLB had also indicated that the [SPVs] terminating the [EPC Contracts] with Wirsol would also be an event of default - and the [SPVs] had no choice but to do this considering the breaches of those contracts. I considered the most appropriate solution was to refinance with a shorter term investment - in this case 5 years. This was a significant step backwards for the SPVs and RFE because the refinancing risk after 5 years is substantial as well as the costs to exit the swap. I consider the loss resulting from having to refinance again in the future and costs to exit the BLB Banking Facilities to be£6.7m .”
“We are meeting Karin [Karin Schramm, of BLB] next week btw - we are paying her out. Pls keep confidential until we’ve told her - paying her out allows us to release the trapped cash from [the Debt Service Recovery Account] and just generally in structure and this helps u with ALE.”
“Karin, Thanks again for the positive and pragmatic approach on our proposal to repay the two facilities (Wirsol 45 and Wirsol 60). As I said when you came in, you've been our best lender. I'm sure we will be involved in future deals somehow. Also, thanks for asking Eversheds for a quote to prepare the docs to release the security. Please send this when you have it. From our side, the team here are making sure the right amount of funds is in the right place at the right time. We've been through the facilities docs and got our view of the redemption journey, but makes sense we work through it openly to avoid surprises. Smooth execution of this is a priority for the whole team here so if you are worried about anything please give me a call. In terms of dates, we are working towards31 August 2018 . Principal Lx Interest from last calc date (28 Feb) to repayment date (31 Aug) Ex Break costs Ex Swap valuation Ex DSR Balance Ex Redemption amount due to Bayern Ex In terms of the document, we are aware the c17.3 sets out the formal notice periods and we will submit these in due course. Anyway, the point of whole mail is to ask if BLB have pro forma redemption statement you wish to use again? We can submit ours for your approval if not. This is being discussed later in the week with our investors, so if you can turn this round quickly by pressing a button on your system I would be grateful”
“that's exactly the point, we need to understand the likelihood for the button to be pushed on time so the repayment does occur on the 31.08. Sheeraz's informed us that you are terminating the EPC, which is a potential EOD under the Facilities Agreement, so as you will understand we need to understand the mechanics and timing of the repayment, which is crucial for us to occur on the 31, as I have also mentioned in our call.”
“We understand that you are planning to prepay, but as long as we have not seen the funds actually coming in, and given the below is a potential event of default under the Facilities Agreement, we need to protect our position and understand the reasons behind termination of the EPC and how you are planning to remedy it. We think a face to face meeting would indeed be very helpful and as a matter of urgency, would like this to happen tomorrow”
“We are very close to having funds organised to facilitate the prepayment, however it is currently looking like funds will not be in our control until 28 th August at the earliest now. We will not be in a position to sign the notice of voluntary prepayment until our account is in credit for cleared funds. This would mean that we would miss the 31 August prepayment date if we cannot reduce the 5BD notice requirement. Karin/Suzy, is there any scope from BLB's side to reduce the 5BD requirement if it means we're able to achieve 31 st August? If so, what is the minimum notice BLB require? If there is no scope to reduce the notice period we expect to be in a position to prepay the facilities in the week commencing 3rdSeptember. Let me know if you have any questions.”
“Following our conversations, we would like to take this opportunity to provide you with further information regarding the follow on investment to replace the Senior Debt with the bank ("BLB') and buyout of existing bond holders across the Toucan 60 and Toucan 45 portfolios. The refinancing represents an opportunity for [redacted] to have first ranking security over the assets of the portfolio and receive the returns that the bank has been receiving to date. The Toucan 19 Solar Farm Portfolio (Toucan 45 & Toucan 60) is operating well and within the predictions expected at the outset. This portfolio has already provided its first interest payment to existing bond holders. It is Rockfire's intention to make the follow on investment before the end of31 August 2018 to avoid early repayment penalties and for Rockfire to demonstrate to Thurrock Council our commitment to delivering requirements efficiently.”
“Toucan Gen Co Limited completed the acquisition of the portfolio on25 May 2017 and took over the operation of the 9 solar PV projects. Overall the sites are operating well and within the predictions expected at the outset. In fact we are within 2.5% of our expectations against revenue and costs to date and overall 2.5% up against our EBITDA expectation. Two Bayerische Landesbank compliance covenant reporting have been completed and debt cycles have been completed without issues. All bond debt payments have been met during the period. At acquisition all sites were fully operational although one site had not achieved the Provisional Acceptance Certificate which was completed on17 August 2017 . Six solar sites have achieved intermediate Acceptance Certificate, two are under discussion with the EPC and 1 is due in September 18.”
“I’m not working for someone that just treats us like a cashpoint for his own equity when [the] taxpayers and signed contracts [sit] above his equity”
“Q. I will come to what the investors are said by you to know. I am currently asking you questions about the formal FSMA document you issued. It says the existing bank debt is 85 million. It says you are raising 85 million. It says you are going to use the new bond funds to pay off the existing bank debt. So it must be saying that you are going to use the 85 million you raised to pay off 85 million of existing debt? A. No, we used that money to pay off the existing debt and to pay our fee. Q. And what you have said there, as I just put to you, is not true, is it? A. No, it is true. I raised the money. I paid off the debt. I paid my fee. Q. Mr Kavanagh, please listen to the question. What I just put to you as being what this prospectus says is not true, is it? A. I am -- I can't agree with you, I am afraid. Q. And you knew that you were not going to pay back the existing debt of 85 million with this bond, didn't you? A. I knew we would pay back the buy in debt whatever that cost would be at the time of paying it back and that the value -- Q. Are you deliberately ignoring the question? A. -- and that the balance would be to pay the commission fees due to the Rockfire Capital from the issuer.”
“The loss resulting from the refinancing is based on the net difference between the BLB capital and interest outflows and the new bond (including the assumed refinance after year 5) capital and interest outflows.”
“The initial sums are enlarged in the bond repayment profile as interest accrues on those sums; and then diminished in the final loss analysis by the application of a discount rate. However, the interest rate and discount rate are very similar and largely net off. As a result, the total figure claimed as a ‘loss’, in respect of the sums used for these purposes [i.e. working capital and the arrangement fee] is almost the same as the original capital amounts.”
“15.1 Notice to Correct If the Contractor fails to carry out any of its obligation under this Contract, the Employer may by notice require the Contractor to make good the failure and to remedy it within the specified reasonable time. 15.2 Termination by Employer The Employer shall be entitled to terminate the Contract if: (a) the Contractor fails to comply with Sub-Clause 4.2 (Performance Security) or with a notice under Sub-Clause 15.1 (Notice to Correct)”
“The Contractor shall be entitled to sub-contract the performance of the whole or any part of the Services to any sub-contractor, provided that such sub-contractors and the terms and conditions of their appointment have first been approved by the Employer in writing, such approval not to be unreasonably withheld.”
“ Period up to16 October 2018 12. We note that the Termination Notice seeks to adhere to clause 20.5 of the O&M Contracts, which provided that termination is effective 30 business days after receipt of the notice by Wirsol (i.e.16 October 2018 ). 13. As stated above, we consider the Termination Notice to be ineffective and it amounts to a repudiatory breach which Wirsol has now accepted. 14. However, in an effort to be constructive and to enable an orderly hand-over between Wirsol and Toucan, Wirsol is prepared to agree enter new agreements upon the same terms of the O&M Contracts for the period between now and16 October 2018 upon the understanding that such agreements are fresh contracts which will terminate on16 October 2018 . 15. Please can you indicate Toucan’s proposal by return. Pending any further response, Wirsol will perform no further work under the O&M Contracts.”
“… Our second letter of3 September 2018 is a valid notice of termination of the O&M Contracts and that that termination will take effect on16 October 2018 . The O&M Contracts remain in full force and effect until16 October 2018 when termination under the notice dated3 September 2018 takes effect. Consequently, there is no need for the SPV Companies and Wirsol to enter into new O&M contracts for this period and the SPV Companies will not do so. Until termination of the O&M Contracts takes effect on16 October 2018 , Wirsol remains obliged to perform its obligations under the O&M Contracts. Wirsol’s unilateral decision to abandon the sites is a further breach of the O&M Contracts. We therefore require that Wirsol confirm by no later than 6pm on6 September 2018 that it will continue to perform its obligations under the O&M Contracts, until they are terminated on16 October 2018 . If you fail to respond by 6pm today then we will proceed on the basis that Wirsol has abandoned the sites. For the avoidance of doubt we hereby put you on notice that such abandonment will mean the SPV Companies will suffer loss and damage and will have no alternative other than to turn off the PV plants at the sites. The SPV Companies take health and safety extremely seriously and they are not prepared to allow sites containing HV equipment (with identified defects) to operate without maintenance and monitoring being performed. Further, as you are aware, if Wirsol does abandon the sites then there is no limit on the damages recoverable by the SPV companies pursuant to clause 13.3 of the O&M Contracts. You have until 6pm today to notify us of your client’s position.”
“On5 September 2018 Wirsol unilaterally ceased to perform its obligations under the O&M Contracts and abandoned the sites. Wirsol left the sites and the HV equipment unmonitored and unmaintained, making no attempt to hand over the sites. Wirsol has not even handed over keys and access codes to the sites. This evidences a wholesale and flagrant disregard for health and safety by Wirsol. It is entirely inconsistent for Wirsol now to say it is trying to achieve an orderly hand over. In the circumstances the SPV Companies cannot reasonably be expected to enter into any further contracts with Wirsol for the operation and maintenance of the sites. In the circumstances the SPV Companies fully expected Wirsol immediately to deliver up all keys, access codes, records and documents (in any form) relating to the sites and services performed by Wirsol under the O&M Contracts. As part of the handover an authorised person will be required to transfer across the HV control (to include a switch of the site and verification of drawings). The SPV Companies will provide a list of dates that facilitate this handover. The SPV Companies reserve all their rights under the O&M Contracts and more generally.”
“Save as provided in Clauses 12 and 3.6, the Contractor shall have no liability to the Employer under or in connection with this Agreement in respect of loss of profits, loss of use, loss of production, loss of business, loss of business opportunity, or any claim for consequential loss or for indirect loss of any nature notwithstanding that the Contractor shall be liable in respect of any claim by the Employer for any costs arising as a result of termination of this Agreement.”
“(c) the Contractor has paid (or the Employer has recovered) all Delay Liquidated Damages and Performance Ratio Damages due and payable under this Contract”
“We make reference to the EPC Contract between WEL Solar Park 16 Limited and Wirsol Energy Limited, dated 27 th October (the "Contract") and the PAC Report issued by Technical Advisor RINA Limited. Terms defined in the Contract shall have the same meaning when used herein. This is the Provisional Acceptance Certificate and Provisional Acceptance Report issued for the purpose of Clauses 10 and Il of the Contract.”
“Further to clause 10 of the EPC Contract please find enclosed the signed PAC certificate, which also formally acts as the Taking Over Certificate. This is provided strictly on the basis that the issue of this Taking Over Certificate does not release the Contractor from any of its obligations under the EPC Contract and shall not be interpreted as a waiver by the Employer of the performance by the Contractor of any of its obligations under the EPC Contract. The Employer reserves all its rights under the EPC Contract. Please confirm your receipt and acceptance of this as the Taking Over Certificate for this site.”
“If the Employer considers himself to be entitled to any payment under any provision of this Contract or otherwise in connection with this Contract, and/or to any extension of the Defects Notification Period, it shall give notice and particulars to the Contractor. However, notice is not required for payments due under Sub-Clause 4.19 (Electricity, Water and Gas) or for other services requested by the Contractor. The notice shall be given as soon as reasonably practicable after the Employer became aware of the event or circumstances giving rise to the claim. A notice relating to any extension of the Defects Notification Period shall be given before the expiry of such period.”
“No Group Company is party to or subject to any material agreement, arrangement, obligation or commitment except the Contracts.”
“14.3 In relation to each Contract for the relevant Subsidiaries, they are legally binding on the Subsidiaries and, so far as the Seller is aware on the other parties to them and are in full force and effect. Each of the Contracts is valid and binding and has been complied with in all material respects by the relevant Group Company and all payment obligations thereunder have been fulfilled (in full) by that Group Company by the applicable contractual due date where the contractual due date was on or before the date of this Agreement. So far as the Seller is aware, there are no events or circumstances likely to give rise to the termination, rescission, avoidance or repudiation of any of the Contracts and no notice of termination or of intention to terminate has been given or received in respect of any of them.”
“11.1 The Seller shall indemnify and hold the Purchaser harmless against any Losses and Expenses arising in relation to: … 11.1.3 any breaches occurring on or before the date of this Agreement, of the Facility Agreement and/or any agreements entered into in connection with the Facility Agreement…”
“The Seller shall not be liable in respect of a Claim (save for any Claim under the Tax Deeds) to the extent that such Claim, or its subject matter, arises from or in connection with, or consists of, any fact, matter or circumstance which has been Disclosed.”
“1.3 For the purposes of this Schedule, except where expressly provided otherwise “Claim” includes any claim against the Seller arising out of or in connection with: 1.3.1 Warranties; and/or 1.3.2. the Tax Deeds.”
“If the Time for Completion was not met, please confirm whether any liquidated damages were claimed from the Contractor. Yes damages claimed and agreed with EPC contractor Please confirm the value of the liquidated damages claimed. Please also confirm whether these have been paid by the EPC contractor to the SPV. See below, answered in Q35 =£76,781 was claimed and yes all invoices paid Was this claimed in relation to the failure to meet the Time for Completion only or is this the total amount of liquidated damages claimed in relation to the failure to meet both the Target Commissioning Date and the Time for Completion? The LD's were for PAC Delays ”
“IV. By countersigning this Taking-Over Certificate, the Contractor acknowledges and agrees that: a. an amount of£63,000 will be deducted from Payment Milestone 9 to take into account an amount of Delay LDs [i.e. liquidated damages] due from the Contractor to the Employer [i.e. WEL Solar Park 10 Limited, the SPV in relation to the Mill Farm site]; … VI. This Taking-Over Certificate and the terms set out herein are not intended to release the Contractor from any of its obligations under the EPC Contract, nor shall it be interpreted as a waiver of the duties therein. The Employer reserves all its rights under the EPC Contract.”
“14.2 The copies of the Contracts, and any material variation to such Contracts, as contained in the Data Room are true and complete copies and, save as Disclosed, there have been no material variations to such Contracts. 14.3 In relation to each Contract for the relevant Subsidiaries, they are legally binding on the Subsidiaries and, so far as the Seller is aware on the other parties to them and are in full force and effect. Each of the Contracts is valid and binding and has been complied with in all material respects by the relevant Group Company and all payment obligations thereunder have been fulfilled (in full) by that Group Company by the applicable contractual due date where the contractual due date was on or before the date of this Agreement. So far as the Seller is aware, there are no events or circumstances likely to give rise to the termination, rescission, avoidance or repudiation of any of the Contracts and no notice of termination or of intention to terminate has been given or received in respect of any of them.”
“If, as the Defendants allege, no such Option existed as at the SPA date, then the failure to disclose the said Option and any agreement to assign and the assignment thereof in Schedule 6 meant that RFE paid for a non-existent asset and thus overpaid the SPA consideration by an equivalent sum”
“… Each of the Contracts is valid and binding and has been complied with in all material respects by the relevant Group Company… So far as the Seller is aware, there are no events or circumstances likely to give rise to the termination, rescission, avoidance or repudiation of any of the Contracts and no notice of termination or of intention to terminate has been given or received in respect of any of them.”
“The Purchaser shall not be entitled to make a Claim (other than a Tax Claim) after Completion in respect of any matter, fact or circumstance within the actual knowledge of the Purchaser and the Purchaser’s employees”
“ Inverters curtailed. Oversizing performance higher in summer months. Busbar sizing, transformer sizing .”
“ Exclusions from clause 12 12.2 Notwithstanding any other provision of this Agreement, the provisions of this Clause 12 and Schedule 5 ( Limitation of Seller's liability) shall not apply to any claim made against the Seller in the case of fraud.”
“The Purchaser agrees and authorises Wirsol Energy Limited (“WEL”) to use all reasonable endeavours (A) to seek an Asset Life Extension (as defined in paragraph 10 below) for each of the Projects listed in the schedule to this deed on behalf of Subsidiaries and (B) satisfy the Conditions Subsequent, in each case prior to31 December 2017 (the “Asset Life Extension End Date”).”
“the extension of the asset life of a Project from its asset life as at the date of this deed… by a minimum of five years, as evidenced by the following: (a) an extension of the term of the lease of the Property (or option to obtain an extension of the relevant lease or a lease option in respect of such Property…) and any rights necessary and ancillary to the relevant lease or lease option… (in each case, a “Property Variation”), in a form satisfactory to the relevant Subsidiary (acting reasonably), with the relevant landlord which the landlord has confirmed in writing to the relevant Subsidiary that he will execute and deliver subject only to the receipt of the counter-signature by the relevant Subsidiary to such lease extension or option; (b) all information required by the Purchaser to register the relevant Property Variation at HM Land Registry…; and (c) a copy of up to date planning permissions in connection with the ongoing operation, maintenance and decommissioning of the Project allowing… for an electricity generation period which extends asset life of the Project as at the date of this deed… by an additional five years.”
“BAYERISCHE LANDESBANK / PROJECT WIRSOL Conditions Subsequent in accordance with the Facilities Agreement Status as at:24 May 2017 ” and notes that: “All paragraph, Clause and Schedule references are to the relevant paragraph, Clause or Schedule of the Facilities Agreement. Unless otherwise defined in this Checklist, terms used in this Checklist have the meanings given to them in the Facilities Agreement.”
“Each ProjectCo [i.e. SPV] shall procure delivery to the Agent [i.e. BLB] of a certified true copy of each Final Acceptance Certificate within ten (10) Business Days of the date of issue”
“10 Business days from the date of issue of the Final Acceptance Certificate (2 years after the PAC [Provisional Acceptance Certificate])” and in the “Status” column says: “Outstanding (not yet due)”
“7. … The Guarantor undertakes to pay to WEL… within 10 Business Days of the later of (i) the Payment Date and (ii) receipt of a valid invoice issued to the Guarantor from WEL an amount equal to the greater of (a)£2,000,000 ; and (b) the aggregate value of each of the Asset Life Extension Amounts for each Asset Life Extension received by the Asset Life Extension End Date. … 9. If all the Conditions Subsequent have not been satisfied in accordance with this deed by no later than30 June 2018 then WEL shall not be entitled to any payment under this deed. … 13. “Payment Date” means the later of (i)31 December 2017 and (ii) the date that all the Conditions Subsequent have been (i) satisfied or (ii) waived by [BLB] and by the Guarantor [i.e. Toucan Energy] (acting reasonably).”
“Save as expressly modified herein, Clauses 18 ( Confidentiality ), 19 ( Assignment ), 20 ( Variation ), 21 ( Invalidity ), 22 ( Costs and Expenses ), 24 ( Entire Agreement ), 25 ( Counterparts ), 26 ( Time of the Essence ), 27 ( Notices ), 29 ( Governing Law and Jurisdiction ) of SPA1 shall apply to this deed mutatis mutandis, save for any reference to the Seller shall be construed as a reference to [Wirsol] and any reference to the Seller’s Guarantor shall be disregarded.”
“31.23.1 Each ProjectCo shall procure delivery to the Agent of: … 31.23.1.1 a certified true copy of each Provisional Acceptance Certificate within five (5) months of the date of this Agreement (other than in the case of Project Wrea Green, in respect of which Wrea Green ProjectCo shall procure the delivery of the same within ten (10) Business Days of the date of issue); 31.23.1.2 a certified true copy of each Final Acceptance Certificate within ten (1) Business Days of the date of issue; …”
“The reason [Mr Kavanagh] wanted the CSs to be included was because under the facilities agreement further distributions could not be made until the CSs were satisfied.”
“[t]he conditions subsequent principally related to the matters arising under the EPC Contracts and OMs and I wanted to make sure RFE’s investment under the SPA was preserved by them being properly and promptly closed out. Incorporating the conditions subsequent under the Banking Facilities to the ALE was a sensible way of approaching this.”
“Q. … My question to you is, its right, isn't it, condition subsequent 49 does not purport to impose an obligation to comply with the EPC contracts or O&M agreements, generally? … A. … What I was saying is that the context of the ALE document has these conditions subsequent in it for purposes of compelling Wirsol to ensure that they carry out all of their obligations to do with the banking facility. I go back to my original point, which is it was always implied within the ALE these matters would be closed out in accordance with that schedule. So I don't agree with your version of that. I don't know what more I can say about that.”
“After chasing Eversheds (Rockfire) and Gowlings in relation to a number of matters on their side of the fence, including the proposed waiver letter to be signed by BLB and Rockfire in respect of the FACs (draft waiver letter attached), we have been informed by today by Gowlings that Rockfire would prefer the requirements to deliver the FACs to remain an ongoing condition subsequent. No reason has been provided other than an indication that this is a commercial decision on the part of Rockfire and that any concerns on our part should be picked up directly with Rockfire.”
“… in relation to BLB unilaterally dropping the requirement for the FCA CS, it would seem that you are able to and moreover, you are completely covered in the facilities agreement per the mail and terms below. This matter is “uber” important to me, and something that I really need to quash ASAP - once again your help is appreciated. I am not copying anyone else as I’d rather leave it to you to determine the best route of communication, nevertheless, feel free to forward both internally and to [Eversheds]. Thank you.”
“ Seek solution to the FAC CS - Action Mark I have spoken with BLB and they are happy to accept dropping the CS without an undertaking from the borrower (important point and the[y] understand the commercial sensitivity). Now it is more a question of mechanics, we have agreed the following steps:- MH [Mr Hogan] will write to BLB / EVS to agree the language and that they can sign-off Upon agreement on point 1 - MH will write to BLB / EVS with RFC / CMS in copy citing the signed ALE and that WEL [Wirsol] are authorised by the Purchaser to satisfy both (A) and (B) below [clause 2 of the ALE Contract], specifically the Conditions Subsequent in each case prior to 31st Dec BLB will respond giving said confirmation CMS will seek waiver of said CS via Gowlings who will struggle to resist given that the bank do not need an undertaking. …”
“Dear Karin - I am writing to you as we are in the process of meeting our obligations under the Asset Life Extension (“ALE”) document that has been agreed between RFE Gen Co Ltd. (the “Purchaser”) and Wirsol Energy Ltd (“WEL”), as we discussed previously. Whilst I am not attaching the ALE, per the agreement the Purchaser agrees and authorises WEL to use all reasonable endeavours to seek an asset life extension to the projects AND satisfy the conditions subsequent (“CS”) prior to31st December 2017 . I draw your attention to a specific CS regarding obtaining FAC on the WEL45 portfolio whereby the CS cannot be satisfied by31st December 2017 given PAC only occurred during the summer of 2016. We also note that FAC is not required as a CS within the subsequent WEL60 portfolio. We are still at a loss as to why FAC would be a CS given that the bank are protected in multiple ways, namely – · The EPC contract has a specific requirement to deliver FAC · The EPC contract has an on-demand bond attached until FAC is achieved · Furthermore clause 29.6.1 and 31.15.4 of the facilities agreement give BLB all the necessary protections required. These have been discussed previously and Rockfire (via Gowlings) do not wish to give an undertaking for the delivery of FAC on the WEL 45 portfolio… Therefore, in the capacity of having the authority to make the request for a full and final waiver of this specific CS, per the ALE, we hereby request that Bayern LB confirm approval for dropping the requirement for said waiver without any further undertakings of the Borrower. Would you please confirm at your earliest convenience - all parties are copied accordingly? Thank you for your attention to this matter. Kind regards, Mark Hogan”
“Mark, Fine for BayernLB. Best regards Karin Sent from my iPhone”
“I very much doubt this was agreed with us. The original proposal was that we took on the responsibility for delivering the FAC to BLB, which we pushed back on. The new approach just looks like Business As Usual, where FAC has to be delivered as part of the Facilities agreement, but it is no longer a condition subsequent for us or Wirsol. The CS was impossible given the deadline of31/12/2017 to complete FAC for sites that have only recently been through PAC or IAC, so this seems like the most sensible conclusion. I think we should agree to this. Andy, let me know what you think or if you want to chat this through at all? Thanks, Steve.”
“Mr Hogan did not send me (or anyone in my team, including either Eversheds or Gowlings) the email of 9:431 November 2017 . It is directly at odds with the recent discussion between us. It took until 4:32pm on2 November 2017 for it to be sent to us from Gowlings (this email is privileged and redacted) and by this time BLB had already commented. I did not see Mr Croucher's response before he sent it to Gowlings 5 minutes later but I saw it on the following morning and I agree with it. He is correct when he stated "I very much doubt this was agreed with us" I confirm this is correct and there was no such agreement.”
“I saw Mr Croucher repeated Mr Hogan's mistaken text to BLB (on the basis the due date was not31 December 2017 under Banking Facility 1 or in fact the ALE) regarding the date of31 December 2017 describing it as: " impossible given the deadline of31/12/2017 ". I believe this date would have been adopted from Mr Hogan in his request to Karin Schramm of BLB which we had only just seen when Mr Hogan stated "the CS cannot be satisfied by31st December 2017 given PAC only occurred during the summer of 2016." Again, I considered all this would be sorted in the documentation of the matter. Consistent with our discussions in September 2017 I was told that BLB was in principle happy to provide the SPV Obligors a waiver in this respect. Mr Croucher discussed that the SPV Obligors should proceed with documenting the proposed waiver and amendment to Banking Facility 1”
“On W45, we need to agree the waiver with regard to FAC that was agreed by Mark Hogan and BLB. Effectively this removes the requirement to deliver FAC notices before the end of this year, as this will be impossible to do. … Hopefully we can get the CSs complete without further drama.”
“Jenny, Rockfire have confirmed that they are fine with this waiver. … Kind regards, Erika [Personalised email signature]”
“Q. I put to you, Mr Kavanagh, that what has happened here is clear: you have agreed with Mr Croucher in saying that you should give a waiver under the ALE contract of CS49, and then Gowlings had been instructed, either directly on your authority or on behalf of Mr Croucher, who had authority for this purpose, to respond on that basis? A. No. The only waiver that was granted was in relation to the banking obligation. That was it. Not the ALE.”
“[t]he WIRSOL stuff has been going on for too many months what’s the issue? Can this not just all be closed off now?”
“[t]he latest weekly update I have seen from them says out of 19 they have got 11 sites and the amount to pay is the original 2m plus£700k can you kindly break all this down against the contract so everyone at Rockfire is very very clear on all liabilities to Wirsol ”
“ Wirsol - We are working through the CS list, which is nearing completion. The key ones being chased are the planning permission sign-offs. ”
“BAYERISCHE LANDESBANK / PROJECT WIRSOL Conditions Subsequent in accordance with the Facilities Agreement Status as at:12 February 2018 ”
“Yes, we are referring to the same thing, BLB has confirmed that they will need a waiver letter signed.”
“I am saying that meeting was two years ago. From my memory of that meeting, I was very, very clear to Mr Hogan why I was making an offer of 2.5 million. What was discussed at that meeting, again, was very clear, that Wirsol's conduct in relation to the sites, that we paid very good money for, was a massive concern, and that we needed to come to some sort of resolution of all of these issues, where he would take his responsibility for actually making sure that the sites, that we had paid good money for were going to last for 85(?) years. And we would seek to deal with the ALE part in this manner, without avoiding -- needing litigation. And the point of CS49 was not discussed by your client and it wasn't discussed by me either. The vast majority of that conversation, from my recollection, was actually how to resolve the dispute between us on both camps. And no, I didn't mention CS49 at that meeting. But neither did your client.”
“The meeting today wasn't as productive as I would have hoped, but on the positive side we are still talking. Liam is basically saying that his guys "screwed" up on the valuation and overpaid us — this is not true but that's his perception. He also said that the Asset Life Extension ("ALE") doesn't give him any benefits, that's also not true. My response to this was "why get us to do it in the first place, if that's the case" ? His recollection of events is screwed but ultimately, it doesn't help us. As of now he is offering to pay£2.5m on the basis that we write off the entire balance — that clearly doesn't work as it would mean a£2.7m P&L hit (we invoiced£5.2m for the ALE). Furthermore, the timeline for this£2.5m wasn't clear. He has said that he needs a clean break settlement and if we cannot find a solution, he may as well pay nothing...”
“I believe that the natural reading of this email exchange is clear and unambiguous. The purpose for the waiver was clearly spelled out in Mr Hogan’s email as well as the email title: it was a request to waive the Condition Subsequent in the ALE Letter. The parties that had to give the relevant waiver were Bayerische Landesbank and Toucan Energy (then known as Rockfire Energy Holdings Limited). Bayerische Landesbank confirmed that the waiver was “Fine for BayernLB”
“15. The critical factor in the present case is that the person who has to act in a commercially reasonable manner in determining whether consent is to be given is “the Guarantor” namely Barclays itself. It is from Barclays that consent is to be obtained and it is Barclays who has to determine whether that consent is to be given, albeit in a commercially reasonable manner. It is the manner of the determination which must be commercially reasonable; it does not follow that the outcome has to be commercially reasonable although, if it is not, that would no doubt cause one to look critically at the manner of the determination. 16. One then has to ask whether, in determining whether or not to consent to early termination, Barclays can take account of its own interest in preference to the interest of Unicredit. To my mind the answer is that it can, because any commercial man whose consent to a course of action is required but to whom the determination (whether to give that consent) is entrusted would think it commercially reasonable to have primary regard to his own commercial interests.”
“19. It is not easy to express a test for commercial reasonableness for the purpose of this (let alone any other) contract but I would tentatively express it by saying that the party who has to make the relevant determination will not be acting in a commercially reasonable manner if he demands a price which is way above what he can reasonably anticipate would have been a reasonable return from the contract into which he has entered and which it is sought to terminate at an early date.”
“What was certainly plain is that, between the 28 February letter in 2018 and this witness statement of 16 October, so that is a period of around eight months, Toucan Energy had never contested the clear suggestion made by the claimant in the letter of 28 February that all of the relevant conditions had been met or waived, and that was a letter addressed specifically to the defendant. It is absolutely remarkable to me that [Toucan Energy] did not come back and say “What do you mean? Of course, they have not been met and they have not been waived”, if that was something in its mind at the time, because, if that was right and if it could really demonstrate that a condition precedent had not been met and the longstop date had now gone past, that was the end to the claimant’s claim. But [Toucan Energy] never asserted anything of the kind…”
“It says clearly "Asset life extension, condition subsequent, waiver request". As I say, I think it's abundantly clear and it was clear to Gowlings and as I say there was email correspondence that makes this clear that Gowlings understood the effect of the condition subsequent on the ALE. At the time I do not believe there was any doubt in their minds or our minds what the effect of this was intended to be. They - and at no point after this, for months and months, beyond the point where my firm ceased to act for it, did they ever raise any concerns that they had not been waived.”
“No waiver will take effect if the person seeking the waiver has failed to disclose to the grantor every material fact or circumstance which (so far as the person seeking the waiver is aware) has a bearing on its subject matter.”
“Mr Kavanagh had concerns some of the equipment would not have an operational life long enough to justify the asset life price. As a seller we were not the developers or EPC but a fund and we were not able to give the representations and warranties he required to progress asset life…”
“Q. Just to unpack that, what has happened here is that Mr Kavanagh has sought specific assurances and warranties, hasn’t he, in relation to the lifetime of the equipment of your previous employer? A. Yes. Q. And they have refused to give those, haven’t they? A. Yes. Q. It is right, isn’t it, if those issues were to be part of an asset life agreement, you would expect them to be negotiated specifically, wouldn’t you? A. As my role as seller, yes, in that transaction, yes. Q. And, in fact, if they had been demanded it would have been reasonable to refuse. That’s what you did, isn’t it? A. Yes.”
“Further to the below, I can confirm that the lease references included in the options are all to ensure that the yielding up obligations in the various principal leases are suspended, in the event that the options are exercised and new leases granted. The attached table confirms the details of the specific clauses in respect of each lease. These same yielding up provisions do of course apply to the new leases to be granted should the options be exercised.”
“Thank you for the below and the table which were very helpful. I have no comments on the forms of Option Agreement. Please send the consent letters and I shall arrange signature.”
“The “Initial Rent" as set out in paragraph 1 of Schedule 3 shall be the Increased Rent as applicable and determined in accordance with the provisions of Schedule 3 of the Principal Lease for the last Review Period of the Term of the Principal Lease (or which would then be applicable but for any abatement or suspension of the Rent under the Principal Lease or restriction on the right to collect it) reviewed in accordance with the Schedule 3 as if the date of commencement of the Lease were a Review Date under the Lease and the rent for the remainder of the Term of the Lease shall be determined in accordance with Schedule 3 of the Lease and for the avoidance of doubt the RP1 value for "the Base Figure" in Schedule 3 of the Lease shall be the RP1 figure for July 2015.”
“2.4 The "Initial Rent" as set out in paragraph 1 of Schedule 3 of the Lease shall be the Increased Rent as applicable and determined in accordance with the provisions of Schedule 3 of the Principal Lease for the last Review Period of the Term of the Principal Lease (or which would then be applicable but for any abatement or suspension of the Rent under the Principal Lease or restriction on the right to collect it) reviewed in accordance with Schedule 3 of the Principal Lease as if the date of commencement of the Lease were a Review Date under the Principal Lease and for the avoidance of doubt the RPI value for "the Base Figure" for the purposes of this clause 2.4 shall be the RPI figure for July 2015. 2.5 The rent for the remainder of the Term of the Lease shall be determined in accordance with Schedule 3 of the Lease.”
“52. I have reviewed the disclosure provided and can see that this was indeed a problem on Upper Wick and Widehurst. Tom Barnacle represented the landowners for Upper Wick and Widehurst and was attempting to introduce wording which related to compounded inflation. I have seen Eleanor Docherty at CMS wrote to Tom Barnacle and stated: "Otherwise any reviews which have already been carried out and included in the Base Rent will be subject to review again and result in a compounded rent figure" "To resolve this in your signed engrossments I propose you deleting the wording in clause 2.4 from "and for the avoidance of doubt" until the end of the clause in manuscript" 53 The result of this was CMS had (after business hours on21 December 2017 ) inserted on Upper Wick and Widehurst clauses after BLB's consent and without informing RFE and our solicitors Eversheds at all. This changed the content of proposed lease option regarding clause 2.4 and introduced clause 2.5 which did not exist at all prior to this point. Both changes relate to cumulative inflation and I am sure CMS knew the SPV would not sign which is likely why CMS had informed BLB: " we have terminated negotiations with the landlords for Upper Wick and Widehurst and we could not agree forms of option acceptable to the companies " 54 This is precisely the lack of transparency which concerned me. None of this was reported in the updates from Wirsol.”
“Leases: a lease of the Premises for the Lease Term and otherwise in the form attached, being in the same form and on the same terms as the Principal Leases, save for the term which in each case will expire on27 February 2052 .”
“As our solicitors offices are currently closed, we are writing to you to confirm that our solicitors are holding a signed option agreement duly executed by us in respect of the Property. Our solicitors are instructed to complete this option agreement as soon as the Company is also in a position to do so. The option agreement grants the Company the right to new leases of the Property. The new leases to be granted pursuant to the option agreement are to be on the same terms as the Principal Leases save that the lease terms shall commence on the expiry of the Principal Leases and end on27 February 2052 . We note that the signed option agreement incorrectly refers to an end date for the leases of 2017, which is clearly an error. When our solicitors' offices reopen, we will instruct them to amend this error. Otherwise the signed option agreement accords with the heads of terms dated11 December 2017 . We trust this letter is of assistance in evidencing our readiness to complete”
“Further to your email of this morning I have received a 'phone call from John McBurney's office to advise that the Option is approved and signed by the Lewis brothers, but that it will not be released unless you personally provide a written assurance that all of the previous agreements discussed between you and the Lewis brothers will be fulfilled.”
“… To enable the Option Agreement to be released by your client our client has confirmed the following:- 1. It will not enter into any easement agreement with NIE without your client's consent. 2. It will undertake a tree management programme with the trees running parallel with Ballinderry Road. This has been agreed and a purchase order is attached herewith for your information. All costs in relation to this will be borne by Wirsol for the works to take place at the first available opportunity. 3. Your client will be able to continue to graze subject to the signing of a grazing licence. 4. Wirsol will monitor and maintain the drainage measures that have been implemented on site. We trust that this is sufficient for your client to release the Option Agreement.”
“Further to our telephone conversation earlier, our clients have instructed that in addition to the matters you have covered they wish to have a term incorporated confirming that your client (Wirsol) will monitor and maintain the drainage measures that have been implemented on site and any additional remedial measures occurring at any stage and produce (at Wirsol expense) written verification by an independent expert to our clients as and when requested from time to time. To proceed further in relation to the April 2017 document mentioned our clients instruct that they require payment of an amount of$218,500.00 .”
“I refer to your email of 20 December. I understand that there have been discussions between Simon McCarthy, my client, and your clients and that various matters have been agreed between them which hopefully can alleviate the release of the executed Option Agreement. My client has given me to understand that it believes that this particular Agreement can be dealt with via exchange of correspondence. I set out the terms below instructed to me: 1. Wirsol will not enter into any easement agreement with NIE without your client's consent; 2. Wirsol will undertake a tree management programme of the trees running parallel with Ballinderry Road. This has been agreed and a purchase order has already been produced for your information. All costs in relation to this will be borne by Wirsol and the works are to take place at the first available opportunity; 3. Your client will be able to graze subject to the signed grazing licence; 4. During Wirsol's Operation and Maintenance (O&M) contract it agrees to monitor and maintain all drainage measures it implements. It also agrees to repair any damage caused to existing drainage during the park's construction and pay 50% of the fees of any agreed drainage expert in the event of any dispute; 5. With regard to a verbal agreement between Simon McCarthy, Wirsol and James Lewis on21 December 2017 , Wirsol will pay£12,000 upon receipt of an invoice for: full and final settlement for any outstanding works to the compound area, outside of the Solar Park leased by WEL Solar Park 15 on14 November 2016 . I should be grateful if you could confirm your client's agreement to these terms and confirm that the exchange of correspondence suffices for this particular purpose.”
“I now return a revised version of my earlier email. You will see that we have amended your suggested wording at item 4 as there has to be some limit on our client's liability to whatever it is indeed liable for. I trust this can be agreed and look forward to hearing from you. Quite separately, I understand that your client has confirmed to my client that the Option Agreement which has been executed can be released and I should be grateful if you could arrange to let me have same.”
“1. Wirsol will not enter into any easement agreement with NIE without your client's consent; 2. Wirsol will undertake a tree management programme of the trees running parallel with Ballinderry Road. This has been agreed and a purchase order has already been produced for your information. All costs in relation to this will be borne by Wirsol and the works are to take place at the first available opportunity; 3. Your client will be able to graze subject to the signed grazing licence; 4. Wirsol will be liable for all remedial works in relation to drainage at the solar farms caused by the construction and operation of the Solar Park. 5. With regard to a verbal agreement between Simon McCarthy, Wirsol and James Lewis on21 December 2017 , Wirsol will pay£12,000 upon receipt of an invoice for: full and final settlement for any outstanding works to the compound area, outside of the Solar Park leased by WEL Solar Park 15 on14 November 2016 .”
“On looking at this matter further, I had discovered a number of errors in the Option Agreement. At clause option point 1 the definition of Lease Term and should read "and ending on27 February 2047 ", not 2017. In clause 1.2 the definition of Leases refers to Lease in the singular, whereas that should be plural. Further in recital 3 on page 2, this should refer to "take leases over the option property". I have been asked to seek your confirmation to these amendments being agreed prior to 31 December, and perhaps you could make the amendments in manuscript to the signed Option being held by you. I look forward to hearing from you further.”
“Further to our 'phone call this afternoon please see below a copy of our email to you of 22 December at 13:54 which does not seem to have reached you, and which hopefully resolves matters. I look forward to hearing from you further as soon as possible”
“I have been speaking with Laura at John McBurney's office several times over the past couple of days. She has come back to me this afternoon to say that in relation to point 3 of the assurances set out below, her client would like to add the wording "as well as sub-letting the land for such grazing purposes" — is this acceptable? In relation to point 5 below the Lewis brothers apparently raised an invoice before Christmas, and are checking if payment has been received”
“Further to our “phone call on 4 January my client is agreeable to the wording of point 3 of the assurances to be amended by the addition of the words “as well as sub-letting the lands for such grazing purposes”
“We refer to previous correspondence, discussions and exchanges herein and enclose herewith 3 invoices previously mentioned and with VAT elements included. Strictly on the basis that these are agreed and now being paid forthwith we enclose Option Agreement, in duplicate, duly signed by our clients for execution by your client and on your undertaking to let us have fully completed counterpart in due course.”
“I have been instructed by Mr Lewis that the following arrangements, agreements and assurances are essential components of any Agreement going forward:- 1. Not to enter into any easement agreement with ME without our clients consent; 2. Undertake a tree management programme with the trees running parallel with Ballinderry Road; 3. Allow my clients to continue to graze livestock on the land (subject to signing of a grazing licence) and with the right to sub-let the lands for such purpose; 4. To monitor and maintain the drainage measures which have been implemented on site and any additional remedial measures occurring at any stage and produce (at your expense) written verification by an independent expert to my clients when requested from time to time. As previously mentioned, there is also the substantial uplift of the Option Fee yet to be determined.”
“Further to your conversation with Eleanor, please find attached the amended option agreements for Upper Wick and Widehurst and redlines of the same. As discussed, we have split the clause in two so that there is one clause dealing with the initial rent review and another dealing with rent for the remainder of the lease. We have then included your "for the avoidance of doubt" provision in the clause for the initial rent review. I can confirm that the company has agreed to the further£1,000 in respect of the landlord's costs for putting in place the agreement between Colin Rea and Louise Rea and Thomas Rea and Katie Rea. For our records, please can you confirm on Upper Wick that you will make the latest amends in manuscript, and that the documents for this property are now agreed. …”
“Just to update you on the above, last Thursday your clients signed the original engrossment you sent to them and my client picked it up. My client's office has today arranged for this to be sent to you via Royal Mail's guaranteed next day delivery service. It should therefore arrive at your offices before 1pm on Thursday 28.12.17, The Royal Mail tracking number for it is: BH830321249GB. I am now waiting for my client's instructions on completion and will be in touch as soon as I have a further update.”
“Q. … Are you saying that you appreciated this in December 2017 or is this a matter that you realised when you reviewed the documents for this trial? A. Sorry. Did I know about this problem in -- Q. Yes. To summarise, you discussed this point here, but I was unclear whether you were saying "We thought this at the time in December 2017 when we received the planning permission document", or whether this is a point you picked up later once these proceedings began? A. No. When I instructed Mr Croucher to do this work (inaudible). Q. You were aware of this in December 2017? A. From this -- from the tracker, yes. Q. If you were aware there was a problem on this, why did you not raise that with Wirsol? A. I assumed Mr Croucher had raised it with Wirsol. That was their job. Q. So you appreciated that if you had spotted an error, it should be raised with Wirsol? A. I would have thought so, yes.”
“(2) Dealing with a case justly and at proportionate cost includes, so far as is practicable— (a) ensuring that the parties are on an equal footing; (b) saving expense; (c) dealing with the case in ways which are proportionate— (i) to the amount of money involved; (ii) to the importance of the case; (iii) to the complexity of the issues; and (iv) to the financial position of each party; (d) ensuring that it is dealt with expeditiously and fairly; (e) allotting to it an appropriate share of the court’s resources, while taking into account the need to allot resources to other cases; and (f) enforcing compliance with rules, practice directions and orders.”
“25. Now let us assume that I am wrong on both points above, so that the issue of law is at least arguable as a matter of contributory negligence. Even if that were the case, I would still refuse to allow the amendments to Response 14. There are two reasons for that. 26. The first is because the amendments were made late, only a few weeks before trial (and with a holiday period intervening). The lateness is neither explained nor the subject of any explanation. 27. The second is because of all the uncertainties that the amendments introduce, and the inevitable adjournment of the trial if they were allowed. On the basis of the case as it presently exists, the claimant has devoted little time, and little of its expert's report, to a consideration of the allegations of contributory negligence arising out of the underpinning works. That is because the claim has hitherto been put on the narrow basis indicated in D&F Estates (i.e. actual knowledge and condoning of the wrong) and the claimant has decided - whether rightly or wrongly - that it has a good case in defence of that very specific allegation. 28. I accept Mr Sullivan's proposition that, if these amendments were allowed, they would require the claimant to reconsider this whole aspect of the case and, more than likely, to focus upon matters which it had previously thought were unnecessary. It would give the case on workmanship and inspection a completely different emphasis. Out of caution, the claimant would have to put itself into the shoes of Toureen and look at all the factual and expert issues (not just the narrow D&F Estates point), to gather evidence in response and weigh its potential liability for contributory negligence on this new basis. 29. It would not stop there. No matter what my views are as to the inherent dangerousness exception as a matter of law, and the difficulty of arguing the point in this case (paragraph 14 above), the claimant would need carefully to consider that aspect of the amendments, for the first time, and in very short order. It may be a matter on which expert, as well as factual, evidence is thought to be required. I acknowledge at once that Ms McCafferty properly indicated that this would not be how the case would be presented at trial, but the discussion of the law set out above demonstrates that considerations of inherent danger may easily become part of the defendant's case, even by default. 30. Thus, if I allowed these amendments, they would not only comprise an unwelcome and unnecessary distraction to the claimant as it prepares for a trial that is a month away, but it would probably also give rise to the need for further evidence, perhaps including expert evidence. That would fatally jeopardise the trial date. On an application of the relevant principles summarised by Carr J in Su-Ling , I am bound to conclude that it would not be appropriate to allow the amendments in those circumstances.”
“In deciding whether to give permission for an admission to be withdrawn, the court will have regard to all the circumstances of the case, including – a) the grounds upon which the applicant seeks to withdraw the admission including whether or not new evidence has come to light which was not available at the time the admission was made; b) the conduct of the parties, including any conduct which led the party making the admission to do so; c) the prejudice caused to any person if the admission is withdrawn; d) the prejudice that may be caused to any person if the application is refused; e) the stage in the proceedings at which the application to withdraw is made, in particular in relation to the date or period fixed for trial; f) the prospects of success (if the admission is withdrawn) of the claim or part of the claim in relation to which the admission was made; and g) the interests of the administration of justice.”
“… we note that Mr Ryder has sought to expand the Claimants’ case in his expert report by relying upon the state of the paint applied to the transformers in support of the alleged failure to design solar parks with an operating life of 25 years… This is not a pleaded allegation, nor has disclosure or witness evidence been provided. As such, it is not a matter before the court…”
“… this issue is referred to in the defects’ experts joint memorandum… and it is addressed (in part) by Dr Lockwood in his report… it is an expert-led point which has long been on the defects experts’ agenda and, as such, it is hard to see what witness evidence or disclosure would be necessary.”
“The maximum currents set out in the Amended Scott Schedule are accurately stated in the second sentence of item 1. However, the relevant current for the purposes of assessing “the rated output for the maximum load curve” is the rated current from the connected inverters set in accordance with the manufacturer’s specification.”
“16. If [transformer overload capacity] were now part of the Defendants’ Defence, to provide a full and complete opinion on this topic I would need to undertake the following additional work: a. Study the various transformer manuals and other transformer documentation in more detail to see what they say about whether the dry-type transformers can be overloaded as part of normal operation. As a minimum I would wish to consider an example from each manufacturer. I note (as above) that it has been difficult to obtain information and documentation from some of the manufacturers and, therefore, time-consuming. b. Compare the requirements of IEC standard 60076-7 for oil-immersed transformers with those of IEC standard 60076-12 for dry-type transformers. c. I would need to consider operational data about the thermal performance of the transformers in service, both from Wirsol (as the prior owners) and Toucan. I would need to consider what monitoring data is available, for what periods, and assess the records of what operational constraints (such as inverter “clipping”) have been applied over those periods. This would be a lot of data from the different monitoring systems and careful consideration would be required” “18. If [busbar capacity] were now a key argument in the Defence to address the matter properly, I would need to undertake the following additional work: … d. Seek from Toucan (and Wirsol) more operational data about the performance of the 3200A busbars in service. There is a real risk their performance in service might be different from their performance on test. In particular, I have heard reports that the busbars are overheating in service, and I am concerned that their capacity may have been overstated. I had understood that the busbar ratings had previously been agreed by all parties and had carried out my previous work and analysis on that agreed basis. Whilst this would be of tangential relevance to the Defence as currently advanced, I believe the actual rating of the busbar and its response to overloading would be significant were the Defendants now to be advancing a case that the busbars can be overloaded by 50%. That said it is a bit unclear to me from the amendments whether the Defendants are arguing that the busbars have an overload capacity of 50% or only that busbars have an overload rating that can be used in normal operation (paragraph 17 g). e. I would therefore propose to monitor/assess the thermal performance of the busbars currently in service. The complexity of this exercise depends on whether the instrumentation is in place to measure the thermal performance. If the instrumentation is already there, the task would involve collecting the data and then interpreting it for a number of sites. Following making arrangements, that would take up to 2 days depending on the number of sites surveyed. However, if the instrumentation is not already in place, then this is much more difficult. It would involve the time and cost of fitting the necessary instrumentation and connecting it to the remote monitoring system. It would then be necessary to wait for a period of hot, sunny days in order to test. Given the current time of year and weather, that is likely to involve waiting until Spring for results.”
“3. I accept that [the two points comprising amendment (ii)] were raised in Dr Lockwood’s first report, however they did not form any part of the Defendants’ pleaded case that I had been asked to address in my reports and I did not understand that these arguments were the points in issue between the parties. I do not agree with them, however, I did not address them in the level of detail I would have had they been relied on by the Defendants as their main defence. … 5. The first of the two new pleaded arguments advanced is to increase the overcurrent setting so it is effectively only used to protect against fault currents and to implement the thermal replica function to provide protection against overloads. These points were raised briefly in Dr Lockwood’s first report at paragraphs 266 and 275 along with a number of other new points such as that the LV busbars were rated at 3250A (paragraph 264). In the time available between the first and second reports I responded briefly in paragraphs 4.2.2.3 to 4.2.2.6 of my supplemental report. 6. In summary, I disagree that this alleged “workaround” is a proper or verified use of the equipment. The 3900A is based on 120% of a busbar rating of 3250A, not the 3200A stated by Burnell and does not take any cognisance of the transformer rating. In my view, the ratings of both cannot be considered in isolation of each other. My view is that the manufacturer’s approved overcurrent setting should be used as the primary protection as it is based on an actual measured value, this is industry practice, and not a theoretical calculated value (as may arise with the use of thermal replica). … 9.If these arguments are now advanced as a central part of the Defendants’ case, I would need to undertake the following further work: a. I would wish to conduct a thorough review of the manuals, Distribution and Network Operator (DNO) and vendor information, which may involve sourcing documents and information not already available. b. The manuals and vendor information would be used to determine the electrical protection requirements to ensure no damage to the transformers and/ or busbars occurred for electrical overloads or electrical faults. This would require to be compiled for each type/ manufacturer of transformer and busbar. c. Once the electrical protection requirements have been determined this would require a detailed protection study to be carried out for each site to determine the electrical protection settings for each site. These would require to be agreed with the transformer and busbar manufacturer. d. I would anticipate a full protection survey in relation to protection settings and thermal replica function to take time to set up. There would then be time for the survey to be carried out, to carry out any evaluative work and to provide a report to the Court. I cannot see that this is possible to be concluded in the next few weeks”
“7. As to the third argument concerning the LV and HV Circuit Breakers defects, the new argument advanced is that the HV Circuit Breaker at Substation 1 could be used to clear an LV fault at Substation 2. It is suggested that once Substation 2 had been isolated there would be some form of automatic system to restore power to substation 1 thus ensuring minimal loss of production. I addressed this briefly at 7.4.1.2 in my first report and 6.2.3.4 in my supplementary report. 8. In my view, this is a wholesale change in operational philosophy and procedures which, on the face of it is completely unsatisfactory, but would require to be reviewed on the basis of any proposed control changes. 9. If [this argument is] now advanced as a central part of the Defendants’ case, I would need to undertake the following further work: … e. As to the circuit breakers, to investigate the feasibility of implementing this type of system detailed schematic drawings would be required for all switchgear at all sites. The schematic drawings would require to be checked to confirm if the switchgear had the required functionality and facilities installed to allow the required control to be implemented. To date I have not seen any relevant detailed schematic drawings for any of the installed switchgear. f. I would anticipate this will require discussions with the manufacturer on switchgear clarifications and/or modifications. g. Detailed control cabling block diagrams, schedules and termination details would be required to determine what existing cabling is in place and what additional cabling would be required for such a scheme. h. Once the schematic diagrams, cabling details had been reviewed a detailed site survey at each site would be required to confirm the site installation is as per the switchgear and cable details provided. This would determine if the proposal was a practical solution. This would be a minimum of one day per site following the above and set-up. Based on the survey notes the feasibility of the proposal would then be assessed and written up. If this was to be implemented this would require a detailed design for each site to be carried out and an installation and commissioning plan to be prepared.”