“(4) Proceedings under this regulation may not be brought unless – (a) The services provider bringing the proceedings has informed the contracting authority of the breach or apprehended breach of the duty owed to him pursuant to paragraph (1)…by the contracting authority and of his intention to bring proceedings under this regulation in respect of it; and (b) they are brought promptly and in any event within 3 months from the date when grounds for the bringing of the proceedings first arose unless the Court considers that there is good reason for extending the period within which proceedings may be brought.” (a) The services provider bringing the proceedings has informed the contracting authority of the breach or apprehended breach of the duty owed to him pursuant to paragraph (1)…by the contracting authority and of his intention to bring proceedings under this regulation in respect of it; and (b) they are brought promptly and in any event within 3 months from the date when grounds for the bringing of the proceedings first arose unless the Court considers that there is good reason for extending the period within which proceedings may be brought.”
“The answer to the first question accordingly is that Article 1(1) of Directive 89/665 requires that the period for bringing proceedings seeking to have an infringement of the public procurement rules established or to obtain damages for the infringement of those rules should start to run from the date on which the claimant knew, or ought to have known, of that infringement.”
“If the national provisions at issue do not lend themselves to such an interpretation, that court is bound, in exercise of the discretion conferred on it, to extend the period for bringing proceedings in such a manner as to ensure that the claimant has a period equivalent to that which it would have had if the period provided for by the applicable national legislation had run from the date on which the claimant knew, or ought to have known, of the infringement of the public procurement rules.”
“….Directive 89/665 requires the national court, by virtue of the discretion conferred on it, to extend the limitation period in such a manner as to ensure that the claimant has a period equivalent to that which it would have had if the period provided for by the applicable national legislation had run from the date on which the claimant knew, or ought to have known, of the infringement of the public procurement rules. If the national provisions do not lend themselves to an interpretation which accords with Directive 89/665, the national court must refrain from applying them, in order to apply EU law fully and to protect the rights conferred thereby on individuals.”
“30 However, the fact that a candidate or tenderer learns that its application or tender has been rejected does not place it in a position effectively to bring proceedings. Such information is insufficient to enable the candidate or tenderer to establish whether there has been any illegality which might form the subject-matter of proceedings. 31 It is only once a concerned candidate or tenderer has been informed of the reasons for its elimination from the public procurement procedure that it may come to an informed view as to whether there has been an infringement of the applicable provisions and as to the appropriateness of bringing proceedings.”
“the standard ought to be a knowledge of the facts which apparently clearly indicate, though they need not absolutely prove, an infringement.”
“A contract notice lacking any information as to the estimated value of the contract, followed by evasive conduct by the contracting authority in response to the questions of a potential tenderer such as that at issue in the main proceedings, must be considered, in view of the existence of a limitation period, as rendering excessively difficult the exercise by the tenderer concerned of the rights conferred on him by Community law…”
“… a claim should not be struck out unless it can be demonstrated sufficiently clearly that it was bound to fail as a matter of law and/or fact, and that I should not determine the serious live issue of fact which requires oral evidence, or which requires a full scrutiny that a trial will bring to bear”
“The real question for me is whether it is clear enough, at this stage, that the claim is bound to fail on limitation grounds, and that a trial (or a fuller hearing of a preliminary issue) would not change that situation. Any doubt about it would have to be resolved in favour of the claimant. When I make any determination in this matter whether of fact law or discretion, I should be taken to be doing so on the footing that the point has been clearly established, and that the same result would clearly be reached at trial.”
“Both Viridor Laing (Greater Manchester) Limited and the Sita Consortium submitted in their BaFOs alternative facilities as back-up for the EfW element of the project. Viridor Laing offered a Combined Heat and Power facility located at the Ineos Chlor Site at Runcorn. At the request of the Authority, Viridor Laing were invited to develop this solution further in the course of the negotiations following their appointment as Preferred Bidder. To satisfy itself that Viridor Laing should remain the Preferred Bidder based upon the Runcorn Facility being the EfW facility for the project, the Authority re-evaluated the Viridor Laing bid once the solution had been developed. The same Evaluation Criteria, weightings and methodology were applied as had been applied at ITT and BaFO. On the basis of this the Preferred Bidder decision was not undermined on the basis of this, the Authority resolved at its meeting on29th June 2007 to proceed with the Runcorn facility as its EfW facility.”
“In the circumstances, if GMWDA continues to refuse further information, Sita will have no choice but to bring proceedings on the basis of the information so far available; to seek from the court an order that further information be supplied, to apply for an order that the contract be set aside, alternatively that no further steps be taken to implement the contract, pending further resolution of the matters.”
“The thrust [of the letter] is an assertion of breach by a party who has a keen understanding of the position and who is offering the other side the chance to head off proceedings which would otherwise ensue.”
‘… come to an informed view as to whether there has been an infringement of the applicable provisions and as to the appropriateness of bringing proceedings.’
“30 However, the fact that a candidate or tenderer learns that its application or tender has been rejected does not place it in a position effectively to bring proceedings. Such information is insufficient to enable the candidate or tenderer to establish whether there has been any illegality which might form the subject-matter of proceedings. 31. It is only once a concerned candidate or tenderer has been informed of the reasons for its elimination from the public procurement procedure that it may come to an informed view as to whether there has been an infringement of the applicable provisions and as to the appropriateness of bringing proceedings. ”