“Can the contractor terminate its employment under clause 8.9.4 of the JCT 2016 Design and Build Form, in a case where a right to give the further notice referred to in clause 8.9.3 has never previously accrued?”
“Termination by Contractor Default by Employer 8.9 .1 If the Employer: .1 does not pay by the final date for payment the amount due to the Contractor in accordance with clause 4.9 and/or any VAT properly chargeable on that amount; or .2 fails to comply with clause 7.1 [number not used]; or .3 fails to comply with clause 3.16, the Contractor may give to the Employer a notice specifying the default or defaults (a ‘specified’ default or defaults). .2 If after the Date of Possession (or after any deferred Date of Possession pursuant to clause 2.4) but before practical completion of the Works the carrying out of the whole or substantially the whole of the uncompleted Works is suspended for a continuous period of the length stated in the Contract Particulars [2 months] by reason of any impediment, prevention or default, whether by act or omission, by the Employer or any Employer’s Person, then, unless it is caused by the negligence or default of the Contractor or any Contractor’s Person, the Contractor may give to the Employer a notice specifying the event or events (a ‘specified’ suspension event or events). .3 If a specified default or a specified suspension event continues for 14 days [28 days] from the receipt of notice under clause 8.9.1 or 8.9.2, the Contractor may on, or within 21 days from, the expiry of that 14 day [28 day] period by a further notice to the Employer terminate the Contractor’s employment under this Contract. .4 If the Contractor for any reason does not give the further notice referred to in clause 8.9.3, but (whether previously repeated or not): .1 the Employer repeats a specified default; or .2 a specified suspension event is repeated for any period, such that the regular progress of the Works is or is likely to be materially affected thereby, then, upon or within a reasonable time [28 days] after such repetition, the Contractor may by notice to the Employer terminate the Contractor’s employment under this Contract.”
“Termination by Employer Default by Contractor 8.4 .1 If, before practical completion of the Works, the Contractor: .1 without reasonable cause wholly or substantially suspends the carrying out of the Works; [or any material part thereof pursuant to clause 4.11;] or .2 fails to proceed regularly and diligently with the performance of his obligations under this Contract; or .3 refuses or neglects to comply with a notice or instruction from the Employer requiring him to remove [or rectify] any work, materials or goods not in accordance with this Contract and by such refusal or neglect the Works are materially affected; or .4 fails to comply with clause 3.3 or 7.1; or .5 fails to comply with clause 3.16, the Employer may give to the Contractor a notice specifying the default or defaults (a ‘specified’ default or defaults). .2 If the Contractor continues a specified default for 14 days from receipt of the notice under clause 8.4.1, the Employer may on, or within 21 days from, the expiry of that 14 day period by a further notice to the Contractor terminate the Contractor’s employment under this Contract. .3 If the Employer does not give the further notice referred to in clause 8.4.2 (whether as a result of the ending of any specified default or otherwise) but the Contractor repeats a specified default (whether previously repeated or not), then, upon or within a reasonable time after such repetition, the Employer may by notice to the Contractor terminate that employment.”
“You have not paid us the amount due to us under Payment Notice No. 27, i.e.£264,242.55 , by the final date for its payment, i.e.15 December 2022 . We therefore give you this Notice of Specified Default under clause 8.9.1 of the Contract.”
“As a preliminary point, it is common ground that what constitutes the ‘specified default’ in question is the failure to pay by the final date for payment the amount due to the Contractor in accordance with Clause 4.9. The fact that it occurred in the context of Payment 27 is not a constituent element of the specified default: if it were otherwise, it would not be possible for the Employer to repeat the specified default on a later occasion in the context of a different payment.”
“The standard clauses in these contracts have been settled over the years by negotiation by representatives of the commercial interests involved and have been widely adopted because experience has shown that they facilitate the conduct of trade. … [T]hey are widely used by parties whose bargaining power is fairly matched…”
“It is also important to have regard to the course of earlier judicial authority and practice on the construction of similar contracts. The evolution of standard forms is often the result of interaction between the draftsmen and the courts and the efforts of the draftsman cannot be properly understood without reference to the meaning which the judges have given to the language used by his predecessors.”
“The parties and the judge were content to treat the history and development of the [standard] form as part of the commercial background to the contract. In cases where it is possible to identify with a degree of confidence the reason for a particular amendment to a standard form, for example, where a change has been made to respond to the effect of a particular decision of the courts, a change in legislation or a widely publicised event, that may be appropriate. Such cases are usually well-known within the industry and are often documented in the trade press. Both parties are therefore likely to be aware of them. I am doubtful, however, whether it is legitimate simply to compare the earlier and later versions of the contract form on the assumption that the parties consciously intended to achieve a particular result by adopting the later version. Such an exercise is not wholly removed from that of referring to drafts produced during the course of negotiations, which are not a proper aid to construction. The earlier version does, of course, serve as an example of how the contract could have been worded differently, but in that respect it has no greater persuasive force than a text created for the purposes of the trial. The fact is that in the present case we have no evidence of why specific changes were made, nor any evidence that the parties turned their minds to the differences between the two forms and there must be a real likelihood that they simply reached for the current form without any consideration of the earlier version. In any event, times have moved on and one cannot assume that the commercial background has not moved with them. In my view the right course when seeking to ascertain the intention of the parties is to consider this contract on its own terms against the commercial background as it existed at the time it was made.”
“In the case of a contract which is intended for standard use throughout a particular industry or market, the court is more likely to focus its attention on the background generally known to participants in the industry or the market and not on the background known to, or the understandings of, the individual parties to the particular transaction.”