“You have not paid us the amount due to us under Payment Notice No. 27, i.e.£264,242.55 , by the final date for its payment, i.e.15 December 2022 . We therefore give you this Notice of Specified Default under clause 8.9.1 of the Contract.”
“envisages an active step being taken by the Contractor, or not. If the Contractor takes that active step under clause 8.9.3 then termination ensues. If he does not, then, if there is a repeated default, the Contractor may serve Notice of Termination under clause 8.9.4.”
“18. … All these words entail is that the Contractor may have decided not to give the clause 8.9.3 notice “for any reason.”. 19. Neither those words, nor clauses 8.9.3 and 8.9.4 as a whole, envisage in my view that a Contractor can give a valid clause 8.9.4 notice in circumstances where the right to give a clause 8.9.3 notice has never arisen. That is where the specified default has been cured within the 28-day period. In my view, clause 8.9.4 requires that a clause 8.9.3 notice could have been given but the Contractor has decided not to do so for whatever reason.”
“In cases where it is possible to identify with a degree of confidence the reason for a particular amendment to a standard form, for example, where a change has been made to respond to the effect of a particular decision of the courts, a change in legislation or a widely publicised event, that may be appropriate. Such cases are usually well known within the industry and are often documented in the trade press. Both parties are therefore likely to be aware of them. I am doubtful, however, whether it is legitimate simply to compare the earlier and later versions of the contract form on the assumption that the parties consciously intended to achieve a particular result by adopting the later version.”
“Whilst there may be occasions when this has to be done in order to assist in solving a problem of an ambiguous wording, I would generally discourage such exercises in “the archaeology of the forms”
“If the Contractor … does not give the further notice referred to in Clause 8.9.3” are broad enough to cover any state of affairs other than one where the Contractor does give notice. Put another way, unless the Contractor gives the further notice referred to in clause 8.9.3, the condition is satisfied. Viewed in isolation there is no basis for a submission that the conditional words imply anything about whether the Contractor could or could not have given the notice. That natural meaning is reinforced by the words “for any reason”, which (at risk of paraphrasing) mean that there is to be no exception based upon the reason why the Contractor does not give the notice. Even assuming that the reason why the Contractor does not give the further notice is that the right to do so has not accrued under Clause 8.9.3, that remains within the meaning of the phrase “for any reason”
“34. Clause 28.2.4 is in my judgment clear and unambiguous and it provides that a notice of determination may be given as soon as the specified default has been repeated. There is nothing unreasonable in that, since the employer has already received a warning in respect of the previous default and must be taken to know that if he repeats the default he runs the risk that the contract may be determined either forthwith or within a reasonable time after the repetition of the specified default. … “In giving a notice of determination under clause 28.2.4, the contractor in my judgment is entitled to have regard to his own commercial interests. It should be remembered that under clause 28.2.4 a notice of determination may only be served if the employer has … repeated a breach of contract about which he previously received a warning under clause 28.2.1 … . It is clear from clause 28.2.1 that a failure on the part of an employer promptly to pay the amount properly due under a certificate … is regarded under the contract as a serious breach on the part of the employer and that the contractor may determine the contract if that breach is repeated provided only that the contractor is not acting vexatiously or unreasonably. The contractor is entitled to be paid by the due date and he is not, for example, bound to incur the expense of pursuing other remedies such as adjudication or arbitration in order to obtain payment but may determine the contract.”
“88. … I note in relation to [Reinwood] that the specialist editors of the Building Law Reports … says that an employer who has defaulted once on his payment obligations is skating on thin ice. 89. The scheme of the contract is that in the event of a default in stage payments, the contractor is entitled to give formal notice. If the default is not rectified or there is a further similar default, the contractor is entitled to give notice of termination. The purpose of the provision is to ensure that the contractor is paid in accordance with the payment provisions. The provisions give the contractor the power to terminate if the payment terms are not complied with … .”