“We refer to the Civils, Structural and Architectural Subcontract between you and us dated20th November 2015 and your application for payment dated4th February 2019 for the sum of£3,353,219.22 excluding VAT. We hereby give you notice of the sum that we consider to be, or to have been due at the payment due date in respect of the above application being a Certificate that the Subcontractor owes the Contract£6,818,521.70 excluding VAT. [T]he basis on which that sum is calculated, is set out in the attached spreadsheet [CSL Application 32 M+W Assessment 35xlsx].”
“The Subcontract constitutes the entire agreement between the Contractor and the Subcontractor with respect to the performance of the Subcontract Works and supersedes any prior negotiation, representation or agreement relating thereto, whether written or oral, except to the extent that they are expressly incorporated in the Subcontract. No change, alteration or modification to the Subcontract shall be effective unless the same shall be in writing and signed by both parties. The Contractor and the Subcontractor agree that they shall not be entitled to enforce or otherwise rely on any term or condition (including but not limited to any term or condition, standard or otherwise, contained in a Quotation, acceptance of Quotation, Purchase order or any Standard Terms and Conditions of either party) which is not contained or incorporated expressly in the Subcontract.”
“ … either party shall have the right to refer any dispute or difference (including any matter not referred to the Contract Manager in accordance with Sub-clause 43.3) as to a matter under or in connection with the Subcontract to adjudication and either party may, at any time, issue a Notice (a ‘Notice of Adjudication’) to the other stating his intention to do so…”
“This clause 44 applies only to the extent (if any) required by [the Act].”
“(1) In this Part “construction operations” means, subject as follows, operations of any of the following descriptions … (2) The following operations are not construction operations within the meaning of this Part … (c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is – (i) … power generation …” (c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is – (i) … power generation …”
“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.” (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.”
“(1) Every construction contract shall – (a) provide an adequate mechanism for determining what payments become due under the contract, and when, and (b) provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. (a) provide an adequate mechanism for determining what payments become due under the contract, and when, and (b) provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. (3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.”
“(1) This section applies in a case where, in relation to any payment provided for by a construction contract – (a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but (b) notice is not given as so required. (2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given. (3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given. (4) If – (a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of – (i) the sum that the payee considers will become due on the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated, and (b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).” (a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but (b) notice is not given as so required. (a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of – (i) the sum that the payee considers will become due on the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated, and (b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).”
“Where any provisions of the Scheme for Construction Contracts apply by virtue of this Part in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned.”
“[63] It follows that the statute contemplated a position where one agreement related to both construction operations under section 105(1) and operations which were excluded by section 105(2). [64] It also follows that the right to refer disputes to adjudication under section 108, the entitlement to stage payments under section 109, the provisions as to dates of payment under section 49. under section 111, the right to suspend performance for nonpayment under section 112 and the prohibition of conditional payment provisions under section 113 will only apply to the subcontract in this case, insofar as the subcontract relates to construction operations… 50. [91] It is clear that the legislation could have dealt with agreements which related both to construction operations and to "other matters" being operations which were not construction operations, in a number of ways. It would have been possible to treat them either as being agreements for construction operations or as not being agreements for construction operations. It would also have been possible for that question to depend on the relative values of the construction operations and of the "other matters". It is clear that Parliament decided that, just because an agreement related, in part, to operations which were not construction operations, this did not prevent the implied terms under section 114(4) of the Act from applying to the construction operations. It follows that a party can refer a dispute arising under the agreement, insofar as it relates to construction operations, to adjudication under a procedure complying with section 108 of the Act. In this case the contract contained no provision for adjudication and it is common ground that any adjudication would have to be carried out in accordance with the Scheme for Construction Contracts (“the Scheme”).”
“[21] At one point, it was apparent that Mr Hickey was itching to submit that the provisions in the 1996 Act ought to be incorporated wholesale, even in a hybrid contract, to apply to all the works. But it seems to me that, first, that submission would have run counter to s 104(5), which expressly provides that the provisions in the Act apply ‘only so far as’ they relate to construction operations; and secondly, ignores the fact that the parties have expressly agreed a different payment regime … In my view, the court must uphold that different regime in respect of all claims to payment in respect of works which are excluded by the 1996 Act. [22] This means that, under a hybrid contract such as this, there are two very different payment regimes. That is what Ramsey J indicated in Cleveland Bridge. Although I find that uncommercial, unsatisfactory and a recipe for confusion, it is the inevitable result of Parliament’s desire to exclude what would otherwise have been obvious construction operations from the ambit of the 1996 Act.”
“[32] The whole point of the default provisions in the 1996 Act, by which an employer becomes liable for the sum notified, is to encourage simplicity and clarity. If x notifies y of a claim for£1,000 , and y does not respond in the prescribed time to challenge that claim,£1,000 becomes due because it is the notified sum. Introducing the possibility of a partial claim for£675 , by reference to a gloss put on an accompanying spreadsheet, would be to confuse the simple system of notification envisaged by the 1996 Act. [33] That interpretation is reinforced by a consideration of the next statutory requirement, that in order to be payment notice, the notice has to set out the basis on which the sum claimed has been calculated … interim payment claim 15 was for everything. There was therefore no explanation in the payment notice of the calculation of£1.4m as being the minimum due in respect of construction operations within the 1996 Act… [34] … Because this was a hybrid contract, it was imperative that the claimant spell out the fact that, regardless of the position in relation to excluded operations, this was a payment notice (with all that that entailed) in respect of the claim for construction operations. … [36] In those circumstances it seems to me inequitable now to penalise the defendant for failing to respond within the limited time prescribed by the 1996 Act, in circumstances where the parties had been operating the contract in a different way, and when interim application 15 did not give any indication that it was a payment notice in respect of a specific part of the claim. If the claimant wanted to take advantage of the right that it has under the 1996 Act, then it had to do so in an open way. The least that the claimant could have done was to spell out in the December 2014 notice how the claim was split and why it was that in respect of the claim for construction operations, a very truncated timetable applied.”