“The courts take a robust approach to adjudication enforcement, enforcing the decisions of adjudicators by summary judgement regardless of errors of procedure, fact or law, unless the adjudicator has acted in excess of jurisdiction or in serious breach of the rules of natural justice: Macob Civil Engineering Ltd v Morrison Construction Ltd[1999] BLR 93 per Dyson J at [14]; Carillion v Devonport Royal Dockyard[2005] EWHC 788 (TCC) per Jackson J at [80]; Carillion v Devonport Royal Dockyard[2005] EWCA 1358 per Chadwick LJ at [85]-[87]; J&B Hopkins Ltd v Trant Engineering Ltd[2020] EWHC 1305 per Fraser J at [12]-[16]; Bresco Electrical Services Ltd v Michael j Lonsdale (Electrical)[2020] UKSC 25 per Lord Briggs at [17]-[26].”
“It is clear that Parliament intended that the adjudication should be conducted in a manner which those familiar with the grinding detail of the traditional approach to the resolution of construction disputes apparently find difficult to accept. But Parliament has not abolished arbitration and litigation construction disputes. It has merely introduced an intervening provisional stage in the dispute resolution process. Crucially, it has made it clear that decisions of adjudicators are binding and are to be complied with until the dispute is finally resolved.”
“In general, an unsuccessful party to an adjudication cannot seek to avoid the result of that adjudication by relying on the right to set-off any other claims… It has often been said that where there are subsequent cross claims, the right course is for the losing party to comply with the adjudicator’s decision and not withhold payment on the ground of his anticipated recovery in a further claim…”
“As I have said, these things are always a matter of fact and degree. An adjudicator cannot, and is not required to, consult the parties on every element of his thinking leading up to a decision, even if some elements of his reasoning may be derived from, rather than expressly set out in, the parties’ submissions. But where, as here, and adjudicator considers that the referring party’s claim as made cannot be sustained, yet he himself identifies a possible alternative way in which a claim of some sort could be advanced, he will normally be obliged to raise that point with the parties in advance of his decision. It seems to me that that principle must apply a fortiori in circumstances where the document from which the alternative approaches to be derived, is a document which the adjudicator was told by the parties to ignore. In those circumstances, common sense demands that, before reaching any conclusion, the adjudicator must ask the parties for their submissions on that alternative approach.”
“…there is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party had contended, provided the parties were aware of the relevant material and the issues to which it gave rise have been fairly canvassed before the adjudicator.”
“Where an adjudicator has departed from the four corners of the submissions made by the parties, was it fair not to seek further submissions? If the issues have been fairly canvassed, or if the adjudicator has simply adopted an intermediate position, fairness will not require that the parties be given an opportunity to make further submissions. Conversely, if the adjudicator proposes a novel approach on a significant issue which has not been canvassed, fairness will point in the opposite direction.”
“8.1. For the purposes of these conditions: .1 a company becomes Insolvent .1 when it enters into administration within the meaning of schedule B one of theInsolvency Act 1986 … Other rights, reinstatement .1 The provisions of clauses 8.4 to 8.7 are without prejudice to any other rights and remedies of the Employer. The provisions in clause is 8.9 and 8.10, and (in the case of termination under either of those clauses ) the provisions of clause 8.12, are without prejudice to any other rights and remedies of the Contractor. .2 … Termination by Employer Insolvency of Contractor .1 If the Contractor is insolvent, the employer may at any time by notice to the contractor terminate the Contractor’s employment under this Contract. .2 … .3 As from the date the Contractor becomes Insolvent, whether or not the employer has given such notice of termination: .1 Clauses 8.7.3 to 8.7.5 and (if relevant) clause 8.8 shall apply as if such notice had been given; .2 The Contractor’s obligations under Article 1 and these Conditions to carry out and complete the works shall be suspended; and .3 The Employer may take reasonable measures to ensure that the site, the Works and Site Materials are adequately protected and that such Site Materials are retained on site; the Contractor shall allow and shall not hinder or delay the taking of those measures. Consequence of termination under clauses 8.4 to 8.6 8.7 If the contract of employment is terminated under clauses 8.4, 8.5 or 8.6: .1 the Employer may employ and pay other persons to carry out and complete the Works and to make good any defects of the kind referred to in clause 2.35, and he and they may enter upon and take possession of the site and the Works and (subject to obtaining any necessary third party consents) may use all temporary buildings, plant, tools, equipment and site materials for those purposes; … .2… .3 no further sum shall become due to the Contractor under this Contract other than any amount that may become due to him under clause 8.7.5 or 8.8.2 and the Employer need not pay any sum that has already become due either : .1 insofar as the Employer has given or gives a Pay Less Notice under clause 4.9.5; or .2 If the Contractor, after the last date upon which such notice could have been given by the Employer in respect of that sum, has become insolvent within the meaning of clauses 8.1.1… .4 following the completion of the Works and the making good of defects in them (or of instructions otherwise, as referred to in clause 2.35), an account of the following shall within 3 months thereafter be set out in a statement prepared by the Employer: .1 the amount of expenses properly incurred by the Employer, including those incurred pursuant to clause 8.7.1 and, where applicable, clause 8.5.3.3, and of any direct loss and/or damage caused to the Employer for which the Contractor is liable, whether arising as a result of the termination or otherwise; .2 the amount of payments made to the Contractor; and .3 the total amount which would have been payable for the Works in accordance with this Contract; .5 if the sum of the amounts stated under clauses 8.7.4.1 and 8.7.4.2 exceeds the amount stated under clause 8.7.4.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor.” 21. There are two further provisions which have been referred to in connection with clause 8.7.4. “1.1 Rectification Period: the period stated as such period in the Contract Particulars (against the reference to clause 2.35) in relation to the Works…” 22. The contract particulars provide for a rectification period of 24 months from practical completion. “2.35 If any defects, shrinkages or other faults in the works or a section appear within the relevant Rectification Period due to any failure of the contractor to comply with his obligations under this contract: .1 such defects, shrinkages or faults shall be specified by the Employer in a schedule … which he shall deliver to the Contractor as an instruction not later than 14 days after the expiry of the Rectification Period; .2…within a reasonable time after the receipt of the schedule…, the defects, shrinkages and other faults shall at no cost to the Employer be made good by the Contractor…” .1 such defects, shrinkages or faults shall be specified by the Employer in a schedule … which he shall deliver to the Contractor as an instruction not later than 14 days after the expiry of the Rectification Period; .2…within a reasonable time after the receipt of the schedule…, the defects, shrinkages and other faults shall at no cost to the Employer be made good by the Contractor…”
“What is the effect of JCT 8.3.1 in the circumstances • of the building part completed in Sept 2020 and abandoned by the Contractor. • IF Employment of the contractor is not terminated under 8.7 • IF Repudiatory breach of either party not accepted and therefore contract affirmed. • The Employer employed and paid other persons to carry out and complete the works and make good any defects under JCT 2.35 • Referral para 9 alleges Philips not entitled to employ others. • Effect of 8.3.1?” • of the building part completed in Sept 2020 and abandoned by the Contractor. • IF Employment of the contractor is not terminated under 8.7 • IF Repudiatory breach of either party not accepted and therefore contract affirmed. • The Employer employed and paid other persons to carry out and complete the works and make good any defects under JCT 2.35 • Referral para 9 alleges Philips not entitled to employ others. • Effect of 8.3.1?”
“8.6 ISSUE “Whether St Philips is correct to aver (at Response [para 1.7]) that the calculation of the final balance due is via JCT clause 8.7.4 and that is agreed by JA Ball? ADJUDICATOR’S DECISION: • NO; clause 8.7.4 cannot apply to calculate the final balance; • NO; Ball does not agree to clause 8.7.4 applying (at Reply to Response [para 11]) ADJUDICATOR’S OBSERVATION: Clause 8.7.4 applies only when employment is terminated under JCT clause 8.4, 8.5 or 8.6. In particular clause 8.5 says clause 8.7.3 to 8.7.5 applies whether or not the Employer has given such Notice of Termination. But the calculation of the account has to be “Pursuant to clause 8.7.1 (see 8.7.4.1)”
“No further sum shall be due to the contractor under this contract other than the any amount that may become due to him under clause 8.7.5 or 8.8.2”? ADJUDICATOR’S DECISION: NO. Clause 8.7.5 relies upon 8.7.4.1, but clause 8.7.4.1 relies upon a determination of the contractor’s employment. That has not happened (clause 8.8.2 does not apply). ____________________________ 8.8 ISSUE “Whether the calculation of the account/sums due machinery, clause 8 under the contract has fallen away?”
“There may be circumstances in which it is possible to demonstrate on summary judgment that the answer the adjudicator arrived at was so obviously correct, that the failure to have allowed the point to be properly ventilated is not material: permitting a party to make submissions could not have changed the outcome. However, generally, it is sufficient for a party to show that the substance of the point which they were deprived of the opportunity to engage with was properly arguable i.e. it had reasonable prospects of success. Beyond that, the Court should not determine the merits of the point itself on the summary judgment application.”
“Rule 24.2 of the Civil Procedure Rules enables the court to give summary judgment on the whole of a claim, or on a particular issue, if it considers that the defendant has no real prospect of successfully defending the claim and there is no other reason why the case or issue should be disposed of at a trial. In circumstances such as the present, where there are latent claims and cross-claims between parties, one of which is in liquidation, it seems to me that there is a compelling reason to refuse summary judgment on a claim arising out of an adjudication which is, necessarily, provisional. All claims and crossclaims should be resolved in the liquidation, in which full account can be taken and a balance struck. That is what r. 4.90 of theInsolvency Rules 1986 requires.”
“64. The reasons why summary enforcement will frequently be unavailable are set out in detail in Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2001] 1 All E.R. (Comm.) 1041; [2001] C.L.C. 927 at [29]–[35] per Chadwick LJ. As he says, the court is well-placed to deal with those difficulties at the summary judgment stage, simply by refusing it in an appropriate case as a matter of discretion, or by granting it, but with a stay of execution… 65. Furthermore it will not be in every case that summary enforcement will be inappropriate. There may be no dispute about the cross-claim, and the claim may be found to exist in a larger amount, so that there is no reason not to give summary judgment for the company for the balance in its favour. Or the disputed cross-claim may be found to be of no substance. Or, if the cross-claim can be determined by the adjudicator, because the claim and cross-claim form part of the same “dispute” under the contract, the adjudicator may be able to determine the net balance. If that is in favour of the company, there is again no reason arising merely from the existence of cross-claims why it should not be summarily enforced. 66… 67. The proper answer to all these issues about enforcement is that they can be dealt with, as Chadwick LJ suggested, at the enforcement stage, if there is one. In many cases the liquidator will not seek to enforce the adjudicator’s decision summarily. In others the liquidator may offer appropriate undertakings, such as to ring-fence any enforcement proceeds: see the discussion of undertakings in the Meadowside case. Where there remains a real risk that the summary enforcement of an adjudication decision will deprive the respondent of its right to have recourse to the company’s claim as security (pro tanto) for its cross-claim, then the court will be astute to refuse summary judgment.”
“Accordingly, it appears that, as to enforcement, Lord Briggs JSC’s starting point was that summary judgment to enforce an adjudicator’s decision will frequently be unavailable when the claimant is in liquidation, with the court either refusing it outright or granting it with an immediate stay of execution. He also noted that where the liquidator sought to enforce the adjudicator’s decision summarily, there could be a real risk that it would deprive the respondent of its right to have recourse to the insolvent company’s claim as security for its cross-claim, and that in such circumstances the court would again refuse summary judgment. It might be said with some force that those observations are directly applicable here.”
“Having regard to the decisions discussed and referred to in this judgment, I consider that the following principles are established or can be derived: (1) … (2) If, at the date of the hearing of the application to enforce an adjudicator's decision, the successful party is in liquidation, then the adjudicator's decision will not be enforced by way of summary judgment: see Bouygues v Dahl Jensen and Melville Dundas. The same result follows if a party is the subject of the appointment of administrative receivers: see Melville Dundas. (3) For the same reasons, I consider that if a party is in administration and a notice of distribution has been given, an adjudicator's decision will not be enforced. (4) If a party is in administration, but no notice of distribution has been given, an adjudicator's decision which has not become final will not be enforced by way of summary judgment. In my view, this follows from the decision in Melville Dundas as well as being consistent with the reasoning in Integrated Building Services v PIHL. (5) If the circumstances are as in paragraph (4) above but the adjudicator's decision has, by agreement of the parties or operation of the contract, become final, the decision may be enforced by way of summary judgment (subject to the imposition of a stay). I reach this conclusion because I do not consider that the reasoning of the majority in Melville Dundas extends to this situation. (6) There is no rule of English law that the fact that a party is on the verge of insolvency ("vergens ad inopiam”) triggers the operation of bankruptcy set-off: see Melville Dundas, per Lord Hope at paragraph 33. However, the law in Scotland appears to be different on this point (perhaps because the Scottish courts do not enjoy the power to grant a stay in such circumstances). (7) If a party is insolvent in a real sense, or its financial circumstances are such that if an adjudicator's decision is complied with the paying party is unlikely to recover its money, or at least a substantial part of it, the court may grant summary judgment but stay the enforcement of that judgment. 53. Straw pre-dated Bresco and Doyle. I propose to adopt the principles set in Straw with the modifications that: a. It is clear from Bresco and Doyle that even in the case of a liquidation, refusal of summary judgment is not inevitable as there may be circumstances, such as those identified by Lord Briggs at [65]. Accordingly, the decision in such cases is fact specific. b. As the decision has to be fact specific, the same must be said of an award in favour of a company which subsequently goes into administration. There is no hard and fast rule that an award will not be enforced in favour of a company in administration. For example, if the evidence is that the administration will save the business such that it can trade out of insolvency or that the company has become insolvent due to the non-payment of the award, these may be powerful reasons for giving judgment without staying enforcement; as happened in the analogous case concerning the impact of a CVA, heard together with Bresco in the Court of Appeal, Cannon Corporate Limited v Primus Build Limited[2019] EWCA Civ 27 . If, on the other hand, the defendant is disabled in pursuing its cross-claim by the administration, that would be a good reason for refusing judgment to allow the insolvency regime, which affects all creditors, to take primacy over that of adjudication, the affect of which is limited to the parties. Further, if the financial state of the claimant, which led to the insolvency would result in there being no prospect that it could repay the award if the cross-claim were successful, that would be a good reason to stay enforcement, or where notice under IR 14.29 had been given, refuse judgment following Bouygues,Bresco and Doyle. 54. The factual background against which this application it to be determined shifted during the course of the hearing. Until the second day of hearing, the claimant’s administrators would only consent to the issue of a cross-claim if the defendant paid£100,000 into court as security for costs and paid the award which was to be ringfenced for such time as a court may order to enable the defendant to pursue its claim. By a letter dated7 October 2022 , shortly before the adjourned hearing of the application, the administrators consented to permitting the defendant to issue a claim to “overturn the Adjudicator’s Decision”
“It is worth emphasising that the key aspect in relation to whether or not to enforce is the protection of the right to set off. It is the prejudice to the payor created by a combination of insolvency and adjudication not being a determinative resolution of the parties’ disputes from which protection is required.” 60. Mr Chennells makes the following points in response: a. There is little distinction between the effect of the administration in this case and the position if Ball was in liquidation. It is massively insolvent and sooner or later will be the subject of an insolvent liquidation, at which point insolvency set-off will apply. He points to evidence that Pythagoras has procured an undertaking from the administrators confirming they will not issue a notice of intended dividend during the ringfencing period and says that this is a device to avoid insolvency set-off b. Until October 2022, i.e. after the first day of hearing, the administrators were trying to stymie St Philips in pursuing their cross-claim by imposing onerous conditions. At the 11th hour, the administrators have made an unexplained volte face on this issue, but are still not permitting St Philips a free run at its cross-claim as the consent to litigate is limited to proceedings to overturn the Adjudicator’s Decision. Mr Stokell has argued that this is sufficient as the balance over the award will have to be proved in the administration, but, says Mr Chennells, St Philips cannot split up its claim just to balance the award. It will have, or would wish, to litigate its whole claim for the court to determine how much of it succeeds and, if there is success, as to the extent whereby it overtops the award. He further highlights the unreasonable stricture arising from the consent in that in any litigation by St Philips, Ball may, and probably will, wish to pursue those of the claims it made in the adjudication, but which failed, in addition to those which succeeded. Accordingly, the problem identified for a litigant facing a company in administration identified in Straw is present in this case as well. c. The Pythagoras guarantee is inadequate for a number of reasons. First, the published accounts of that company for June 2020 show capital reserves of£98,730 , well short of its potential liability under the guarantee. These were all that the claimant had provided to the defendant up to15 September 2022 . On the day before the first hearing, a third statement from Mr McMahon was produced attaching management accounts showing capital reserves of£183,648 , but these fluctuated between December 2021 and July 2022 between a minus figure of£32,000 and a positive balance of£242,000 . He says that I should bear in mind that Mr McMahon’s assertions that the company has cash of about£295,000 does not advance matters as any cash is taken into account in the management accounts. He also says that I should be unmoved by Mr McMahon’s assertions that the shareholders of Pythagoras have cash and unencumbered properties and will stand by the company to ensure it always meets its obligations. Mr Chennells relies upon the late production of this information, despite the fact that for months before the hearing, certainly from July 2022, the defendants have been saying they would not accept a Pythagoras guarantee. d. The second objection to the guarantee is that, apart from the costs of the enforcement proceedings, it is limited to new proceedings to overturn the adjudicator’s decision, whereas such proceedings will be used to determine the whole final balance between the parties. e. The assertion that the estimate of the defendant’s costs for its new claim are disproportionate assumes that it is limited to the amount of the award. The costs, which are estimated at£336,175 , are both reasonable and proportionate once one takes into account that St Philips are claiming at least£500,000 and Ball claimed£221,709 for loss of profit in the adjudication claim. Thus, a minimum of just over£700,000 is at stake. At a more granular level, the overall estimated costs of the expert phase of£35,170 , trial preparation of£52,440 and trial costs of£32,220 are unexceptional for a case proceeding in the London TCC. Whilst the defendant has produced a precedent H setting out its breakdown of costs, there is nothing similar from the clamant from which to make a comparison. f. There is no justifiable purpose in ordering the payment of a sum which will be ring-fenced and remain of no use to Ball or St Philips until disposal of the latter’s claim. He referred me, in this regard, to Doyle, where at [57]-[58] and [100] Coulson LJ expressed the view that ordering a payment into court or into an escrow account is the worst of all worlds. It deprives the defendant of the use of the cash, which is contrary to the ethos of adjudication to maintain construction industry cash flow and cannot be used by the liquidator. Mr Chennells says the same reasoning must apply to ring-fencing in this case. He accepts that it may be legitimate if there were doubts as to the defendant’s solvency, but although Mr McMahon produced a statement to suggest that there were, these have been answered by Mr Downer and the issue was not pursued by Mr Stokell. g. The funding agreement between Pythagoras and the administrators is champertous. A request for documentation about the arrangements between them was refused by Circle Law on12 September 2022 who made the bald assertion that there was compliance withDamages-Based Agreement Regulations 2013 (“DBA Regulations”) as Pythagoras was not entitled to more than 50% of any net proceeds recovered. The retainer letter, dated29 April 2021 was not provided by Ball until20 September 2022 . Having had sight of the agreement, it is clear that, contrary to reg 4(3) of the DBA Regulations, Pythagoras will be entitled to receive more than 50% of the ‘payment’ recovered, as defined by the regulations. This is because the April 2021 agreement states that it will keep 50% of recoveries after the issue of proceedings. ‘Payment’ while excluding expenses, is defined in reg 1(2), as including disbursements incurred by Pythagoras for counsel’s fees. It is, therefore, inevitable that it must be keeping more than 50% of the sums recovered. Further, in breach of reg 3, the agreement does not specify the claim or proceedings or part of proceeding to which it relates and does not specify the reason for setting the amount of payment at the level agreed. The only reason given in the agreement for the 50%, being that it is for “the significant risk we are taking”, is insufficient for these purposes. The letter of10 October 2022 setting out what Pythagoras intended by the April 2021 agreement and asserting that it would not work in such a way as to give it more than 50% of the payment, unsupported by any statement and written in the context of trying the argue that the agreement complies, is worthless, as is the letter from Circle Law with the explanation that they are paying for counsel before any realisations are split. h. Whilst a champertous agreement does not, of itself result in the proceedings which they support be an abuse, they are in this case. In Meadowside, judgment was refused where the funding agreement was unenforceable for champerty as it did not comply with the DBA Regulations. The court refused summary judgment as, on the limited evidence, there was a realistic prospect of the defendant establishing that the agreement was an abuse of process. In this case, a similar conclusion should be reached as (a) Pythagoras has no interest in the underlying business of Ball, (b) its sole interest is in what it recovers from this dispute, (c) if Ball is successful is will recover a modest sum, something less than 50% of its claim, and (d) Pythagoras and Circle Law have a clear interest in Ball winning for otherwise it gets nothing despite incurring expenditure. There is a lack of clarity as to the arrangements between Pythagoras and Circle Law as to who pays counsel. Bearing in mind that Pythagoras is 60% owned by Mr McMahon and Circle Law is owned in equal shares by Mr and Mrs McMahon, looked at realistically, the risk and reward in this action falls on Mr McMahon. i. If this is an appropriate case for granting judgment, enforcement should be stayed in accordance with the principles summarised in Wimbledon Construction 2000 Ltd v Vago[2005] EWHC 1086 (TCC) . In that case HH Judge Coulson QC, as he then was, after a review of the relevant authorities said at [26]: “…there are a number of clear principles which should always govern the exercise of the court's discretion when it is considering a stay of execution in adjudication enforcement proceedings. Those principles can be set out as follows: a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute. b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money. c) In an application to stay the execution of summary judgment arising out of an Adjudicator's decision, the Court must exercise its discretion under Order 47 with considerations a) and b) firmly in mind (see AWG). d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a)rendering it appropriate to grant a stay (see Herschell). e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House). f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if: (i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or (ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals).” was made (see Herschell); or sums which were awarded by the adjudicator (see Absolute Rentals).”