“The defendant local authority, “West Sussex”, had decided to award a service contract for highway maintenance to a company X which it judged to have the highest score in the procurement exercise. The claimant, “Amey”, started legal proceedings (“the First Action”) alleging that but for a breach of thePublic Contracts Regulations 2015 (SI 2015 No 102) it would have received a higher score than X and should have been awarded the contract. It made a claim for loss of anticipated profit and/or its tender preparation costs. West Sussex gave notice to all bidders of the legal challenge and that it considered the appropriate course of action was to terminate the procurement. West Sussex then claimed the procurement process had been lawfully abandoned and that Amey could not pursue proceedings relating to the award of a nonexistent public contract nor alleged breaches of tender rules that no longer existed. Amey issued a second set of proceedings challenging the lawfulness and effect of the abandonment. West Sussex argued the decision to abandon the procurement was lawful and, in any event, did not cause Amey any loss. Held: (1) As to the lawfulness of abandonment decision: the court should only disturb the contracting authority’s decision where there has been a manifest error. There is a broad equivalence between the concepts of manifest error and Wednesbury unreasonableness (see paragraph 81); Lion Apparel Systems v Firebuy Ltd[2007] EWHC 2179 (Ch) , Woods Building Services v Milton Keynes Council (No 2)[2015] EWHC 2172 (TCC) , followed. (2) The decision to abandon the procurement had not been irrational. The hope and belief of West Sussex that the decision would cancel Amey’s cause of action was only one element of the approach it took to the broad problem and was a rational attempt to preserve public funds taking into account a number of factors. Amey had not shown that there was any better approach for West Sussex to take than abandoning the procurement and starting again while securing the provision of interim services from another. Put another way, Amey had not shown that the decision was not expedient in the public interest (see paragraphs 82 to 83). (3) The decision did not infringe the equal treatment obligation, since all bidders were equally placed, being bidders to whom no binding commitment had been made and who accepted the risk of a rational decision to withdraw the procurement (see paragraphs 84 to 85). (4) Even though West Sussex could have explained its reasons more fully or in different terms, there was no lack of transparency which rendered its decision unlawful (see paragraph 86).”
“The Italian contracting authority provisionally awarded a public contract to the only remaining tenderer in a tendering procedure, the other tenderers having been rejected. The contracting authority subsequently concluded that the tenderer’s bid was anomalous. At the same time preliminary criminal investigations were brought against the legal representative of the tenderer in respect of, inter alia, fraud. The contracting authority decided not to proceed with the definitive award of the contract to the tenderer and to cancel the related tendering procedure, in accordance with the power available to the administration under national law to withdraw, suspend or modify its own measures. The tenderer brought an action challenging the contracting authority’s decision before the Regional Administrative Court, Lombardy, which considered that the contracting authority had failed to have regard to article 45 of Parliament and Council Directive 2004/18/EC, taking the view that under that article a tenderer might be excluded only where the tenderer had been convicted by a judgment having the force of res judicata. The court was, moreover, uncertain as to the full extent of its own jurisdiction to review the legality of a decision of a contracting authority. The court therefore referred to the Court of Justice for a preliminary ruling questions concerning the interpretation of articles 41(1), 43 and 45 of Directive 2004/18. In essence those questions were: (i) whether a contracting authority was permitted to withdraw an invitation to tender where the condition for excluding an economic operator under article 45 of Directive 2004/18 was not fulfilled; and (ii) whether, under European Union law, the national court could conduct a review of a contracting authority’s decision to take account of the reliability and suitability of the tenderers’ bids and to substitute its own assessment as to the expediency of withdrawing the invitation to tender. Held: (1) That a decision to withdraw an invitation to tender for a public contract had to comply with articles 41(1) and 43 of Directive 2004/18 but the Directive did not contain any provision concerning the substantive or formal conditions for such a decision; that European Union law permitted member states to provide in their legislation for the possibility to withdraw an invitation to tender, which was different from a decision to exclude a tenderer under article 45 of Parliament and Council Directive 2004/18/EC; that the grounds for a decision to withdraw from the procedure could be based on reasons which reflected, inter alia, the assessment as to whether it was expedient, from the point of view of public interest, to carry an award procedure to its conclusion, having regard, among other things, to any change that might arise in the economic context or factual circumstances, or the needs of the contracting authority concerned; that the grounds for such a decision might also relate to there being an insufficient degree of competition, due to the fact that, at the conclusion of the award procedure, only one tenderer was qualified to perform the contract; that, therefore, provided the principles of transparency and equal treatment were complied with, a contracting authority could not be required to carry to its conclusion an award procedure that had been initiated and to award the contract in question, even where there remained only one tenderer in contention; and that, accordingly, articles 41(1), 43 and 45 of Directive 2004/18 meant that, where the conditions for the application of the grounds for exclusion set out in article 45 were not fulfilled, that article did not preclude the adoption by the contracting authority of a decision not to award a contract for which a procurement procedure had been held and not to proceed with the definitive award of the contract to the sole tenderer remaining in contention to whom the contract had been provisionally awarded (post, paras 27, 29—30, 35—37, operative part, para 1). (2) That a decision to withdraw an invitation to tender for a public procurement contract was a decision taken by a contracting authority in relation to which a member state was required, by the third sub-paragraph of article 1(1) of Council Directive 89/665/EEC, to establish in their national law review procedures designed to ensure that decisions relating to contracts falling within the scope of Directive 2004/18 might be reviewed effectively, and as rapidly as possible, on the grounds that such decisions had infringed European Union law in the field of public procurement or national rules transposing that law; that a review of the legality of a contracting authority’s decision was as to whether an act was lawful, rather than expedient, and could not be confined to an examination of whether the decision was arbitrary; but that, in the absence of specific EU legislation, the national legislature might grant the competent national courts and tribunals more extensive powers to review whether a measure was expedient (post, paras 39— 46, operative part, para 2). Hospital Ingenieure Krankenhaustechnik Planungs GmbH (HI) v Stadt Wien (Case C-92/00 )[2002] ECR I-5553 , ECJ applied.”
“In my view the decision of the ECJ in Universale-Bau does not assist MEL. It simply confirms that at every stage the procedure for awarding a public contract must comply with both the principle of equal treatment and the principle of transparency. It is the guidelines produced by the European Court of First Instance in Citymo SA v Commission of the European Communities (Case T-271/04 ) which are relevant in the present context. In that case liability arose under the Commission's Financial Regulation, rather than directly under Directive 2004/18/EC, however the principles of transparency, proportionality, equal treatment and non-discrimination still apply (see paras 122 and 123). Significantly, for present purposes the court made clear that the contracting authority has "a very broad discretion" to refuse to conclude the contract and, therefore, to terminate pre-contract negotiations which have been started (para 111). The Court stated: "112. It follows that, in order for the condition concerning the existence of unlawful conduct to be fulfilled, the applicant must show not only that the Commission breached one of the rules of law relied on by the applicant, having regard to the circumstances of the decision not to take up the lease and consequently to terminate the pre-contract negotiations, but also that that breach constituted a manifest and serious disregard of the limits imposed on the Commission's discretion." Accordingly, if the contracting authority delays informing the other party to the negotiations of its decision to abandon the procurement and has thus continued the precontract negotiations which it knew were bound to fail, that conduct could breach the principle of good faith and amount to the abuse of its right not to contract (para 131).” "112. It follows that, in order for the condition concerning the existence of unlawful conduct to be fulfilled, the applicant must show not only that the Commission breached one of the rules of law relied on by the applicant, having regard to the circumstances of the decision not to take up the lease and consequently to terminate the pre-contract negotiations, but also that that breach constituted a manifest and serious disregard of the limits imposed on the Commission's discretion." Accordingly, if the contracting authority delays informing the other party to the negotiations of its decision to abandon the procurement and has thus continued the precontract negotiations which it knew were bound to fail, that conduct could breach the principle of good faith and amount to the abuse of its right not to contract (para 131).”
“The duty of equal treatment requires that the contracting authority must treat both parties in the same way. Thus "comparable situations must not be treated differently" and "different situations must not be treated in the same way unless such treatment is objectively justified": see Fabricom v Belgium [2005] ECR1-01559 at paragraph 27. Thus, the contracting authority must adopt the same approach to similar bids unless there is an objective justification for a difference in approach.”
“In general … to ensure the development of effective competition, leading to selection of the best bid. Thus … the principle generally forbids different treatment of entities in a comparable competitive position. This approach to equal treatment, as articulated in the previous edition of the present book, was expressly endorsed in domestic law by Briggs J in the High Court in Azam & Co. v Legal Services Commission[2010] EWHC 960 (Ch) at [35], concluding that all potential bidders need to be given access to substantially the same information.”
“35. The court must carry out its review with the appropriate degree of scrutiny to ensure that the [...] principles for public procurement have been complied with, that the facts relied upon by the Authority are correct and that there is no manifest error of assessment or misuse of power. 36. If the Authority has not complied with its obligations as to equality, transparency or objectivity, then there is no scope for the Authority to have a ‘margin of appreciation’ as to the extent to which it will, or will not, comply with its obligations. 37. In relation to matters of judgment, or assessment, the Authority does have a margin of appreciation so that the court should only disturb the Authority’s decision where it has committed a ‘manifest error’. 38. When referring to ‘manifest’ error, the word ‘manifest’ does not require an exaggerated description of obviousness. A case of ‘manifest error’ is a case where an error has clearly been made (at para.15).”
“Chandler was a claim for Judicial Review and the relevant passage was in response to a submission that a complaint that the public procurement regime had not been complied with was a matter for private, not public, law. That submission was rejected as an oversimplification because a failure to comply with the Public Contracts Regulations may give rise to situations where a public body may be subject to public law review and remedies.”
“There are not yet any cases in which the application of judicial review principles has been accepted in a way that has clearly added to the obligations under the legislation itself.”
“… Implementation of the Trust’s estate strategy; estates rationalisation; capital programme planning; master-planning; raising finance and investment; strategic non-clinical or clinical service transformation planning; healthcare planning in relation to configuration of services in the estate; and also the procurement and project/contract management of a range of services in relation to the delivery of New Projects (including construction and FM Facilities management. ) and Secondary Services (as defined below). These services are expected to be provided through a joint venture body (JV) established between the Trust and the Partner.”
“I understand this decision is in line with the outcome of the Trust’s procurement process and that you have discussed the matter with stakeholders, including local MPs, and as a Board have assured yourself on this decision.”
“Unfortunately we had some important discussions this week when four of you were unavailable and not present. The first, I was surprised to hear about, is a complete turnaround on the estates plan. Not only are we abandoning it and looking at alternatives, we face an expensive legal action which NHSI will underwrite only to the extent of£200,000 . I am struggling to separate my annoyance with NHSI, the manner in which we have been marched up and down and up and down this particular hill and how we handle the communications with the much bigger issues that this is a critical and major decision. I fear that it seems to me that the Executive have reacted rather than taken this as a positive and deliberate choice. Too many of the arguments that were deployed to make us back the original choice now seem to have evaporated. The biggest reason behind this is inevitably politics with NHSI completely compromised by the possibility of any political ripples and the London Mayor’s intervention. Nothing will ever appear in writing or even be said but it has been made clear the SEP is dead!”
“I agree that we would benefit from further discussion around the way forward on Estates as I am keen that, regardless of NHSI’s blocking tactics, we press on with our transformation plans, particularly the vision that a master plan will bring. I also think we need to be very clear how any change of heart on signing a SEP is communicated as it would be unfortunate if it increased the power of certain lobby groups!”
“I met with both Steve Bloomer and Siobhan this afternoon and was taken step by step through the process with NHSI. Other elements have also played a part, though I still believe we are seeing off [DWHC] and the politicians are not engaging sufficiently to understand the complexities or the limits to how much we will use our ‘preferred bidder’. But the involvement of the Mayor for entirely political reasons and the NHSI lack of backbone mean that there are no options. … The three phases [of the discussion we will have] are how we got to where we are including legal implications and risks, how we accelerate the master plan, and what vehicle we adopt to deliver the estates strategy. Only after that can we plan the PR strategy but for the present that will be to maintain the mantra “We haven’t signed any contract. On the good news side Steve [Bloomer] believes we will secure more funding from NHSI not least because we are in their good books having hit the control total last year, agreed it for next year, reduced the overall deficit to approaching£1m , met the agency cap and delivered a surplus!...”
“As the Trust is still not in a position to sign the contract I believe that we should hold off on any further activity / meetings so as not to incur additional costs at this time. We will review this regularly and move forward when the position changes”
“Two of the key reasons for pursuing the SEP in preference to other options (namely (1) the need for JV partner investment and working capital; (2) the need for JV partner resource) have now fallen away due to the Trust’s improved financial position and strengthened relationships with the NCL STP, Haringey and Islington Health and Wellbeing Partnership, the GLA, London Estates Board and neighbouring Trusts. The Trust is now in a stronger position to be able to access additional support from a range of partner organisations (as opposed to a single JV partner) to produce the required capacity and capability, and through these relationships generate significant investment funds. The adoption of a more traditional approach to estates transformation is therefore preferred; In addition, there are new risks associated with pursuing the SEP namely: (1) the risk that the Trust will not be able to engage stakeholders sufficiently in the development of a deliverable masterplan nor gain stakeholder support for business plans developed through a SEP; and (2) the fact that the Trust will face additional decision-making hurdles by NHSI that all developments undertaken through the SEP would be classed as ‘novel and contentious’, and therefore would require full business cases for all new projects, including business cases below£15million which would not be subject to the usual delegated authority for capital investment”