“When referring to a ‘manifest’ error, the word ‘manifest’ does not require any exaggerated description of obviousness. A case of ‘manifest error’ is a case where an error has clearly been made.”
“115. Third, I agree with Mr Anderson that it is not my task merely to embark on a remarking exercise and to substitute my own view but to ascertain if there is a manifest error, which is not established merely because on mature reflection a different mark might have been awarded. Fourth, the issue for me is to determine if the combination of manifest errors made by Newham in marking the tenders would have led to a different result.”
“In neither EU nor domestic law is there an articulation of what is understood by "manifest". The phrase is defined in dictionaries as something which is: readily perceived, clear, evident, clearly apparent, obvious or plain. The etymology is from the Latin "manifestus" - palpable or manifest. These definitions are helpful only to a degree. What has to be "manifest" is the inappropriateness of a measure. There are two broad types of case where inappropriateness is put in issue. First, where it is said that a measure is vitiated by a clearly identifiable and material error. These are the relatively easy cases because the error can be identified and determined and its materiality assessed. The error may be a legal one, e.g. the measure is on its face discriminatory on grounds of nationality (as in R v Secretary of State for Transport ex Parte Factortame[1991] ECR I-3905 ). It may be a glaring error in logic or reasoning or in process. But even here there are complications since whilst it is true that an error which is plain or palpable or obvious on the face of the record may easily be termed "manifest" that cannot be the end of the story. An error which is clear and obvious may nonetheless not go to the root of the measure; it might be peripheral or ancillary and as such would not make the disputed measure manifestly inappropriate. Equally an error which is far from being obvious or palpable may nonetheless prove to be fundamental. For instance a decision or measure based upon a conclusion expressed mathematically might have been arrived at through a serious error of calculation. The fact that the calculation is complex and that only an accountant, econometrician or actuary might have exclaimed that it was an "obvious" error or a "howler", and even then only once they had performed complex calculations, does not mean that the error is not manifest. An error in the placing of a decimal point may exert profound consequences upon the logic of a measure. This suggests that manifest in/appropriateness is essentially about the nature, and, or centrality/materiality of an error. An error will be manifest when (assuming it is proven) it goes to the heart of the impugned measure and would make a real difference to the outcome.”
“Formal queries and complaints should be acknowledged in 24 hours, logged, and a reasonable response made within 5 working days. Where the issue is complex, the response may be a reasonable programme for resolution of the issue. The query/complaint must then be resolved within this programme.”
‘Provide a method statement (of two A4 pages maximum) setting out your proposals to meet the requirements of the service information.’
“Q: IS it really acceptable for£3 million of public money to be spent on reinstatement works in response to a tender where you have not received a single proposal in relation to how that£3 million worth of work is going to be done? A: [Pause] If you put it like that, No. ”
‘we got 8 but we should have got 10’
“Q: The fact that Woods used the title Project Director rather than Contract Director or Project Manager cannot provide any proper basis to penalise the Woods tender, can it? A: [pause] At the time we looked at it, that is how we looked at it. Q: I’m not asking you that question Mr Pink. We have looked at the tenders properly now. This did not provide any proper basis, did it, to penalise the Woods tender? A: [pause] No.”
“how do you propose to ensure the Health and Safety of employees, residents and other stakeholders on site?”
“please describe how you would manage the defect correction period. Please describe what procedures you have in place for managing complaints (maximum one A4 page)”
“Q: There is no mention, is there, of queries and complaints being acknowledged within 24 hours? A: No. Q: There is no mention, is there, of a reasonable response being made within five working days? A: No. … Q: So if it is not complex, it has to be the subject of a reasonable response and has to be dealt with within five working days, yes? A: Yes… Q: Let me put a very simple example to you. If you have a non-complex complaint and EAS acknowledges it after 7 days, logs it after 8 days and remedies it on day 9, that is in direct breach and is directly and clearly non-compliant with contractual KPI requirement, is it not? A: I did not see that, I thought I saw – [Repeat question] A: Correct.”
“As part of any pre-contract start meeting we will always endeavour to meet with the client’s representative and other nominated parties to look at the project requirements from all angles, ensuring that the working relationship between our company and the client’s representatives is always in the best interests of, and provides complete compliance for, the client and their residents. We can also draw on previous experience from a removal perspective as well as an analytical one to ensure that any proposed method of removal is the best option specific to the requirements of the contract whilst providing Value to Money for the clients.”