“For the performance of the SERVICES, the COMPANY shall pay the CONTRACTOR in accordance with Exhibit C hereto.”
“to be given on the whole of the claim in favour of the Claimant”
“All works in respect of the BOG Compressor House All works in respect of the LER and Substation Building All painting works; and
“Where an agreement relates to construction operations, and other matters, this Part applies to it only so far as it relates to construction operations.”
“one cannot make sense of the Act by a minute analysis of the work to see what was plant and what was not. One must look at the nature of the work broadly.”
“I do not consider that it was the intention of the Act for there to be a minute analysis to find an item which arguably was a construction operation or was within the exclusion, so as to defeat the purpose of giving or excluding the rights of the Act to what on a straightforward and commonsense analysis is a contract for construction operations within section 105(1) or excluded operations under section 105(2).”
“steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is … (ii) the production, transmission, processing or bulk storage…. of… gas… .”
“…the process engineering industry made it very clear to me - the record speaks for itself - that it has not had the same dispute and payment problems as the construction industry as a whole. That is why we decided that that industry should be excluded. In reaching that conclusion, we do not seek to exclude ordinary construction processes - there is sometimes a little of both on site. We are trying to address that consideration without embracing an industry that does not have any real problems.” (2) Also on7 May 1996 Mr Jones said that the Government were clarifying the exclusion of process engineering and continued “Examples of that are oil refining and chemicals. There has been much unnecessary confusion. We want to make it absolutely clear that only the plant and machinery and its associated steel work are excluded from the Bill and not wider construction operations on process engineering sites.”
“The passages show that the intention was to exclude steelwork which formed an integral part of the machinery and which was directly and necessarily connected to the plant and that other steelwork would come within construction operations to which the bill applied.”
“In my judgment, subject to the questions of the privileges of the House of Commons, reference to Parliamentary material should be permitted as an aid to the construction of legislation which is ambiguous or obscure or the literal meaning of which leads to an absurdity. Even in such cases references in court to Parliamentary material should only be permitted where such material clearly discloses the mischief aimed at or the legislative intention lying behind the ambiguous or obscure words. In the case of statements made in Parliament, as at present advised I cannot for see that any statement other than the statement of the Minister or other promoter of the Bill is likely to meet these criteria.”
“Where an agreement relates to construction operations, and other matters, this Part applies to it only so far as it relates to construction operations.”
“50. It is also necessary to consider what the practical effect is of construing section 105(2) narrowly or more broadly. Take the present case. On any view the main contract with AEE includes a significant amount of work which can plainly be described as “assembly installation... of plant or machinery”
“This leaves the question of whether the whole of ABB’s activities are construction operations or whether at least some of them are not, thereby requiring the statutory blue pencil exercise to be performed with regard to Palmers’ work that is provided for by section 104(5) of the Act.”
“Since a contract might in part relate to construction operations and in part works which were not construction operations, it was necessary for the legislation to regulate the application of adjudication procedure to such mixed contracts. The solution adopted was to provide (in section 104(5)) that the adjudication provisions would apply to such a contract only in so far as it related to construction operations. It therefore becomes necessary to consider on an item-by-item basis whether a contract relates to construction operations and is therefore to that extent a construction contract in respect of which the right to refer to adjudication arises.”
“ The alternative to my granting reduction was for me to hear submissions identifying that part of the adjudicator's decision that was within his jurisdiction, and enforce it to that extent only, by granting decree for payment in the pursuer's favour restricted to the sum reflecting the intra vires part of the decision. In my view either of the two suggested courses would be competent. It would, in my view, be open to me to regard the adjudicator's error as to the scope of his jurisdiction as undermining the validity of his decision as a whole, despite there being parts of it that might have been made to the same effect if he had not erred as to his jurisdiction. It would therefore be open to me to reduce the whole of the adjudicator's decision. Alternatively, it would in my view be open to me to approach the matter from the pursuers' rather than the defenders' point of view, ask myself to what extent the decision was intra vires, and grant decree for payment enforcing that part of the decision that was valid and could properly be given the statutory temporary effect.”
“Mr Nissen submitted that, even if some of the works undertaken by Gibson Lea could be regarded as “construction operations” it was plain that other items were not within that description so that, at best, the Act only applied to some of the items supplied under the contracts with which I am concerned.”
“A question which was raised in the proceedings which the judge did not have to answer in the circumstances, related to what would have been the case if part of the Contract work could be classified as “construction operations” and part not.”
“This would seem to suggest that one can adjudicate in respect to that element of a construction-related contract which addresses “construction operations”
“It seem to me that section 104(5) is intended to make clear that where a contract relates both to construction operations and to other activities, the contract is to be treated as severable between those parts which relate to construction operations and those parts which relate to other activities and the Part II and the provisions for Adjudication are to apply to the contract only in so far as the contract relates to construction operations.”
“this seems a sensible and practicable interpretation of the Act and would appear to be the only way in which real effect can be given to section 104(5).”
“the defendant has realistic prospects of success in contending that the adjudicator had no authority to decide anything other than the question of determination and liability for the two earlier invoices”
“Accordingly I have come to the conclusion that the decision is enforceable only as to the invoices of22 February 2000 for£11,300 , and£617 , if it possible to sever those amounts, which I believe it is, from the Adjudicator’s decision. Put another way the defendant does not have realistic prospects of success in resisting payment for the sum of those invoices.”
“In this case I have no means of determining how much of the adjudicator’s fees is referable to the part of the decision for which the claimant has obtained judgment. On the other hand it is clear that the adjudicator must have incurred the majority of his fees in investigating and deciding the issues on which I have decided that he had jurisdiction. In my judgment it follows from my earlier decision that the defendant does not have realistic prospects of success in relation to that part. However, equally, the claimants cannot therefore recover the whole of the amount claimed and their application for judgment in this respect fails.”
“if the sums in question did require an effective notice and if the adjudicator could not have decided that Sindall could withhold or deduct the amounts in question then he may have made an error. That is immaterial since the adjudicator’s decision has to be enforced as it stands regardless of such an error so on that basis KNS’s application has to be dismissed….”
“There may be instances where an adjudicator’s jurisdiction is in question and the decision can be severed so that the authorised can be saved and the unauthorised set aside. This is not such a case. There was only one dispute even though it embraced a number of claims or issues. KNS’s present case is based on severing parts of the adjudicator’s apparent conclusions from others. It is not entitled to do so. Adjudicator’s decision are intended to be provisional and in the nature of best shots on limited material. They are not to be used as a launching pad for satellite litigation designed to obtain what is to be attained by other proceedings, namely the litigation or arbitration that must ensue if the parties cannot resolve their differences with the benefit of the adjudicator’s opinion. KNS must therefore accept the whole of this decision and if it does not like it seek a remedy elsewhere (in the absence of successful negotiation or some other form of ADR). Furthermore I do not consider that it is right to try to dismantle and reconstruct this decision in the way suggested by KNS for that intrudes on the adjudicator’s area of decision-making. Mr Mason understandably and properly said that he had not set out all his reasons. Had he done so he might well have explained why a certain course was not in accordance with his thinking. In addition the parties have to accept the decision “warts and all”; they cannot come to the Court to have a decision revised to excise what was unwanted and to replace it with what is or was thought to be right, unless the court is the ultimate tribunal.”
“I take the view that it is not right for the Court to try and dismantle or reconstruct a decision. It seems to me that a party cannot pick and choose amongst the decisions given by an adjudicator, assert or characterise part as unjustified and then allege that the part objected to has been made without jurisdiction. … Either the Adjudicator has jurisdiction or he does not. If he has jurisdiction it seems to me that his decision is binding even if he was wrong to reach the conclusion he did.”
“In my judgment it cannot be right that it is open to a party to an adjudication simultaneously to approbate and to reprobate a decision of the adjudicator. Assuming that good grounds exist on which a decision may be subject to objection, either the whole of the relevant decision must be adopted or the whole of it must be contested. It may, of course, be important correctly to characterise what constitutes a decision of the adjudicator. It is likely that, to be relevant for the purposes now under consideration, a decision will be the answer to a question referred to the adjudicator rather than a conclusion reached on the way to providing such an answer. For example, if the adjudicator has had referred to him/her for decision the question how much money is due to the contractor and also the question to what extension of time for completion of construction works the contractor is entitled, it is likely that it will be open to a party to the adjudication to accept a determination in relation to the sum due while disputing, if otherwise there are good grounds for so doing, the assessment of the extension of time, or vice versa. In such a case two separate questions would have been referred to the adjudicator. However that situation is to be distinguished from the case in which in order to answer the question to what sum a party is entitled it is necessary to consider a number of elements of claim, or the case in which in order to reach a conclusion as to what extension of time is appropriate a number of grounds of possible entitlement to extension of time need to be considered. In each of these later cases the result of the evaluation of the various elements will be a single cash sum or a single period of extension of time. It seems to me that the option available to a party who otherwise has good grounds for objecting to a decision that a particular sum is payable is to accept it in its entirety or not at all. It does not have the option of declining to accept the decision in its entirety, but to accept the reasoning which led to particular items being included in the overall total. Similarly with an evaluation of a period of extension of time. The overall period of extension of time must be accepted or none.”
“In my judgment the alternative application for an interim payment made in this action, which in substance is a type of application frequently made as an alternative on behalf of beneficiaries of the decision of an adjudicator who are concerned as to the vulnerability of the decision, betrays a misconception as to the juridical nature of the decision of an adjudicator. The obligation on the part of those involved in an adjudication process to comply with or give effect to the decision is purely contractual. The decision of an adjudicator is not like an award of an arbitrator or the judgment of a court and directly enforceable. It is enforceable at all simply because by their contract the parties have agreed to comply with it or to give effect to it. … It is obviously conceptually possible for the parties to an adjudication procedure to agree to be bound by, and to give effect to, not only the decision on the dispute referred, but also any decision on a constituent element in the eventual overall total, or any process of reasoning adopted in the course of reaching a conclusion on the overall dispute. Whether that happened in any particular case will depend on the proper construction of the relevant contract, but it has not happened in the present case. Thus once the decision as to the total amount to be paid has been successfully attacked, it cannot be said that any other amount has been determined by [the adjudicator] to be due in a way which is binding upon Stansell. In those circumstances the necessary foundation for giving judgment for some sum less than£93,204.50 or for making of an Order for an interim payment simply does not exist.”
“(1) Where two or more disputes are referred to an adjudicator, a valid objection to one decision, on jurisdictional or natural justice grounds, will not necessarily affect the validity and enforceability of the adjudicator’s decision on the other dispute or disputes. (2)Where a single dispute is referred to one adjudicator, it may not be severed so as to excise a part of the decision to which valid objection is taken, on jurisdictional or natural justice grounds, leaving the balance valid and enforceable. A decision on the single dispute is either valid and enforceable or invalid and not enforceable.”
“(a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises. ... (c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deal with the other(s). .... (e) There is a proviso to (c) ... above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced. (f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the court.”
“This will allow the Adjudicator’s decision to be severable, should this prove to be necessary upon enforcement, in the event that the Adjudicator finds in favour of the referring party.”
“The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.”
“In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction ... the decision will not be enforced by the Court.”