“25. Thus, the contractual regime for interim payments under the Subcontract is as follows. CSL is entitled to make an application for an interim or instalment payment on a monthly basis upon completion of each milestone. Each application submitted by CSL must set out CSL's assessment of the amount due in respect of completed milestones and any other amounts to which CSL considers itself to be entitled, together with the basis of calculation of the sum claimed and supporting documentation, less sums previously certified. Each instalment payment becomes due sixteen days after the date of CSL's application ("the Payment Due Date"). The contract manager issues a certificate sixteen days after the application, setting out his response to the application, including the basis on which the certified sum has been calculated. MW is obliged to pay the sum due nineteen days after the Payment Due Date ("the Final Date for Payment"). If MW intends to pay less than the sum due, it must issue a pay less notice no later than one day before the Final Date for Payment. Subject to any pay less notice, the sum due is (a) the amount certified for payment in the contract manager's certificate or, in the absence of such certificate, (b) the amount assessed by CSL as due in its application.”
“(5) Where an agreement relates to construction operations and other matters, this Part applies to it only so far as it relates to construction operations.”
“110A Payment notices: contractual requirements (1) A construction contract shall, in relation to every payment provided for by the contract - (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date. (2) A notice complies with this subsection if it specifies - (a) in a case where the notice is given by the payer - (i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated; (b) in a case where the notice is given by a specified person - (i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated. (3) A notice complies with this subsection if it specifies - (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated. (4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero. (5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply. (6) In this and the following sections, in relation to any payment provided for by a construction contract - “payee” means the person to whom the payment is due; “payer” means the person from whom the payment is due; “payment due date” means the date provided for by the contract as the date on which the payment is due; “specified person” means a person specified in or determined in accordance with the provisions of the contract.” (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date. (a) in a case where the notice is given by the payer - (i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated; (b) in a case where the notice is given by a specified person - (i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated. (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated. “payee” means the person to whom the payment is due; “payer” means the person from whom the payment is due; “payment due date” means the date provided for by the contract as the date on which the payment is due; “specified person” means a person specified in or determined in accordance with the provisions of the contract.”
“64. It also follows that the right to refer disputes to adjudication under section 108, the entitlement to stage payments under section 109, the provisions as to dates of payment under section 110, the provisions as to notice of intention to withhold payment under section 111, the right to suspend performance for non payment under Section 112 and the prohibition of conditional payment provisions under section 113 will only apply to the Subcontract in this case, insofar as the Subcontract relates to construction operations… 91. It is clear that the legislation could have dealt with agreements which related both to construction operations and to "other maters" being operations which were not construction operations, in a number of ways. It would have been possible to treat them either as being agreements for construction operations or as not being agreements for construction operations. It would also have been possible for that question to depend on the relative values of the construction operations and of the "other matters". It is clear that Parliament decided that, just because an agreement related, in part, to operations which were not construction operations, this did not prevent the implied terms under section 114(4) of the Act from applying to the construction operations. It follows that a party can refer a dispute arising under the agreement, insofar as it relates to construction operations, to adjudication under a procedure complying with section 108 of the Act. In this case the contract contained no provision for adjudication and it is common ground that any adjudication would have to be carried out in accordance with the Scheme for Construction Contracts. ("the Scheme").”
“105. Where a party refers a dispute to an adjudicator who only has jurisdiction in respect of part of that dispute, I do not consider that there is anything, in principle, which prevents the adjudicator from making a decision as to that part of the dispute which is within his or her jurisdiction. In other words, the fact that part of the dispute relates to matters over which an adjudicator has no jurisdiction does not prevent the adjudicator from exercising the jurisdiction that he or she has. 106. In summary therefore I do not see that there is any objection in the way in which the Notice of Adjudication or the Notice of Referral were drafted which means that, to the extent that the dispute was within the Adjudicator's jurisdiction, she could give a valid decision… 116. It is clear that if the dispute referred to adjudication in this case had been limited to the part for which the Adjudicator had jurisdiction there would have been a valid adjudication and a valid decision. Where there is an overall dispute as to payment, delay or disruption arising in part from construction operations and in part from other excluded operations then the adjudication provisions cannot be applied to only part of that overall dispute. If that overall dispute can be divided so that part of the overall dispute relates only to construction operations then that part can be referred to adjudication.”
“21. Beyond the passage to which I have referred in the judgment of Ramsey J in Cleveland Bridge (paragraph 19 above), there is no other authority which addresses the question of what payment provisions apply to a hybrid contract. At one point, it was apparent that Mr Hickey was itching to submit that the provisions in the 1996 Act ought to be incorporated wholesale, even in a hybrid contract, to apply to all the works. But it seems to me that, first, that submission would have run counter to s.104(5), which expressly provides that the provisions in the Act apply "only so far as" they relate to construction operations; and secondly, ignores the fact that the parties have expressly agreed a different payment regime (paragraph 6 above). In my view, the court must uphold that different regime in respect of all claims to payment in respect of works which are excluded by the 1996 Act. 22. This means that, under a hybrid contract such as this, there are two very different payment regimes. That is what Ramsey J indicated in ClevelandBridge. Although I find that uncommercial, unsatisfactory and a recipe for confusion, it is the inevitable result of Parliament's desire to exclude what would otherwise have been obvious construction operations from the ambit of the 1996 Act.”
“33 That interpretation is reinforced by a consideration of the next statutory requirement, that in order to be payment notice, the notice has to set out the basis on which the sum claimed has been calculated. Because the notice of December 2014 and the accompanying spreadsheet did not begin to address the complexities of what were and were not construction operations, interim payment claim 15 was for everything. There was therefore no explanation in the payment notice of the calculation of£1.4 million as being the minimum due in respect of construction operations within the 1996 Act. So it was not a payment notice in respect of the claim for£1.4 million for construction operations, because the basis for the calculation of that figure, let alone the figure itself, is nowhere explained or set out in interim payment application 15. 34. Thirdly, I have concluded that, in so far as it is now said that the notice of December 2014 is a payment notice for£1.4 million in respect of construction operations, such a claim is not at all clear or unambiguous from a perusal of either the notice or the accompanying spreadsheet. How could it be, when the claimant was claiming for everything, regardless of whether or not the works were construction operations within the Act? Because this was a hybrid contract, it was imperative that the claimant spell out the fact that, regardless of the position in relation to excluded operations, this was a payment notice (with all that that entailed) in respect of the claim for construction operations.”