“1. The following documents (hereinafter called “the Contract”) shall be read as one and shall constitute the entire express agreement between the parties with respect to the Works and shall prevail over and supercede all prior agreements, understandings, statements, commitments and communications between the parties with respect to the Works and neither party shall be bound by any of the foregoing not appearing in or incorporated by specific reference into the Contract. (a) This Contract Agreement … (d) The Conditions of Contract are the Core Clauses for Option A: Priced Contract with Activity Schedule and secondary options H, L, M, P, R, Y (UK) 2, Y (UK) 3 and Z1, Z2, Z3 and Z4, as detailed in the Contract Data Part One, together with Appendix 1 … (a) This Contract Agreement … (d) The Conditions of Contract are the Core Clauses for Option A: Priced Contract with Activity Schedule and secondary options H, L, M, P, R, Y (UK) 2, Y (UK) 3 and Z1, Z2, Z3 and Z4, as detailed in the Contract Data Part One, together with Appendix 1 … 5. The Contract shall be governed by and construed in accordance with English Law and in the event of any dispute relating thereto the parties hereby submit to the jurisdiction of the Courts of England.” 7. The conditions of contract include the following clauses: “10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. The Adjudicator shall act as stated in this contract and in a spirit of independence. 11.1 In these conditions of contract, terms identified in the Contract Data are in italics and defined terms at capital initials … 51.5 Interest is calculated at the interest rate and is compounded annually … 90.2 If the Contractor is dissatisfied with an action or a failure to take action by the Project Manager, he notifies his dissatisfaction to the Project Manager no later than • four weeks after he became aware of the action or • four weeks after he became aware that the action had not been taken. Within two weeks of such notification of dissatisfaction, the Contractor and the Project Manager attend a meeting to discuss and seek to resolve the matter. 90.3 If either Party is dissatisfied with any other matter, he notifies his dissatisfaction to the Project Manager and to the other Party no later than four weeks after he became aware of the matter. Within two weeks of such notification of dissatisfaction, the Parties and the Project Manager attend a meeting to discuss and seek to resolve the matter. 90.4 The Parties agree that no matter shall be a dispute unless a notice of dissatisfaction has been given and the matter has not been resolved within four weeks. The word “dispute” (which includes a difference) has that meaning. 90.5 Either Party may give notice to the other Party at any time of his intention to refer a dispute to adjudication. The notifying Party refers the dispute to the Adjudicator within seven days of the notice … 90.8 The Adjudicator acts impartially. The Adjudicator may take the initiative in ascertaining the facts and the law. 90.9 The Adjudicator reaches a decision within twenty-eight days of referral or such longer period as is agreed by the Parties after the dispute has been referred. The Adjudicator may extend the period of twenty-eight days by up to fourteen days with the consent of the notifying Party. 90.10 The Adjudicator provides his reasons to the Parties and to the Project Manager with his decision. 90.11 The decision of the Adjudicator is binding until the dispute is finally determined by the tribunal or by agreement … 92.1 The Adjudicator gives his decision on the dispute as independent adjudicator and not as arbitrator. His decision is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award … 93.1 If after the Adjudicator • notifies his decision or • fails to do so within the time provided by this contract a Party is dissatisfied, that Party notifies the other Party of his intention to refer the matter which he disputes to the tribunal. It is not referable to the tribunal unless the dissatisfied Party notifies his intention within four weeks of • notification of the Adjudicator’s decision or • the time provided by this contract for this notification if the Adjudicator fails to notify his decision within that time whichever is the earlier. The tribunal proceedings are not started before Completion of the whole of the works or earlier termination. 93.2 The tribunal settles the dispute referred to it. Its powers include the power to review and revise any decision of the Adjudicator and any action or inaction of the Project Manager or the Supervisor related to the dispute. A Party is not limited in the tribunal proceedings to the information, evidence or arguments put to the Adjudicator.” • four weeks after he became aware of the action or • four weeks after he became aware that the action had not been taken. • notifies his decision or • fails to do so • notification of the Adjudicator’s decision or • the time provided by this contract for this notification if the Adjudicator fails to notify his decision within that time 8. The Schedule of Contract Data includes the following provisions: “1 … the Adjudicator is to be agreed between the parties … 9 Disputes and determination • The person who will choose a new adjudicator if the Parties cannot agree a choice is the - President for the time being of the Institution of Civil Engineers • The tribunal is arbitration. • The person who will choose a new adjudicator if the Parties cannot agree a choice is the - President for the time being of the Institution of Civil Engineers • The tribunal is arbitration. 10 Optional statements • The arbitration procedure is the Institution of Civil Engineers Arbitration Procedure (England and Wales) 1997 …”
“1. Preamble A Under a contract dated21st August 2001 (“the Contract”) the Employer entered into an agreement with the Contractor in which the Contractor was to construct the 1050 mm Samlesbury to Helmshore Pipeline and Associated AGI works (hereinafter called the “Works”) B Disputes have arisen between the Parties regarding the extent to which the Contract Price for the Works and the Date for completion of the Works should be changed to take into account the occurrence of certain facts, matters and events. The Parties have agreed to settle these disputes on the terms set out in this Supplemental Agreement. C The terms of the Contract shall continue with full force and effect save and except to the extent to which the terms of this Supplemental Agreement modify, alter or vary the terms contained in the Contract. 2. Terms of Supplemental Agreement. 2.1 The total Contract Price shall be adjusted to£30,500,000.00 , and the unpaid balance of this sum shall be paid in accordance with the terms set out at ection 3 of the Supplemental Agreement. 2.2 This adjustment to the total Contract Price shall be in full and final settlement of the following: i. The Contractor’s entitlement to adjustment of the total Contract Price in respect of Compensation Events (as defined by clause 60 of the Contract) where such entitlement has accrued or arisen, whether wholly or in part, by virtue of any act, omission, default, instruction, physical condition, weather condition, decision, survey, drawing or diagram inaccuracy, transaction, event or other matter occurring prior to the date of this Supplemental Agreement and regardless of whether such entitlement has been notified orally or in writing or at all, and regardless of whether such entitlement was known or not known to either Party prior to or at the date of this Supplemental Agreement. ii. The Contractor’s entitlement to reimbursement for all additional costs, losses, damages and expenses associated with carrying out the Works, including all damages for prolongation, delay and disruption, whether such entitlement arises under the Contract in tort or otherwise, where such entitlement has accrued or arisen either wholly or in part by virtue of any act, omission, default, instruction, physical condition, weather condition, decision, survey, drawing or diagram inaccuracy, transaction, event or other matter prior to the date of this Supplemental Agreement and regardless of whether such entitlement has been notified orally or in writing or at all, and regardless of whether such entitlement was known or not known to either Party prior to or at the date of this Supplemental Agreement. iii The Contractor’s entitlement to adjustment of the total Contract Price in respect of any Compensation Event (as defined by clause 60 of the Contract) arising from any act, omission, default, instruction, physical condition, weather incident, decision, survey, drawing or diagram inaccuracy, transaction, event or other matter occurring after the date of this Supplemental Agreement where such adjustment would otherwise be£5,000.00 or less. 2.3 In consideration of those matters taken into account at 2.2 (i) and (ii) above, the Date for Completion of the Works shall be: Mechanical completion:28th February 2003 Completion of the works:19th September 2003 2.4 The Contractor hereby warrants that as at the date of this Supplemental Agreement it had no entitlement to any adjustment of the total Contract Price, any entitlement to adjustment to the Date for completion of the Works or entitlement to reimbursement for additional costs, losses, damages and expenses associated with carrying out the Works other than that for which provision is now made in sections 2.2 and 2.3 of this Supplemental Agreement. 2.5 The Contractor hereby irrevocably waives and withdraws all claims against the Employer arising from any act, omission, default, instruction, physical condition, weather condition, decision, survey, drawing or diagram inaccuracy, transaction, event or other matter occurring prior to the date of this Supplemental Agreement.”
“We, Mecright Ltd, accept the sum of£366,000 in respect of manufacture, supply, delivery and installation … in full and final settlement of all our claims under the above contract but without prejudice to our outstanding obligations.”
“12. The issues as presented to me really boil down to whether the question of whether the agreement was entered into under duress is a matter which prevents me from granting the declaration sought. It is common ground that there was an agreement. Equally, the settlement agreement is an agreement which, but for the plea of economic duress, would have the effect of extinguishing all the disputes that then existed on 15th March so that there could be no dispute capable of being referred to adjudication thereafter in relation to valuation. 13. The subcontract incorporated the terms of DOM//1. Clause 38A.1 of DOM//1 applies where a party exercises its right under Article 3 to refer “any dispute or difference arising under this Subcontract to adjudication”
“We were extremely disappointed to receive your notice of adjudication dated13th July 2001 , particularly as you had indicated that you wished to resolve our differences without the need for proceedings. As you are well aware, there are a number of live issues between us, not least your refusal to honour valuation no. 12. However, for purely commercial reasons only, we are prepared to pay you the sum of£43,196.85 in full and final settlement of your claims relating to liquidated and ascertained damages under the contract. The sum is calculated as the difference between your claim for£60,000 offset against outstanding interim certificate no. 12, in the sum of£14,300.55 plus VAT, i.e.£16,803.15 . This payment will not constitute an admission that these sums are due and owing to Larraby Land Limited, nor that Quarmby Construction Company Limited waives its rights to challenge certificates issued by the Architect.”
“(6) Total fees shall not exceed£300,000 including VAT before deductions.”
“That case is, however, not relevant to this one. First and foremost, the agreement of20th February 2003 was not a settlement agreement settling all disputes or a stand alone agreement. It was clearly intended to be a variation agreement varying the terms of the underlying contract. It is to be read with and as part of that underlying contract. Furthermore, it does not settle all disputes, it merely provides a new contract sum or cap, albeit that that cap is subject to unspecified deductions. Thus, a dispute as to whether it is enforceable is one arising under the contract since its terms form part of and are to be read with the underlying contract.”
“There are special circumstances which render it inexpedient to enforce the judgment.” 51. NGG applies, pursuant to that rule, for an order that execution of McConnell’s summary judgment be stayed. The application is, essentially, based upon two grounds. First, it is said that NGG has a good prospect in future proceedings of clawing back much of the moneys awarded by the adjudicator. Secondly, McConnell is an Australian company, which is registered in Victoria. At the time of contracting with NGG, McConnell had a registered branch office in the UK. Now, however, that office has been closed down. Consequently, any judgment or arbitral award obtained by NGG will have to be enforced in Victoria. Mr Baatz submits that this process will be more time consuming and expensive than enforcing against McConnell’s registered office in England. 52. I am bound to say that I could see much force in this argument, but for McConnell’s offer of a bond. By letters dated 23rd August and19th September 2006 , McConnell’s solicitors offered to provide a bond, which would protect NGG’s position if NGG subsequently obtains a judgment or arbitral award clawing back money awarded by the adjudicator. 53. If a bond is provided by McConnell, that will be sufficient to meet the specific concerns expressed by NGG. In those circumstances, the general principle applies, that an adjudicator’s decision must be enforced promptly, even if the defendant has good prospects of recovering the money paid in later proceedings. See the judgment of Judge Coulson in Wimbledon Construction Company 2000 Limited v Derek Vago[2005] BLR 374 and the judgment of Judge Toulmin CMG QC in Hillview Industrial Developments (UK) Limited v Botes Building Limited[2006] EWHC 1365 (TCC) . 54. Let me now draw the threads together. On the basis that a bond along the lines offered in correspondence will be provided, I refuse NGG’s application for a stay. In the unlikely event that the parties are unable to agree the wording of the bond, the dispute should be referred back to myself for decision. Part 6 - The cross-applications relating to NGG’s counterclaim 55. As explained in Part 3 above, McConnell is applying for an order that the counterclaim be stayed to arbitration. NGG is applying for summary judgment in respect of part of the counterclaim and for the trial of preliminary issues. 56. Logically, I must consider first the application for a stay pursuant to section 9 of the Arbitration Act. This raises the question whether the contract contains an arbitration clause. 57. Mr Baatz submits that there is no effective arbitration clause, because clause 5 of the contract agreement overrides clauses 9 and 10 of the Schedule of Contract Data. I have come to the conclusion that this submission cannot be correct. The Schedule of Contract Data is a form published by the ICE which the parties fill in as they see fit. In the blank form, clause 9 reads: “The tribunal is …”
“The arbitration procedure is …”
“(1) A party to an arbitration agreement against whom legal proceedings are brought (whether by way of claim or counterclaim) in respect of a matter which under the arbitration agreement is to be referred to arbitration may (upon notice to the other parties to the proceedings) apply to the court in which the proceedings have been brought to stay the proceedings so far as they concern that matter. (2) An application may be made notwithstanding that the matter is to be referred to arbitration only after the exhaustion of other dispute resolution procedures … (4) On an application under this section, the court shall grant a stay unless satisfied that the arbitration agreement is null and void, inoperative, or incapable of being performed.”