“The parties’ submissions and the evidence and documents provided to support the parties’ cases are extensive in the extreme and for us to address each and every point raised by the parties would be impracticable and therefore we have confined our reasons to the essentials only …”
“ (1)The tribunal shall– (a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent; (b) adopt procedures suitable to the circumstances of the particular case, avoiding unnecessary delay or expense, so as to provide a fair means for the resolution of the matters falling to be determined” (a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent; (b) adopt procedures suitable to the circumstances of the particular case, avoiding unnecessary delay or expense, so as to provide a fair means for the resolution of the matters falling to be determined”
“1. Section 68(2)(d) is “designed to cover those issues the determination of which is essential to a decision on the claims or specific defences in the course of the reference. 2. HHJ Humphrey Lloyd was correct in Weldon Plant Ltd v The Commission for New Towns [2001] 1 All ER (Comm) 264 to state that Section 68(2)(d) is not to be used as a means of launching a detailed enquiry into the manner in which the tribunal considered the various issues. It is concerned with a failure, that is to say where the arbitral tribunal has not dealt at all with the case of a party so that substantial injustice has resulted, eg where a claim has been overlooked or where the decision cannot be justified as a particular key issue has not been decided that is crucial to the result. It is not concerned with a failure to arrive at the right answer to an issue. 3. Arbitrators do not have to deal with every argument on every point raised; they should deal with essential issues.”
“1 Reparation owed for delay in the payment of a sum of money consists of legal interest on that sum over the period that the debtor has been in default of payment. 2 At the end of each year, the amount on which legal interest is calculated is increased by the interest owed over that year”. (2) The same claim was repeated in paragraph 240 of Imtech’s Opening Submissions and put forward, in identical terms, in paragraph 237 of Imtech’s Closing Submissions; (3) In paragraph 674 of its Defence and Counterclaim GN contended that interest would not be payable under Article 6.119 of the Code until Imtech gave written notice of default to GN. GN then pleaded that interest would only be due from the date of the Points of Claim. It relied on Article 6.82 of the Code which provides that: “1. Default commences when the debtor is put into default by a written notice granting him a reasonable period for the performance and the debtor fails to perform within this period. 2 If the debtor is in a temporary impossibility to perform or it is evident from his attitude that a warning would serve no purpose, he may be put into default by a written declaration to the effect that he is held liable for his non-performance”. (4) In paragraph 305 of its Reply Imtech stated that GN was in default during the course of the works by failing to recognise variations and issue variation orders, failing to award appropriate extensions of time and failing to pay to Imtech the additional sums to which it was entitled. (5) In section P of its Closing Submissions in March 2007 GN submitted (in paragraph 903) that section 49 of the Act provides for the freedom of the parties to agree on “interests”
“It is agreed that the parties have agreed that interest is recoverable on any sums awarded in accordance with Articles 6:119 and 6:120 of the DCC as set out in paragraph 903 of GN’s Closing Submissions… The rates of interest set out in Paragraph 904 of GN’s Closing Submissions are agreed. The applicable rate of interest from1st January 2007 is 6%.” (7) In a letter dated13th June 2007 GN claimed that it did not receive the letters of12th June 2002 and18th August 2002 relied on by Imtech. And that neither letter fulfilled the requirements of Article 6.82. (8) In a later submission Imtech asserted that the letter of12th June 2002 qualified as a notice of default and invited Loyens & Loeff to reconsider its position that the letter had not been received saying “Imtech has written evidence that GN was in fact aware of the AKD letter dated12th June 2002 at that time. However the Code of Conduct of the Dutch Bar prohibits the submission of such evidence”
“It is accepted that the works had to be carried out in compliance with the Specification. It is also accepted that if Imtech’s Scope of Works documents wrongly omitted items or quantities that were part of Imtech’s scope on a true construction of the Specification, Imtech was obliged to carry out such works within the original Contract Price… .” (b) Paragraph 40: “The[BF]Specification dated June 2000 constituted the general specification for the Works but did not set out in detail the scope of Imtech’s works. It is accepted that Imtech agreed that the Specification would prevail in the event that there was any conflict between the Imtech Scope of Work documents and the Specification (e.g. if Imtech incorrectly translated the description or quantities of any system) but Imtech did not warrant that the BF Specification was adequate and complete or complied with the material rules and regulations…”
“15. It is clear and not disputed that the Claimant was obliged to carry out that work which came within the electrical scope of supply in accordance with the drawings and specification 16. The next and most important question is as to the amount of electrical work that IMI were obliged to carry out for the Contract price. The Claimant’s case is that this was delineated by their “description and scope of supply document (A2/285) and their cross reference list (A2/319)”
“38 The Confirmation Order dated20th July 2000 and the November Order both provided that the work to be undertaken by Imtech for the Contract Price was as set out in Imtech’s quotations. The detailed scope of works on which Imtech’s quotations were based (subject to specific additional deliverables) was set out in the Cross Reference List and the Technical Description Documents and the converging letters from Imtech expressly stated that the quotations were by reference to “our scope of supply”
“Imtech’s case is that 95 closing dampers and 55 fire dampers (150 in total) was a reasonable estimate based on the information available at the time of the Contract. 182 closing dampers were actually installed, 87 more than the 95 anticipated by the Contract. ….”
“The installation of 109 I/O points for Imtech’s convenience was normal practice ….”
“it would be difficult if not impossible to value the Claimant’s entitlement accurately and therefore having regard to the various authorities regarding circumstances where it is difficult or impossible to accurately value claims and doing the best we can with the various figures and evidence provided we assess the Claimant’s entitlement under this head in the sum of€1,000,000.00 .”
“3. We have carried out a thorough analysis of the claim and agreed many of the quantities, norms and rates that apply to its valuation. In summary, the Farrow assessment is Є 2,579,561, as detailed in Appendix 1 and the Kommers valuation is Є 2,419,754 (or Є 2,075,964 exclusive of ironwork) as detailed in Appendix 2 These are the figure in the Third Joint Statement. In the Fourth Joint Statement they were revised to: Farrow – Є 2,532,227 and Kommers Є 2,296,879 (or excluding Ironwork Є2, 053,935). . 4. Although we are agreed on the approach to valuation and have agreed many quantities, norms and rates, there are a number of aspects where we have different views. These can be identified from the detail in Appendices 1 and 2 and we shall address the difference and our opinions on them in our individual reports. 5. We confirm that this statement does not deal with any aspect of liability, only quantum of the claims. We also note that out agreement on figures does not bind the Parties to them.”
“The Claimant also alleges that the HVAC system included over 200 additional fans and dampers with over 1300 cables, we accept on the evidence that there was a considerable amount of additional equipment and in principle we find that the Claimant is entitled to payment for the additional cables required because of this additional HVAC equipment. We have included this example in our valuation below.”
“We have not been given the reasons for the total increase in the cabling but only 5 isolated examples plus a claim that there were additional cables required for additional HVAC equipment. There is no indication as to what the other causes of additional cable were or as to what percentage of the additional cable was taken up by the examples given or as to the likely amount of additional cable involved in example 2 which we found was the responsibility of the Claimant and therefore we do not feel that we can fairly conclude that the additional cable used is all or principally the responsibility of the Respondent. We do, however find that the Claimant is entitled to some payment in respect of examples 3 (Late information) and 4 (Clashes) and in respect of additional HVAC equipment and we recognise that it would be difficult if not impossible to value the Claimant’s entitlement accurately and therefore having regard to the various authorities regarding circumstances where it is difficult or impossible to accurately value claims and doing the best we can with the various figures and evidence provided we assess the Claimant’s entitlement under this head in the sum of€1,000,000.00 and we so Award”
“Arbitration and applicable law Any dispute or difference touching or concerning this Contract or arising there from shall be referred to arbitration in London to a single arbitrator to be appointed by agreement between the parties or, (failing agreement within 12 days after either party has given to the other a written request to concur in the appointment of a single arbitrator) to two arbitrators one to be appointed by each party and in the event that they disagree : to an umpire chosen by the two arbitrators so appointed. Any such reference shall be a submission to arbitration in accordance with theArbitration Act 1996 or any statutory variation, modification or re-enactment thereof for the time being in force.”
“(1) Unless a contrary intention is expressed therein, every arbitration agreement shall, where the reference is to two arbitrators, be deemed to include a provision that the two arbitrators may appoint an umpire at any time after they are themselves appointed, and shall do so forthwith if they cannot agree.”
“In our view the choice of umpire is at this moment premature as there is no indication yet that arbitrators might disagree. We suggest that the Tribunal should refrain from spending time to this until the issue of disagreement arises”