“In his application dated12 May 2017 the tenant has invited me to admit an irregularity in the conduct of the proceedings or in the award, pursuant tos.68(2)(i) of the Arbitration Act 1996 . The alleged irregularity which I am invited to admit is that at paragraphs 9.18 to 9.21 of my award dated8 May 2017 I treated the Lot 1 Case D notice to remedy as if it alleged that the construction of the concrete path and wall were a breach of clause (26) of the relevant tenancy agreement, when in fact that notice only alleged that it was a breach of clause (27), and I have found that there was no breach of clause (27). I invited the landlords’ submissions in response, which were made in a letter from Clarke Willmott dated3 August 2017 . I have considered those submissions, but have concluded that there was an irregularity in the conduct of the proceedings and/or in the award, because the tenant is correct that the Lot 1 Case D notice to remedy only relied on clause (27), and not also on clause (26). I have already concluded that I cannot correct this irregularity under s. 57 (or s.
“An application or appeal may not be brought if the applicant or appellant has not first exhausted— (a) any available arbitral process of appeal or review, and (b) any available recourse under section 57 (correction of award or additional award).” (a) any available arbitral process of appeal or review, and (b) any available recourse under section 57 (correction of award or additional award).”
“(1) To create formal dispositive parts of the Award recording the Arbitrator’s decision is in respect of the four notices dated19 March 2013 served on the Tenant by the Landlords under Cases D and E in Part I of Schedule 3 of theAgricultural Holdings Act 1986 … in respect of the agricultural holdings known as Lot 1 and Lot 2 at Bosawsack, Constantine, Cornwall … (2) To deal with the question whether the Tenant is liable to comply with the Case D notice to remedy a breach of the tenancy agreement dated23 March 1978 … by constructing the concrete path and retaining wall on Lot 1 when the notice … particularised the breach as a breach of clause (27) of the Tenancy Agreement and the Arbitrator found that the Tenant had not breached clause (27) by constructing the path and wall? (3) To deal with the question whether the Landlords are prevented by waiver, acquiescence or estoppel from requiring the Tenant to remedy a breach of the Tenancy Agreement constructing the path and wall by the Case D Notice? (4) To give reasons for the Arbitrator’s determination in clause 9.20 of the Award that the Case D Notice should not be modified by deleting the item of work requiring the removal of the path and wall pursuant to article 5 (a) of theAgricultural Holdings (Arbitration on Notices) Order 1987 …”
“If the Arbitrator accepts that there is an irregularity in the conduct of the proceedings or in the Award but he decides that he is unable to make the changes sought by the Tenant in paragraph 11 above, then the Arbitrator is asked formally to admit the irregularity and thus facilitate the Tenant having the court to make the changes on application under section 68(2)(i) and (3)(b) of the 1996 Act.”
“(26) No fixtures are to be erected or installed anywhere on the holding by the Tenant without the previous consent in writing of the Landlord or his agent… (27) Not to carry out any alterations or make any addition to the farm buildings (if any) or erect any new building or to make any other improvements within the meaning of Sections 49 and 50 of theThird Schedule to the Agricultural Holdings Act 1948 …”
“In so far as the notice inaccurately asserted that the rent ‘otherwise due’ had been due on and from the quarter days listed, it did not mislead and could not reasonably have misled the tenant in any way. Furthermore, it did not and could not affect the clarity of the notice as to what the tenant was required to do or what the effect would be if the tenant did not comply with it. To treat this notice as invalid, therefore, would be to carry the need for strict compliance with the statutory requirement to a length beyond any useful purpose. The statutory purpose of the notice was fully satisfied. On this ground alone I would allow this appeal.”
“The outcome in such cases does not depend on the particular circumstances of the actual parties, such as the state of mind or knowledge of the recipient or the actual prejudice caused by non-compliance on the particular facts of the case: see [32] [of Natt v Osman]. The intention of the legislature as to the consequences of non-compliance with the statutory procedures (where not expressly stated in the statute) is to be ascertained in the light of the statutory scheme as a whole: see [33]. Where the notice or the information which is missing from it is of critical importance in the context of the scheme the non-compliance with the statute will generally result in the invalidity of the notice. Where, on the other hand the information missing from the statutory notice is of secondary importance or merely ancillary, the notice may be held to have been valid: see [34]. One useful pointer is whether the information required is particularised in the statute as opposed to being required by general provisions of the statute. In the latter case the information is also likely to be viewed as of secondary importance. Another is whether the information is required by the statute itself or by subordinate legislation. In the latter case the information is likely to be viewed as of secondary importance. In this connection it must not be forgotten that while the substantive provisions of a bill may be debated clause by clause, a draft statutory instrument is not subject to any detailed Parliamentary scrutiny. It is either accepted or rejected as a whole. A third is whether the server of the notice may immediately serve another one if the impugned notice is invalid. If he can, that is a pointer towards invalidity.”
“1. I hereby give you notice that I require you to remedy within … months from the date of service of this Notice the breaches, set out below, of the terms or conditions of your tenancy, being breaches which are capable of being remedied of terms or conditions which are not inconsistent with your responsibilities to farm the holding in accordance with the rules of good husbandry. 2. This Notice requires the doing of the work of repair, maintenance or replacement specified below. Particulars of breaches of terms or conditions of tenancy Term or condition of tenancy Particulars of breach and work required to remedy it ……………………….. ……………………………………………..”
“if there is a breach then Miss Horsford acquiesced in it or waived it or is otherwise estopped from complaining about it and the landlords can be in no better position…”
“Every tenant farmer now has security of tenure for his life provided that he pays his rent and farms the land properly. The farm is thus a most valuable asset. But it is liable to be forfeited if the tenant farmer is late for two months with his rent after it is demanded. It is necessary for the landlord to make a proper demand. But, once given, if the rent is not paid within two months, the tenant farmer is out. He is given no days of grace. Even one day late is fatal. His cheque, as here, may be held up for only a day; nevertheless the landlord can say to him: ‘Out you go, you and your family, forever’. The hold-up may be due to a misunderstanding with the bank, but still the landlord can give him notice to quit. The court is powerless to help him. The statute contains no provisions to relieve him. Equity, it is said, cannot intervene. It is important that tenant farmers should know this to be the state of the law.”
“In some of the cases it is said that the plaintiffs by their acts and omissions have impliedly waived performance of the covenants. In other cases it is said that the plaintiffs, having acquiesced in past breaches, cannot now enforce the covenants. It is in all cases a question of degree. It is in many ways analogous to the doctrine of estoppel, and I think it is a fair test to treat it in that way and ask, ‘Have the plaintiffs by their acts and omissions represented to the defendant that the covenants are no longer enforceable and that he is therefore entitled to use his house as a guesthouse?’”
“40. Section 68(2)(d) provides for situations where there has been a ‘failure by the tribunal to deal with all the issues that were put to it’. 41. This ground was considered by Morison J in Fidelity Management SA v. Myriad International Holdings BV[2005] EWHC 1193 (Comm) at paragraph 9 where he summarised the following propositions which were extracted from the decision of Colman J in World Trade Corp v. Czarnikow Sugar[2005] 1 Lloyd’s Rep 422 : “1. Section 68(2)(d) is "designed to cover those issues the determination of which is essential to a decision on the claims or specific defences raised in the course of the reference". 2. HH Judge Humphrey Lloyd was correct in Weldon Plant Ltd v The Commission for New Towns [2001] 1 All ER (Comm) 264 to state that Section 68(2)(d) is not to be used as a means of launching a detailed enquiry into the manner in which the tribunal considered the various issues. It is concerned with a failure, that is to say where the arbitral tribunal has not dealt at all with the case of a party so that substantial injustice has resulted, eg where a claim has been overlooked or where the decision cannot be justified as a particular key issue has not been decided that is crucial to the result. It is not concerned with a failure to arrive at the right answer to an issue. 3. Arbitrators do not have to deal with every argument on every point raised; they should deal with essential issues. 4. "Deficiency of reasoning in an award is. . .the subject of a specific remedy under the 1996 Act [section 70(4) of the Act]. It is accordingly self-evident that: (1) failure to deal with an "issue" under section 68(2)(d) is not equivalent to failure to deal with an argument that had been advanced at the hearing and therefore to have omitted the reasons for rejecting it; (2) Parliament cannot have intended to create co-extensive remedies for deficiencies of reasons one of which (section 68) was a general remedy which might involve setting aside or remitting the award in a case of serious injustice and one of which (section 70(4)) was designed to provide a specific remedy for a specific problem; (3) the court's powers under section 68(2) being engaged only in a case where the serious irregularity has caused substantial injustice, the availability of the facility to apply for reasons or further reasons under section 70(4) would make it impossible to contend that any "substantial injustice" has been caused by deficiency of reasons." 5. Accordingly, section 68(2)(d) is confined in its application to essential issues, as distinct from the reasons for determining them. 6. "If one simply approaches that provision by asking whether that which has not been dealt with is capable of being formulated as an essential issue of the nature of what would be included in an agreed list of issues prepared for the purpose of a case management conference if instead of an arbitration the matters were to be determined in court, the answer should normally be obvious.” 42. I respectfully accept that summary as setting out the relevant considerations.” “1. Section 68(2)(d) is "designed to cover those issues the determination of which is essential to a decision on the claims or specific defences raised in the course of the reference". 2. HH Judge Humphrey Lloyd was correct in Weldon Plant Ltd v The Commission for New Towns [2001] 1 All ER (Comm) 264 to state that Section 68(2)(d) is not to be used as a means of launching a detailed enquiry into the manner in which the tribunal considered the various issues. It is concerned with a failure, that is to say where the arbitral tribunal has not dealt at all with the case of a party so that substantial injustice has resulted, eg where a claim has been overlooked or where the decision cannot be justified as a particular key issue has not been decided that is crucial to the result. It is not concerned with a failure to arrive at the right answer to an issue. 3. Arbitrators do not have to deal with every argument on every point raised; they should deal with essential issues. 4. "Deficiency of reasoning in an award is. . .the subject of a specific remedy under the 1996 Act [section 70(4) of the Act]. It is accordingly self-evident that: (1) failure to deal with an "issue" under section 68(2)(d) is not equivalent to failure to deal with an argument that had been advanced at the hearing and therefore to have omitted the reasons for rejecting it; (2) Parliament cannot have intended to create co-extensive remedies for deficiencies of reasons one of which (section 68) was a general remedy which might involve setting aside or remitting the award in a case of serious injustice and one of which (section 70(4)) was designed to provide a specific remedy for a specific problem; (3) the court's powers under section 68(2) being engaged only in a case where the serious irregularity has caused substantial injustice, the availability of the facility to apply for reasons or further reasons under section 70(4) would make it impossible to contend that any "substantial injustice" has been caused by deficiency of reasons." 5. Accordingly, section 68(2)(d) is confined in its application to essential issues, as distinct from the reasons for determining them. 6. "If one simply approaches that provision by asking whether that which has not been dealt with is capable of being formulated as an essential issue of the nature of what would be included in an agreed list of issues prepared for the purpose of a case management conference if instead of an arbitration the matters were to be determined in court, the answer should normally be obvious.”
“14. It is likely to be a serious irregularity under section 68 for the tribunal to fail to deal with all essential issues. But it may do so concisely. A failure to deal with an issue is not the same as a failure to set out the reasoning for rejecting a particular argument. Such a failure is remediable under section 70(4): see Colman J in Margulead Ltd v Exide Technologies [2004] 2 All ER (Comm) 727 and in World Trade Corporation Ltd v Czarnikow Sugar Ltd [2004] 2 All R (Comm) 813; and Morison J in Fidelity Management SA v Myriad International Holdings BV[2005] EWHC 1193 (Comm) .”
“Arbitrators do not have to deal with every argument on every point raised; they should deal with essential issues.”
“I determine that the requirement to remedy should not be deleted on the grounds that it is unnecessary or unjustified and I determine that the notice should not be modified.”
“ ‘serious irregularity’ means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant…”
“The question of law that arises from the Award is this: on the facts found by the Arbitrator, and given the statutory requirements, is the Case D Notice valid and effective to render the Tenant liable to remove the path and wall?”