“(2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant… (d) failure by the tribunal to deal with all the issues that were put to it…”
“The fact that Section 68(2)(d) is confined in its application to essential issues as distinct from the reasons for determining them should give rise no practical difficulties. If one simply approaches that provision by asking whether that which has not been dealt with is capable of being formulated as an essential issue of the nature of what would be included in an agreed list of issues prepared for the purposes of a case management conference if instead of an arbitration the matters were to be determined in court, the answer should normally be obvious.”
“…whether the arbitrators accorded to any particular evidence more weight or less weight or no weight at all was not an "issue" within the meaning of section 68(2)(d). It was merely the process of resolving the issue of what loss, if any, had been suffered by Czarnikow”
“It is likely to be a serious irregularity under section 68 for the tribunal to fail to deal with all essential issues. But it may do so concisely. A failure to deal with an issue is not the same as a failure to set out the reasoning for rejecting a particular argument. Such a failure is remediable under section 70 (4): see Colman J in Margulead Ltd v Exide Technologies [2004] 2 All ER (Comm) 727 and in World Trade Corporation Ltd v Czarnikow Sugar Ltd [2004] 2 All R (Comm) 813; and Morison J in Fidelity Management SA v Myriad International Holdings BV[2005] EWHC 1193 (Comm) .”
“In my view there has been a serious irregularity in that the Tribunal, in not addressing the waiver/estoppel defence or its Dutch equivalent at all, has failed to deal with all of the issues that were put to it and has thereby acted in a way which was unfair. The distinction between an issue, on the one hand, and a point or a line of reasoning, on the other, may on occasion be difficult to draw. But I am satisfied that the Tribunal could not deal fairly with the present case without resolving, as part of its adjudication on Claim 1, Variation 1, the issue as to whether or not Imtech had, in either of the ways asserted, precluded itself from claiming for work done between Revision 5 and Revision 23. I do not accept that the issues put to the Tribunal can be limited to the headings used for the respective claims.”
“…it should not be left to the parties, or the task of the court, to engage in speculation of that kind. If the determination of an issue is crucial to the result, as in these references waiver was crucial to the question whether there was an actionable breach of contractual warranty, then however unmeritorious the arguments might be in favour of that issue the arbitral tribunal is bound to deal with it and, in my view, to do so in such a way, normally by reference in the award or reasons, as to make it evident to the parties that the tribunal has indeed dealt with it… there should be some form of communication, normally in the form of a decision, by an arbitral tribunal to the parties from which the latter can ascertain whether or not an essential issue has been dealt with. It is not sufficient for an arbitral tribunal to deal with crucial issues in pectore, such that the parties are left to guess at whether a crucial issue has been dealt with or has been overlooked: the legislative purpose of section 68(2)(b) is to ensure that all those issues the determination of which are crucial to the tribunal’s decision are dealt with and, in my judgment, this can only be achieved in practice if it is made apparent to the parties (normally, as I say, from the award or reasons) that those crucial issues have indeed been determined.”
“A distinction is drawn in the authorities between, on the one hand, ‘issues’ and, on the other hand, what are variously referred to as (for example) ‘arguments’ advanced or ‘points’ made by parties to an arbitration or ‘lines of reasoning’ or ‘steps’ in an argument”
“The assumption of responsibility question, as it was identified and presented by PIC on this application is, to my mind, an ‘issue’ within the meaning of sub-section 68(2)(d). It is not simply a way of presenting the question of foreseeability, and not simply an argument in support of a contention that losses were not within the First Limb or the Second Limb of Hadley v Baxendale. It can be difficult to decide quite where the line demarking issues from arguments falls, but here almost the whole of Dow’s claim could have depended (and on the Tribunal’s other conclusions did depend) upon how the assumption of responsibility question was resolved. I accept PIC’s submissions about whether it was an issue because this accords with what I consider to be the ordinary and natural meaning of the word, and I find support for this conclusion in that, as I see it, fairness demanded that the question be ‘dealt with’ and not ignored or overlooked by the Tribunal, assuming it was put to them.”
“…(iii) A tribunal is not required to deal with each issue seriatim: it can sometimes deal with a number of issues in a composite disposal of them. (iv) In considering an award to decide whether a tribunal has dealt with an issue, the approach of the court (on this as on other questions) is to read it in a ‘reasonable and commercial way expecting, as is usually the case, that there will be no substantial fault that can be found with it’: Zermalt Holdings SA v Nu-Life Upholstery Repairs Ltd[1985] 2 EGLR 14 at p. 14F per Bingham J. (v) This approach may involve taking account of the parties’ submissions when deciding whether, properly understood, an award deals with an issue. Although submissions do not dictate how a tribunal is to structure the disposal of a dispute referred to it, often awards (like judgments) do respond to the parties’ submissions and they are not to be interpreted in a vacuum.”
“Mr Parsons also argued that the buyers’ contentions as to the inapplicability of the Rotterdam resale prices were not an ‘issue’ before the board but instead were an argument or a step in the argument in respect of a broader issue, namely: what was the sellers’ correct measure of damages for breach of contract. I reject this submission. In my judgment, the buyers’ contentions with respect to the inapplicability of the prices achieved on resale in Rotterdam constituted a distinct ‘issue’ before the board.”
“(a) Section 68 reflects "the internationally accepted view that the Court should be able to correct serious failures to comply with the "due process" of arbitral proceedings: cf art 34 of the Model Law." (see Lesotho Highlands Development Authority v Impregilo SpA[2005] UKHL 43 , Paragraph 27); relief under Section 68 will be appropriate only where the tribunal has gone so wrong in the conduct of the arbitration that "justice calls out for it to be corrected." (ibid). (b) The test will not be applied by reference to what would have happened if the matter had been litigated (see ABB v Hochtief Airport[2006] 2 Lloyd’s Rep 1 , paragraph 18). (c) The serious irregularity requirement sets a "high threshold" and the requirement that the serious irregularity has caused or will cause substantial injustice to the applicant is designed to eliminate technical and unmeritorious challenges (Lesotho, paragraph 28). (d) The focus of the enquiry under Section 68 is due process and not the correctness of the Tribunal’s decision (Sonatrach v Statoil Natural Gas[2014] 2 Lloyd’s Rep 252 paragraph 11). (e) Section 68 should not be used to circumvent the prohibition or limitations on appeals on law or of appeals on points of fact (see, for example, Magdalena Oldendorff[2008] 1 Lloyd's Rep 7 , Paragraph 38, and Sonatrach Paragraph 45). (f) Whilst arbitrators should deal at least concisely with all essential issues (Ascot Commodities NV v Olam International Ltd [2002] CLC 277 Toulson J at 284D), courts should strive to uphold arbitration awards (Zermalt Holdings SA v and Nu Life Upholstery Repairs Ltd[1985] 2 EGLR 14 at page 15, Bingham J quoted with approval in 2005 in the Fidelity case[2005] 2 Lloyds Rep 508 paragraph 2) and should not approach awards “with a meticulous legal eye endeavouring to pick holes, inconsistencies and faults on awards with the objective of upsetting or frustrating the process of arbitration". (g) As to Section 68(2)(d): (i) There must be a "failure by the tribunal to deal" with all of the "issues" that were “put” to it. (ii) There is a distinction to be drawn between “issues” on the one hand and “arguments”, “points”, “lines of reasoning” or “steps” in an argument, although it can be difficult to decide quite where the line demarking issues from arguments falls. However, the authorities demonstrate a consistent concern that this question is approached so as to maintain a “high threshold” that has been said to be required for establishing a serious irregularity (Petrochemical Industries v Dow[2012] 2 Lloyd’s Rep 691 paragraph 15; Primera v Jiangsu[2014] 1 Lloyd’s Rep 255 paragraph 7). (iii) While there is no expressed statutory requirement that the Section 68(2)(d) issue must be “essential”, “key” or “crucial”, a matter will constitute an “issue” where the whole of the applicant’s claim could have depended upon how it was resolved, such that “fairness demanded” that the question be dealt with (Petrochemical Industries at paragraph 21). (iv) However, there will be a failure to deal with an “issue” where the determination of that “issue” is essential to the decision reached in the award (World Trade Corporation v C Czarnikow Sugar Ltd[2005] 1 Lloyd’s Rep 422 at paragraph 16). An essential issue arises in this context where the decision cannot be justified as a particular key issue has not been decided which is critical to the result and there has not been a decision on all the issues necessary to resolve the dispute or disputes (Weldon Plan Ltd v The Commission for the New Towns[2000] BLR 496 at paragraph 21). (v) The issue must have been put to the tribunal as an issue and in the same terms as is complained about in the Section 68(2) application (Primera at paragraphs 12 and 17). (vi) If the tribunal has dealt with the issue in any way, Section 68(2)(d) is inapplicable and that is the end of the enquiry (Primera at paragraphs 40-1); it does not matter for the purposes of Section 68(2)(d) that the tribunal has dealt with it well, badly or indifferently. (vii) It matters not that the tribunal might have done things differently or expressed its conclusions on the essential issues at greater length (Latvian Shipping v Russian People’s Insurance Co[2012] 2 Lloyd’s Rep 181 , paragraph 30). (viii) A failure to provide any or any sufficient reasons for the decision is not the same as failing to deal with an issue (Fidelity Management v Myriad International[2005] 2 Lloyd’s Rep 508 , paragraph 10, World Trade Corporation, paragraph 19). A failure by a tribunal to set out each step by which they reach its conclusion or deal with each point made by a party is not a failure to deal with an issue that was put to it (Hussman v Al Ameen[2000] 2 Lloyds Rep 83 ). (ix) There is not a failure to deal with an issue where arbitrators have misdirected themselves on the facts or drew from the primary facts unjustified inferences (World Trade Corporation at paragraph 45). The fact that the reasoning is wrong does not as such ground a complaint under Section 68(2)(d) (Petro Ranger[2001] 2 Lloyd’s Rep 348 , Atkins v Sec of State for Transport[2013] EWHC 139 (TCC) , paragraph 24). (x) A tribunal does not fail to deal with issues if it does not answer every question that qualifies as an “issue”
“Turning to s.68(2)(d)) challenges in particular, the Board in RAV Bahamas observed: i) Section 68(2)(d) can be broken down into three questions. What is an issue? Has the issue been put to the arbitrators? Have the arbitrators failed to deal with it? ([38]). ii) There is a distinction to be drawn between 'issues' on the one hand and 'arguments', 'points', 'lines of reasoning' or 'steps' in an argument, although it can be difficult to decide quite where the line demarking issues from arguments falls. However, the authorities demonstrate a consistent concern that this question is approached so as to maintain a 'high threshold' that has been said to be required for establishing a serious irregularity ([40(ii)]). iii) A matter will constitute an 'issue' where the whole of the applicant's claim could have depended upon how it was resolved, such that 'fairness demanded' that the question be dealt with ([40(iii)]). iv) There will be a failure to deal with an 'issue' where the determination of that 'issue' is essential to the decision reached in the award. An essential issue arises in this context where the decision cannot be justified as a particular key issue has not been decided which is critical to the result and there has not been a decision on all the issues necessary to resolve the dispute or disputes ([40(iv)]). v) The issue must have been put to the tribunal as an issue and in the same terms as is complained about in the section 68(2) application ([42]). It is necessary to consider the arbitration proceedings as a whole, including the pleadings and the written and oral submissions. Having done so, in general what is required is that the tribunal's attention has been sufficiently clearly drawn to the issue as one which it is required to determine, such that it would reasonably be expected to deal with it. vi) If the tribunal has dealt with the issue in any way, section 68(2)(d) is inapplicable and that is the end of the enquiry; it does not matter for the purposes of section 68(2)(d) that the tribunal has dealt with it well, badly or indifferently ([43]). It matters not that the tribunal might have done things differently or expressed its conclusions on the essential issues at greater length. A failure to provide any or any sufficient reasons for the decision is not the same as failing to deal with an issue. Nor is a failure by a tribunal to set out each step by which it reached its conclusion or deal with each point made by a party a failure to deal with an issue that was put to it. vii) A tribunal may deal with an issue by so deciding a logically anterior point such that the other issue does not arise. If the tribunal decides all those issues put to it that were essential to be dealt with for the tribunal to come fairly to its decision on the dispute or disputes between the parties, it will have dealt with all the issues ([43]). viii) Whether there has been a failure by the tribunal to deal with an essential issue involves a matter of a fair, commercial and commonsense reading (as opposed to a hypercritical or excessively syntactical reading) of the award in question in the factual context of what was argued or put to the tribunal by the parties (and where appropriate the evidence) ([43]).The court can consider the pleadings and the written and oral submissions of the parties to the tribunal in this regard.”
“192. There are three references in the Award to the alleged assignment, all when summarising the parties' arguments: i) At [466], when summarising the Czech Republic's case as to what the 2014 Resolution decided. ii) At [959], when noting the Claimants' case that the assignment was invalid "so there is no reason to reduce Claimants' claim by 30% (as Mr Laputa suggests)". iii) At [1006], when noting the Czech Republic's case that there were no documents confirming the alleged invalidity of the assignment. 193. While it might be said of any issue which would impact the relief granted that the tribunal must have rejected the argument because it is not reflected in the relief, I do not think that inference cannot fairly be drawn on this occasion. On a fair, commercial and commonsense reading of the Award in question in the factual context of what was argued or put to the tribunal by the parties, I am satisfied that the tribunal did not deal with this issue in the Award”
“I am in no doubt whatsoever that the Tribunal did not deal with the Counterfactual Case either in paragraph 293 or indeed, anywhere else in the Award. In this regard there is no reference to the factual matters that Kazakhstan relied upon, the disputed issues of Kazakh law that were addressed extensively by both parties in expert evidence (both in writing and in cross-examination at the July 2022 oral hearing), the extensive submissions of the parties’ uranium experts which addressed (amongst other matters) whether WWM would have been able to fulfil the CE Contract, or the submissions of the parties’ quantum experts addressing (amongst other matters) WWM’s inability to fund TGK and satisfy its outstanding liabilities. One would expect all such matters to be dealt with as part of addressing the Counterfactual Case.”
“Nor is there any substance in WWM’s submission that the Tribunal must have dealt with the Counterfactual Case “implicitly” on the basis that it would have had the Counterfactual Case “well in mind”
“140….Experienced tribunals do fail to deal with issues that are put to them. With the greatest of respect to the eminent arbitrators in this case, even Homer nods, and experience does not bring with it infallibility, and even the most knowledgeable and skilled arbitrators can fall into error or have lapses of judgment. It is because experience shows that tribunals do fail to deal with issues that are put to them that Parliament has legislated that there will be a serious irregularity where there is “a failure by the tribunal to deal with all the issues that were put to it” (in the very words of section 68(2)(d)). This is a statutory recognition (if one were needed) that tribunals do, indeed, fail to deal with important issues that were put to them. Indeed the law reports are replete with examples where a tribunal has failed to deal with an essential issue that was put to it… 141. The issue is whether, on a fair, commercial and commonsense reading of the Award in the factual context of what was argued by the parties having regard to the evidence and the written and oral submissions of the parties, the Tribunal has failed to deal with the issue (Raytheon at [33(g)(xii] as approved in RAV Bahamas at [43])….”
“Whether [Echjay] is entitled to damages on account of [Indus’s] breach of Clause 3 of the MSA, and, if so, in what sum?” and 68.2. for Indus: “Whether [Echjay] is entitled to any damages, and, if so, in what sum?”
“….Even in the first report, capacity was identified as a factor for one out of seven products. For six out of seven products, even in the first report, the report proceeds on the basis that the existing capacity is adequate and sufficient to meet the RKFL order.”
“329. The Claimant submits that the Respondent’s Valuation Expert neglected that the Claimant’s facilities actually operate six days a week and that existing capacity is sufficient to produce the shaft parts mentioned in the meeting minutes without additional investment. 330. The Claimant argues that recalculating capacity on a six-day week basis dispels any perceived capacity shortfall…” 81.2. then at paragraph 343: “The Claimant further notes that, even if the expert’s Rebuttal Report approach were rejected, any adverse impact would affect only one shaft (Shaft No. 52854451AA) that might require new machinery for monthly outputs of 40,975 units…”
“He further clarifies that even the first expert report demonstrated adequate capacity for six out of seven products. Only one product had a capacity deficit, which was addressed in the damages analysis…”
“Next, the Parties have contentions with regards to whether the Claimant can legitimately work six days a week to enhance capacity of Shaft No. 52854451AA.”
“…that a decision as to damages involved a decision as to loss of profits and that involved a decision as to both capacity and lead time”
“Given that the Claimant is not making these parts undisputedly, the basis for the Claimant’s Quantum Expert to assert 7 months of lead time which includes validation/ PPAP, is completely based out of thin air.”
“…the products being sourced from RKFL, are not products which are being developed for the first time – they are existing products viz. products which are presently being supplied to and used by the end customers. The PPAP process for changing the supplier for existing products would be a significantly truncated and shorter process than for products which are being developed for the first time. The validation period taken into consideration by the Respondent’s Valuation Expert is therefore completely wrong.”
“…The point that I’m trying to make is that if they suppress the evidence which is in their possession, our expert has gone on the basis that if these parts are resourced parts, the lead time for approval and PPAP could be six months or seven months, which is well within the notice termination period and certainly within the two-year sunset period.”
“The Respondent states that for other shafts and gear parts, the Claimant’s expert merely relied on the Claimant’s instructions (i.e. lead times of 6 months for the shafts and 7 months for gear ring and gear pinions) without verification and that new parts or designs would need validation” 149.2. at paragraph 493: “The Respondent critiques the methodology adopted by the Claimant’s quantum expert, particularly regarding lead times for product development and validation. For instance, the expert assumes that shafts and gear pinions not currently supplied by the Claimant can be developed within six to seven months based solely on the Claimant’s instructions, without conducting independent research or consulting industry specialists. The Respondent argues this assumption is flawed, as product development in the automotive industry typically involves lengthy validation processes, often taking years” 149.3. and then at paragraph 661: “…The Respondent contends that a lead time of approximately two years is necessary to organise the specialised machinery required to meet the production requirements, and that the Claimant was unable to demonstrate that it could commence production within the two-year timeframe.”
“674. For Gear Pinion (0065122), the Tribunal has adopted the calculation in Annexure 6 of the Claimant’s Quantum Expert Report dated11th July 2024 for the period of two years and with the profit after tax of 12%, the total is USD 392,063. 675. For product reference number Gear Pinion (0067022), the Tribunal adopts the calculation in Annexure 6 of the Claimant’s Quantum Expert Report dated11th July 2024 . Applying the profit after tax of 12%, the total loss of profit for the two-year period is determined to be USD 606,862. 676. For product reference number Gear Ring (0065080), the Tribunal adopts the calculation in Annexure 6 of the Claimant’s Quantum Expert Report dated11th July 2024 . Applying the profit after tax of 12%, the total loss of profit for the two-year period is determined to be USD 575,563. 677. For product reference number Gear Ring (0065147), the Tribunal adopts the calculation in Annexure 6 of the Claimant’s Quantum Expert Report dated11th July 2024 . Applying the profit after tax of 12%, the total loss of profit for the two-year period is determined to be USD 685,980.”
“Moving on to the capacity and ramp up assumptions…”