"... ascertained by allocating to each activity bar in the Payment Programme a monetary value equal to the same percentage of the total amount attributed to the whole of that activity bar in the Payment Programme as the percentage of the total work represented by the said bar has been properly completed on Site and in accordance with the Sub-Contract ... and aggregating the said monetary values for all activity bars."
"[Cleveland Bridge] contend that in valuing their work up to15 February 2004 the fixed elements of the preliminaries should be paid for on a time elapsed basis, whereas the variable elements should be paid for by reference to what 'deliverables' (as shown in schedules 2 to 5) had been delivered. CB pointed out that this is how preliminaries were assessed during the course of the project. CB maintain that this is what the subcontract required. Accordingly, CB refer to the summary of schedules 2 to 5 and point out that15 February 2004 fell in the middle of month 17. CB claim all the fixed preliminaries shown in that summary up to month 16 plus half of the fixed preliminaries shown for month 17 plus such of the variable preliminaries as had been delivered by15 February 2004 . "
"In choosing between these rival submissions, I start with paragraph (a) of schedule 1 to the Supplemental Agreement. The court has to determine 'the gross valuation as at15 February 2004 of work properly completed on site and goods and materials brought on to site by the contractor and off-site materials in accordance with the provisions of the subcontract'. Each of those three activities (completing work on site, bringing materials on to site and procuring materials off-site) generate preliminary costs. The whole thrust of paragraph (a) is directed towards work actually done and materials actually provided. As the Court of Appeal pointed out in CA judgment 1, paragraph (a) of schedule 1 to the Supplemental Agreement is closely linked to clause 21 of the subcontract conditions; and within clause 21 the 'core provisions' is clause 21.3.2: see paragraphs 100 to 101 of May LJ's judgment. Clause 21.3.2.1 requires interim applications for payment to be based on 'the value of the works properly completed'. "
"Clause 21.4.1 of the subcontract conditions provides that the gross valuation shall be the lesser of (1) the amount specified in the Payment Profile and (2) the gross value of the works in accordance with clause 21.3.2. This provision indicates to me that (absent the Supplemental Agreement) both the Payment Profile and schedules 2 to 5 (which feed into the Payment Profile) were intended to operate as a cashflow cap, rather than as provisions which conferred automatic entitlement to payment on a time elapsed basis. "
"That interpretation does not make commercial sense. Nor does it accord with the express terms of the subcontract."
"Subsequent developments in the law of restitution demonstrate that this reasoning is no longer sound. The common law restitutionary claim is based not on implied contract but on unjust enrichment: in the circumstances the law imposes an obligation to repay rather than implying an entirely fictitious agreement to repay."
"All costs ... incurred by the subcontractor from15 February 2004 in connection with the erection and site works (being site staff, direct labour, cranes and other site related costs)."
"One point to note relates to the handling of retention. Retention was originally levied against the sums sought by Cleveland Bridge in accordance with the conditions of the subcontract as a safeguard against any future sums that might become due to Multiplex. Now that the project is complete, Multiplex accepts that Cleveland Bridge are entitled to the release of the retention levied against the valuations under schedule 2. However, it is Multiplex's case that the retention monies withheld can be applied to reduce the sums due to Multiplex by way of damages under Scott schedule 4. In these circumstances, Multiplex continue to levy retention against the sums due to Cleveland Bridge under schedule 2, but will make an appropriate cash credit for that sum against monies found to be due to Multiplex under Scott schedule 4."
"In fact retention was a complete irrelevance to the valuation exercise which the court had to undertake. Retention is obviously applicable in relation to interim valuations as work progresses. Since, however, this is a final account calculation, retention is irrelevant. Equally, the amount of the retention bond is irrelevant. However, what is relevant is that when the court carried out its final assessment of the sums payable to Cleveland Bridge and the sums paid, credit must be given for the fact that Cleveland Bridge have paid back to Multiplex in excess of£1.5 million in respect of this bond. That is the sum paid calculation will need to be£1.5 million less than it otherwise would have been."