“Future Fabrication is to be outsourced by MPX as per schedules handed by B Rogan (BR) to A Muldoon (AM) on 11/02/04 with any changes to be agreed by them.”
“The Contractor will carry out the following Sub-Contract Works: “(i) Attached A4 Schedule (2 pages) entitled “Schedule 3 MPX Fabrication responsibility including MPX sublet, China steel returned unmade and 667T CBUK sublets; (ii) Attached A4 Schedule entitled “Schedule 3 varied Sub-Contract Works Part A – Document 2””
“132. Temporary works design is not intrinsically linked to permanent works design. There are a number of ways of constructing steelwork to a given design. There is considerable scope for the ingenuity of different teams over how such erection will be achieved. In relation to temporary supports, different teams will have their own preferences, partly dependent on the equipment available to them. 133 Therefore temporary works are generally inseparable from permanent works. This was especially so on the Wembley project, where the temporary works required were extraordinarily complicated.”
“In the period post15 February 2004 , did (i) the design and drafting, and (ii) the fabrication of some or all temporary works relating to the bowl, the arch and/or the roof fall within: (a) ‘all remaining works’ (in paragraph (b) of Schedule 1 to the Supplemental Agreement); and/or (b) ‘erection and site works’ (in paragraph (c) of Schedule 1 to the Supplemental Agreement); and/or (c) ‘temp works – roof props’ (in Schedule 3 Part A to the Supplemental Agreement)?”
“158. The effect of clause 3.1 is that the fabrication referred to in that clause is not excluded altogether from the subcontract works. On the contrary, that fabrication work is to remain part of the subcontract works, but is to be paid for on a cost plus basis until such time as a new contract is agreed between the parties or, alternatively, Multiplex serves notice under clause 8. 159 Let me turn now to clause 3.2. If the phrase “all design and fabrication drawings” includes design and fabrication drawings for temporary works, then the clause makes perfectly good sense. CB retains responsibility for all designs and fabrication drawings, even though certain of those drawings are to be paid for on a cost plus basis. Alternatively, the phrase “all design and fabrication drawings” may be a somewhat clumsy reference to all design and fabrication drawings for the permanent works. However clause 3.2 is interpreted, it is not inconsistent with the conclusion that the design of roof temporary works falls outside the scope of the lump sum works.”