“(1) All issues of breach (save for the variations claims) (2) The Notional Tender Claim (Section 7 of the Amended Particular of Claim) (3) The following CBUK Settlement Claims: (i) the claim for£799,139 in respect of SV 399; (ii) the claim for£5,250,000 paid to CBUK under the CBUK Settlement Agreement; (iii) the claim for£6,073,279 in respect of the additional premium within the£12 million lump sum agreed with CBUK; (iv) the claim for the premium paid for the fabrication of steel for the PPT and bowl by Hollandia (excluding the quantum of such claim); (v) the claim for£1,280,700 in respect of the premium paid for the steel which was to be fabricated by CBUK's subcontractor in China, Shanghai Grand Tower, but which was returned to the UK for fabrication; (vi) the claim for£68,911 in respect of the audit of the moving roof carried out by Hollandia; (vii) the claim for£1,230,527 in respect of the premium paid for the pre-cast terracing installation by PCE; (viii) the claims for£6,001,955 and£167,549 in respect of payments made on a cost reimbursable basis for steel site erection works up to2 August 2004 ; (ix) the claim for£500,000 in respect of the premium paid to CBUK for the use of its temporary works. (ii) the claim for£5,250,000 paid to CBUK under the CBUK Settlement Agreement; (iii) the claim for£6,073,279 in respect of the additional premium within the£12 million lump sum agreed with CBUK; (iv) the claim for the premium paid for the fabrication of steel for the PPT and bowl by Hollandia (excluding the quantum of such claim); (v) the claim for£1,280,700 in respect of the premium paid for the steel which was to be fabricated by CBUK's subcontractor in China, Shanghai Grand Tower, but which was returned to the UK for fabrication; (vi) the claim for£68,911 in respect of the audit of the moving roof carried out by Hollandia; (vii) the claim for£1,230,527 in respect of the premium paid for the pre-cast terracing installation by PCE; (viii) the claims for£6,001,955 and£167,549 in respect of payments made on a cost reimbursable basis for steel site erection works up to2 August 2004 ; (ix) the claim for£500,000 in respect of the premium paid to CBUK for the use of its temporary works. (4) All issues of causation (including delay and disruption) up to2 August 2004 . It is recorded that the parties have agreed that: (i) the Court should investigate the causes of delay up to2 August 2004 ; (ii) the Court should determine which events caused critical delay to the Project judged at2 August 2004 ; (iii) if the Court concludes that as at2 August 2004 critical delay hadoccurred for which Mott is responsible, the question of whether that delay caused critical delay to the completion of the Project may depend on facts which occurred after2 August 2004 which are not the subject of the Sub-Trial. (iv) The Court will not investigate or determine the credit that is to be applied to any claim.”
‘there is a lot of money at stake so therefore the costs will be high’
“(a) Each party’s estimate of costs provided to the Court in advance of the CMC on11 December 2009 is to be regarded as their respective maximum likely recovery on costs at the end of the Sub-Trial, subject to (b) below. (b) If either party’s estimate has good reason to have incurred higher costs it is open to that party to identify and explain to the Court why those costs are in excess of the estimate.”