"The Subcontract constitutes the entire agreement between the Parties and supersedes all prior negotiations, commitments, representations, communications and agreements relating to the Subcontract, either oral or in writing except to the extent they are expressly incorporated herein. The Subcontractor confirms that it has not relied upon any representation inducing it to enter into the Subcontract (whether or not such representation has been incorporated as a term of the Subcontract) and agrees to waive any right which it might otherwise have to bring any action in respect of such representation. The Subcontractor further confirms that there is not in existence at the date of the Subcontract any collateral contract or warranty of which the Subcontractor is the beneficiary which might impose upon the Contractor obligations which are in addition to or vary the obligations expressly contained in the Subcontract and which relate in any way to the subject matter of the Subcontract. The Subcontractor's only rights arising out of, or in connection with, any act, matter or thing said, written or done, or omitted to be said, written or done, by or on behalf of the Contractor (or any agent, employee or subcontractor of the Contractor) in negotiations leading up to the Subcontract or in the performance or purported performance of the Subcontract or otherwise in relation to the Subcontract are the rights to enforce the express obligations of the Contractor contained in the Subcontract and to bring an action for breach thereof. Nothing in this clause 1.8 is intended to exclude liability of the Contractor for fraud or fraudulent misrepresentation."
"Valuation of Variations. Subject to the proviso to clause 4.6.2.2, Valuations for Variations which have not been agreed pursuant to the procedures under clause 4.6 shall be valued on a fair and reasonable basis consistent with the values included in the build up of the Subcontract Sum in the Numbered Documents for work or services of a similar character after making allowance for any significant change in the quantity of the work or services carried out or in conditions under which it is to be carried out. If no work or services of a similar character are included in the build up of the Subcontract sum such other basis as is fair and reasonable shall be used and such value shall be added to or deducted from the Subcontract sum."
"For the purpose of paragraph 21.3.2.1 the value of the works properly completed shall be ascertained by allocating to each activity bar in the Payment Programme a monetary value equal to the same percentage of the total amount attributed to the whole of that activity bar in the Payment Programme as the percentage of the total work represented by the said bar as has been properly completed on Site and in accordance with the Subcontract prior to the end of the Relevant Month, and aggregating the said monetary values for all activity bars."
"A valuation will be compiled up to 15-2-04 (after which the arrangements described in the foregoing will apply) including£25k for overtime for week ending 15-2-04. This valuation will be checked by an independent QS. Payment will be made on the basis of this valuation, less paid to date. The valuation will include an approximate deduction for site office rent. Should CBUK dispute any deductions made by MPX, in this valuation, then the value of the deductions, only, may be referred to Dispute Resolution."
"Unless the context otherwise requires, or this Agreement specifically otherwise provides, words and phrases used in this Agreement shall have the meanings (if any) given or ascribed to them by the Subcontract."
"Subject to Clause 2.2, the provisions of this Agreement are in full and final settlement of all disputes between the Contractor and the Subcontractor and all and any claims by the Subcontractor to the Contractor and by the Contractor to the Subcontractor existing on or before15 February 2004 under or in connection with the Subcontract whether for extension of time, direct loss and/or expense, Variations, other adjustments to the Subcontract Sum, damages for breach of contract or otherwise or howsoever arising. Neither the Contractor nor the Subcontractor shall be entitled or permitted to make or pursue any claims against the other for any matter arising from any event or circumstance occurring up to and including15 February 2004 (whether or not known to the Subcontractor)."
"Clause 2.1 shall not apply to any claim that the Contractor might have for design, workmanship or materials not being in accordance with the Subcontract."
"The Subcontract works shall be varied post15 February 2004 only by the omission of the fabrication and supply to the Site of the items specified in Schedule 3, Part A."
"Save as may be subsequently adjusted in accordance with the terms of the Subcontract (any such adjustment being subject to Clause 2.1 above), it is agreed that (taking account of all the matters referred to in Clauses 2.1, 3.1 and 3.2) the adjusted subcontract sum (exclusive of Value Added Tax) shall be as specified in Schedule 1."
"In consideration of the above, the Contractor has paid to the Subcontractor prior to the date of this Agreement the sum of£4 million (exclusive of Value Added Tax)."
"In addition, the Contractor shall pay to the Subcontractor the sum of£1.25 million (exclusive of Value Added Tax) within 14 days following completion of the lifting of the steel arch (forming part of the Subcontract works) to the position referred to in Schedule 1, paragraph (e)."
"Mr Stewart contends that the effect of clause 2.1 is that CB compromised its claim in respect of disputed pre-15th February variations. Accordingly, sums attributable to those variations should be left out of account in determining the gross valuation of the steelwork as at 15th February (as required by schedule 1, paragraph (a)). Also, sums attributable to those variations should be left out of account in determining what reimbursement is due to CB under schedule 1, paragraph (c), for fabrication and retrofit work done onsite after 15th February."
"Mr Tomlinson, on the other hand, accepts only that CB's loss and expense claims attributable to pre-15th February variations were compromised by the Supplemental Agreement. Mr Tomlinson submits that the measured value of the varied work was not so compromised. Accordingly, the measured value of the pre-15th February variations fell to be included in the valuation of the steelwork as at 15th February (required by schedule 1, paragraph (a) of the Supplemental Agreement)."
"Unless the context otherwise requires, or this Agreement specifically otherwise provides, words and phrases used in this Agreement shall have the meanings (if any) given or ascribed to them by the Subcontract."
"The Subcontract is to be read as a whole and the effect or operation of any recital, article or clause in the Subcontract must therefore unless otherwise specifically stated be read subject to any relevant qualification or modification in any other recital, article or clause in the Subcontract."
"In my view, the combined effect of these provisions in conjunction with those mentioned above is to preclude reliance upon negotiations or statements made before16th June 2004 for the purpose of displacing or qualifying any written provisions of the Supplemental Agreement."
"For the purpose of paragraph 21.3.2.1 the value of the works properly completed shall be ascertained by allocating to each activity bar in the Payment Programme a monetary value equal to the same percentage of the total amount attributed to the whole of that activity bar in the Payment Programme as the percentage of the total work represented by the said bar as has been properly completed on Site in accordance with the Subcontract prior to the end of the Relevant Month, and aggregating the said monetary values for all activity bars."