"4. Product/Quality Gasoil meeting the following guaranteed specifications: Test Limit Method ASTM Density at 15degC 0.876kg/l max D1298"
"When parties enter into a contract on terms that the certificate of some independent person is to be binding as between them, it is important that the Court should not lightly relieve one of them from being bound by a certificate which was honestly obtained and not vitiated by fraud or fundamental mistake on the part of the certifier. When, for instance, as in this case, the certificate called for by the contract is one relating to the quality of goods sold, the business purpose is to avoid disputes about quality, and that purpose is defeated unless it is made difficult for a party to go behind a valid certificate. "
"… the defendant's contention that an error in principle does not vitiate a valuation unless it is shown by the person relying on it that it also results in a materially different valuation, both in the part of the valuation subject to error and in the overall valuation."
"… I have felt compelled to the conclusion that although, as I think, Mr Jenkinson [the valuer] erred in principle in treating himself as bound on accountancy principles to regard only the break-up value, Mrs Dean has nevertheless failed sufficiently to establish that a consideration of the values of the plant 'in situ' or otherwise would produce, in all the circumstances, a figure of value materially different from that at which Mr Jenkinson arrived."
"… if the courts are satisfied that the valuation was made under a mistake, they will hold it not to be binding on the parties."
"If this error had been material, it would have been enough to vitiate the whole of the certificate, small as it might be and regrettable as the consequences might be."
"This error is not material because it does not affect the result."
"He was not there dealing with any question of burden of proof; nor – which is crucial – was he dealing, and nor indeed was Evershed MR dealing [in Dean v Prince ] with a valuation made in a manner contrary to directions binding upon the valuer as to the manner or method of valuation."
"… I do not conclude that there is any requirement of general application that where a valuation is made on an erroneous principle, yet the valuation nevertheless stands unless it is also shown that a valuation on the right principle would produce a materially different figure from the figure of the valuation that he made. (This would incidentally place on the objector the onus, not only of proving that the selected expert has acted on the wrong principle, but of incurring what might be the very heavy burden and expense of a completely new valuation, which itself might not be accepted as conclusive between the parties and merely leading to yet another valuation.) The authorities thus to my mind establish that if a valuation is erroneous in principle, it is vitiated and cannot be relied upon even though it is not established that the valuation figure is wrong."
"It is simply the law of contract. If two persons agree that the price of property should be fixed by a valuer on whom they agree, and he gives that valuation honestly and in good faith, they are bound by it. Even if he has made a mistake they are still bound by it. The reason is because they have agreed to be bound by it."
"97. Materiality must, of course, also be considered in the light of the particular contract. In this case, the contract lays down the procedures for submissions and documents passing between the parties and the expert according to a carefully regulated procedure and timetable for what is likely to be, at best, quite a lengthy process but one which is to be pursued at considerable speed. In that context, it seems to me that the test of materiality has to be capable of being applied, at the latest, at the moment when the error first comes to light, which is likely to be in the first formal document produced by the expert after the error has occurred, or on a request for clarification by one or another party soon thereafter. The ultimate effect of the error on the parties' position may not be known, or even capable of being forecast with any accuracy, especially if it arises at an early stage. Both parties agree that it cannot be necessary or possible to wait until the outcome or effect of the error is known, which may be a long way down the line, before being able to decide whether the error is sufficiently material to vitiate the expert's act. It is therefore a question of assessing materiality by reference not to whether it actually affects the ultimate result, but according to its potential effect on the result and, perhaps even more importantly, on the process, including the ability of the parties to manage and deal with the procedure in accordance with the contract. 98. I should also say that, if the expert has committed a material breach of instructions, then as a matter of law the relevant act is not binding on any of the parties, leaving aside of course the effect of their subsequent acts. It is not a point on which the court has a discretion whether or not to allow the expert's act to stand. I do not consider that Lightman J intended to suggest that there was such a discretion when summarising the law in British Shipbuilders v VSEL Consortium plc[1997] 1 Lloyd's Rep 105 at 109, even though he said that the court 'may' set the decision aside. That he did not mean to indicate that it was a discretionary issue appears in any event from the next following sentence. The relevant passage is: '(3) If the expert in … his determination fails to comply with any conditions which the agreement requires him to comply with in making his determination, the court may intervene and set his decision aside. Such a determination by the expert as a matter of construction of the agreement is not a determination which the parties agreed should affect the rights and duties of the parties, and the Court will say so.'"
"The word 'material' as used by Dillon LJ in Jones v Sherwood at p.287 ('if the mistake made was that the expert departed from his instructions in a material respect') is capable of meaning that either the mistake must be more than trivial or that the mistake must have made a material difference to the result. If it were the latter, then the protection afforded by a final certificate clause would become less effective since the court would have to try the facts to see if the error made a material difference. Since the whole purpose of the final determination provision is designed to avoid such a trial, I cannot think that the Court of Appeal meant more by the word material than 'not de minimis .' As Knox J pointed out in Nikko Hotels v MEPC[1991] 2 EGLR 103 , it is not the business of the court to weigh the importance of a stipulation in a contract. If the requirement to use the method specified in clause 4 was contractual that is an end of the matter, whether or not the court thinks it was important or would have made a difference. The assumption the court makes, on normal principles of construction, is that the parties have chosen to define their rights and obligations according to their own needs, whatever they may have been. In this case, with an on-sale, one can envisage the possibility that the Buyers wanted the old fashioned test for reasons connected with it. However, that is speculation. The position is, I think, that it is no business of the court to enquire why the Buyers asked for this particular test. That was what was agreed … "
"… it seems to me that there is no room for any debate as to whether the oversight or blunder would or would not have made any material difference to the result. If it could be shown that there was a manifest error then in my judgment that would be an end of the case. If fraud was shown, I cannot accept that it would be open to debate as to whether the fraud did or did not affect the result; so also would manifest error."
"Fraud or collusion unravels everything" (per Lord Denning in Campbell v Edward s). The exception for "manifest error", however, seems to me of a rather different character and to be designed essentially to fill the gap in the law created by the development to which I have already referred: the overthrow of the Dean v Prince principle of setting aside determinations for mistake. Nowadays, if parties wish to contract on the basis that they will not be held to mistakes made by the expert in the course of carrying out his instructions, they must needs include a term like this with regard to manifest error. But if they do, is it then really to be said that provided only the mistake is obvious, the determination will be avoided irrespective of whether it could affect the outcome? In this context I am inclined to think not. Take the very error committed in Frank H. Wright (Constructions) Limited v Frodoor , the erroneous inclusion of a 'not' in the report. I do not think that that ought properly to be regarded as a "manifest error"
"If the mistake made was that the expert departed from his instructions in a material respect- eg if he valued the wrong number of shares or valued the shares in the wrong company….either party would be able to say that the certificate was not binding because the expert had not done what he was appointed to do"