“theConstruction (Design and Management) Regulations 1994 or any remaking thereof or any amendment to a regulation therein”. b. “Development Control Requirements”: the definition as modified reads: “any statutory provisions and any decision of a relevant authority thereunder which control the right to develop the site, including any building or fire regulations, and any planning or listed building permissions, approvals, reserved matters or conditions specified or referred to therein (or to be obtained pursuant thereto) and made or to be made under any planning statutes.” c. “Planning Supervisor”: “the Contractor or the other person named in article 7.1…”
“the works briefly described in the First recital and referred to in the Employer’s Requirements and the Contractor’s Proposals and including any changes made to those works in accordance with this Contract.”
“The strip-out and partial demolition of the existing 8 storey building with its 3 levels of basements, separation from the adjacent buildings to the east, refurbishment and strengthening of part of the existing buildings and addition of a 9th floor, construction of a new 9 storey steel framed building connected to the existing retained building, fit-out of upper office floors to category A and completion of retail areas to shell and core development in phased sections at 107 Cheapside, London EC2, for which works he [the Employer] has issued to the Contractor his requirements (hereinafter called “the Employer’s Requirements”);….”
“The Contractor shall upon and subject to the Conditions carry out and complete by Sections the Works referred to in the Employer’s Requirements, …, the Articles of Agreement, these Conditions and the Appendices in accordance with the aforementioned documents and for that purpose shall complete the design for the Works….”
“16.1 When a Section has reached practical completion and the Contractor has complied with clause 6A.5.1, or has complied sufficiently with clause 6A.5.2, whichever clause is applicable, the Employer shall give the Contractor a written statement to that effect, which statement shall not be unreasonably delayed or withheld, and practical completion of such Section shall be deemed for all purposes of this Contract to have taken place on the day named in such statement. …….. 16.5 When practical completion of all the Sections has been achieved, and the Contractor has complied with clause 6A.5.1 or has complied sufficiently with clause 6A.5.2, whichever clause is applicable, in respect of all the Sections, the Employer shall give the Contractor a written statement to that effect and Practical Completion of the Works shall, for the purpose of clause 30.5.1 be deemed to have taken place on the day named in such statement.”
“The Contractor shall, by no later than the date of practical completion of each Section or the date on which the Employer takes partial possession of any part of the Works pursuant to clause 17 (hereinafter referred to as “the relevant parts of the Works”) and without further charge to the Employer, supply to the Employer 3 hard copies and 1 electronic copy on CD Rom of a full and complete health and safety file which shall have been prepared in accordance with the DCM Regulations and the Employer’s Requirements in relation to the relevant Section or the relevant part of the Works, together with 3 hard copies and 1 electronic copy on CD Rom of all working drawings and draft information showing or describing the relevant Section or the relevant part of the Works as-built and concerning the maintenance and operation thereof (including any installations comprised in such Section or the relevant part of the Works) as may be specified in the documents named in clause 5.1, such draft information to be reasonably complete and in sufficient detail to enable the relevant Section or the relevant part of the Works to be fitted out and to enable its safe occupation, use and maintenance and to include all commissioning records and test data.”
“All new construction and, where practicable, alterations and additions to the retained parts will comply with all relevant statutory regulations current at the date of the relevant consent including the current Building Regulations, appropriate British Standards/British Standard Codes of Practice and CIBSE recommendations. The recommendations including in the British Council for the Offices Specification have been used as guide in the preparation of this design.”
“Retail units are provided on the Cheapside frontage either side of the office entrance. The units will be offered at “shell” status with sleeves for incoming Utilities by tenant and capped off connection for drains”
“The retail units will be finished to Shell and Core status to include the following finishes:- Floors Concrete slab to a light tamp finish to receive a floor screed and finishes by tenant. NB. Some slabs are existing …………..”
“Reasonable provisions shall be made with respect of the following, in accordance with Approved Document M. All references in the following conditions to provisions, Tables, Diagrams, Sections and paragraphs relate to Approved Document M The objectives and design considerations with Approved Document M should be addressed in all proposals.”
“Access and egress to the building shall be provided and maintained for the life of the development for disabled persons in compliance with the provisions ofSection 4 of the Chronically Sick and Disabled Persons Act 1970 . Details of the provision shall be submitted to and approved in writing by the Local Planning Authority. REASON: To ensure that the development will be accessible for people with disabilities in accordance with the following policies….”
“10.1 The Vendor shall procure that the Employer shall keep the Purchaser informed as to the progress of the Works and every anticipated Certificate Date and shall use its reasonable endeavours to give to the Purchaser at least ten business days notice of every anticipated Certificate Date. The Purchaser’s consent shall be required for any partial possession, such consent not to be unreasonably withheld or delayed. 10.2 Without prejudice to the generality of paragraph 9.1 the Vendor shall procure that the Employer shall procure that the Employer’s representative gives to the Purchaser not less than five business days written notice of the Employer’s Representative’s intention to inspect the works for the purpose of establishing whether Practical Completion of a section has occurred. A representative of the Purchaser and a representative of the Purchaser’s lender shall have the right to accompany the Employer’s Representative on the inspection and the Purchaser’s representative shall have the right to make representations which the Vendor shall procure the Employer’s Representative to take into account (but without prejudice to the Employer’s Representative’s independent discretion in deciding whether to certify practical completion). 10.4 The Certificate of Practical Completion for each section shall be final and binding on the parties and shall be conclusive evidence for all purposes of this Schedule that Practical Completion for the relevant section has been reached save only in the case of manifest error or fraud.”
“One would normally say that a task is practically completed when it was almost but not entirely finished, but “practical completion” suggests that that is not the intended meaning and that what is meant is the completion of all construction work that has to be done.”
“The obligation upon the contractors under clause 21 to complete the works by the date fixed for completion must, in my view be an obligation to complete the works in the sense in which the words "practically completed" and "practical completion" are used in clauses 15 and 16 of the contract. I take these words to mean completion for all practical purposes, that is to say, for the purpose of allowing the employers to take possession of the works and use them as intended. If completion in clause 21 meant completion down to the last detail, however trivial and unimportant, then clause 22 would be a penalty clause and as such unenforceable…..”
“One test to be applied is whether the work was ‘finished’ or ‘done’ in the ordinary sense, even though part of it is defective. And ‘it is relevant to take into account both the nature of the defects and the proportion between the cost of rectifying them and the contract price’.”
“Practical Completion is perhaps easier to recognise than to define. No clear answer emerges from the authorities as to the meaning of the term.”
“So in questions in which the parties have entrusted the power of decision to a valuer or other decision-maker, the courts will not interfere either before or after the decision. This is because the courts' views about the right answer to the question are irrelevant. On the other hand, the court will intervene if the decision-maker has gone outside the limits of his decision-making authority. One must be careful about what is meant by “the decision-making authority”
“The first question, therefore, is what the agreement has entrusted to the expert. The second is whether that is what he has decided. If so, the third is whether it can be shown that he has made a mistake which vitiates his decision.”
“If a decision is issued in a dispute where it is binding ‘save for manifest error’ a party wishing to challenge the decision may face insuperable difficulties if the expert is not obliged to give reasons and fails to set out the reasons for his decision.”
“The Building Specification clearly states that the retail units will comply with Building Regulations and Menolly therefore assumes that suitable access provision will be made. The District Surveyor has confirmed that ramped access is required to meet with the Building Regulations. The current handover specification does not allow the unit to meet with the District Surveyor’s approval or the Building Regulations…… Menolly do not accept that the works completed are in accordance with the Purchase Agreement and any variation from the ER’s must be addressed by the Developer in order to comply with their duty to the purchaser.” c. Although Menolly now relies principally on the 1970 Act rather than the Building Regulations, the complaint is in essence the same. d. There have been without prejudice discussions, the details of which I have not of course been provided with, for settling that dispute by a financial adjustment leaving Menolly to sort out level access with its proposed tenants. e. Later in the year, we find Mr Kingdon of CBRE emailing Mr Ramsay on4 November 2008 as follows: “Please would you let me know the status of the sectional completion for the retail areas at the above property following review of our snagging list sent to you on1 October 2008 ……. We also still maintain that level access is required to comply with building regulations. This will probably need to be agreed between principles [sic] if you cannot impose this on ISG under the contract. Our stance on this is clear, the shopfronts were omitted but no other works were and therefore Menolly only intended to put in the shopfronts, however due to the levels this will not be enough to comply with Part M.” f. The thrust of that email is according to Mr McGhee clear: Menolly regard provision of level access as something which they are entitled to see delivered. It is not a recognition that the Employer has no right to impose this obligation on the Contractor but only a recognition that, if the Contractor opposes, matters will have to be dealt with between Cerep and Menolly. g. Then on12 December 2008 , Menolly’s solicitors wrote to Cerep’s solicitors. They attached a schedule of items which were regarded as “significant problems”
“Retail - CBRE is awaiting confirmation that all outstanding snagging is completed before we re-inspect for handover”
“Accordingly Menolly knew and/or assumed (as did all other relevant parties, who came to so know and assume on the basis of the stance adopted by Menolly) that Section 1 of the Works had been validly certified and all that remained was the certification of Section 2 of the Works.”
“I appreciate that the works should be snag free in a perfect world and any snagging by ISg after handover will be more difficult for ISg as this will require your permits. But it would help if you highlighted show stoppers preventing handover.”
“Retail – CBRE is awaiting confirmation that all outstanding snagging is completed before we re-inspect for handover”
“Practical Completion is due on 15th December for the main works which is delaying commencing work on site for the retail enabling works project. We have a draft programme from Vector Build which shows three months on site although we believe it will be possible to complete Unit E by early March to enable your fit out to commence.”]. Menolly accepting that level access are works for it to undertake post pc/handover, as part of Vector Build’s scope. 5.12.08 Mr Kingdon email re the inspection which took place on that date setting out main issues. No reference to level access. 10.12.08 CBRE prepare a generic snagging list in advance of impending pc. No reference to level access. 2.12.08 CBRE to Mr Ramsay attaching report relating to quality issues on site No comment to level access. 31.12.08 Mr Ingram Evans to others in CBRE re inspection on 5.1.09 “Menolly has reached an agreement with Carlyle and therefore the purchase will go ahead. Please can you keep Monday 5th free for a detailed inspection for acceptance. Bryan [Higgins] would like as many as our team available as possible as John Ramsay is likely to certify PC and we need to agree snags and argue whether the outstanding works list is acceptable for PC.”
“We really need to bottom out PC of the Building and Vector Build‟s programme ASAP. I am coming around to the view that we start the Retail Works unconditionally…Units E and F in the Vodafone/Boots configuration is not a layout I have a problem recommending even in the open market and whatever happens Menolly will HAVE to lower the slab to let the units”
“PC was not achieved Friday, but a further inspection is anticipated tomorrow/Wednesday. We are due to meet all consultants with a view to kicking-off the job, following which we should be in a position to issue you with a sensible timetable. Apologies for the delay, but we have been messed around considerably by the main contractor, ISg. We are almost there now.”