“The Contractor certifies a payment within three weeks of each assessment date. The first payment is the amount due. Other payments are the change in the amount due since the last payment certificate. A payment is made by the Subcontractor to the Contractor if the change reduces the amount due. Other payments are made by the Contractor to the Subcontractor. Payments are in the currency of this subcontract unless otherwise stated in this subcontract.”
“The date upon which each payment becomes due and the final date for payment of payments becoming due are as provided in Option Y(UK)2.”
“The date on which a payment becomes due is twenty-one days after the assessment date. The final date for payment is twenty-one days or a different period for payment if stated in the Subcontract Data after the date on which payment becomes due. The Contractor's certificate is the notice of payment to the Subcontractor specifying the amount due at the payment due date (the notified sum) and stating the basis on which the amount was calculated.”
“If either Party intends to pay less than the notified sum, he notifies the other Party not later than seven days (the prescribed period) before the final date for payment by stating the amount considered to be due and the basis on which that sum is calculated. A Party does not withhold payment of an amount due under this contract unless he has notified his intention to pay less than the notified sum as required by this subcontract.”
“Dear Sirs, Please find attached the Advance Assessment of the Enisca AFP 25 Application For Payment 25. . Due to the assessment resulting in a negative payment value (due to a previous on account overpayment), Advance have adjusted the figures below to show a Zero Payment to prevent any credit notes needing to be made. Advance Assessment of PWDD Price of Work Done to Date. :£2,097,662.60 Less 5% Retention: (£104,883.13 ) Cumulative Payment due:£1,992,779.47 Less Paid to date:£2,157,068.49 Payment Amount Due: (£164,288.02 )”
“Dear Sirs, Project No SCADV35615 Sub Contract Order No: SCADV35615-049 REF: WITHHOLDING/PAYLESS NOTICE We refer to your application number 17, relating to period ending26th March 2021 . Please be advised that, in accordance with the subcontract terms and conditions between us, we give notice of our assessment of your application number 17 as follows: i) Application paid in full ii) Your application has been amended in accordance with the attached detail; • Advance Assessment of PWDD:£2,097,662.60 • Less 5% Retention: -£104,883.13 • Payment due:£1,992,779.47 • Less Paid to date:£2,157,068.49 • Payment amount due in period: -£164,288.02 …” … iii) Cumulative Payment value excluding VAT and before retention is:£2,157,067.49 .”
“…to require an employer at periodic intervals to pay “the notified sum” by the final date for payment, irrespective of whether or not that sum in fact represents a correct valuation of the work to date. If an employer fails to give relevant notice, irrespective of whether this is by mistake, administrative oversight or any other reason, then a sum for which the contractor has applied becomes immediately contractually payable, even if it is wrong in valuation terms.”
“[47]The dispute or difference referred in the First Adjudication concerned the true valuation of the BHL’s entitlement in respect of Interim Application 22. The Notice of Adjudication expressly sought declarations and payment based on “the true value of BHL’s Application for Payment Number 22 dated16 July 2021 ”