“4.1.1 A declaration as to the correct valuation of each of the items in dispute that have been referred to the adjudicator in this adjudication .. 4.1.2 An order that [Hitachi] shall pay to Sisk the sum of£3,947,187.42 plus VAT or such other sum as the adjudicator may decide (plus VAT); …”
“Accordingly this decision does not rehearse each and every issue raised by the Parties but it does address the Dispute referred, namely whether the items are Variations or matters for deduction, whether a time bar or other agreement applies and what the proper valuation is and sum due for the purposes of Application 6.” ii) At [38]-[45] he considered the basis for valuation under Clause 30.1 and continued at [46]: “Both Sisk and [Hitachi] at times seek to rely on unsupported costs in their respective valuations. Absent common ground in the parties’ approach to valuation, I have applied contract rates and allowances where I am directed to them and am satisfied that they are sufficiently evidenced, alternatively Costs and Expense where sufficiently evidenced. If I have insufficient evidence to conclude a valuation I have had regard to any admissions made by either party and applied those to my valuation. In very many cases however the detail provided both in Application 6 and Payment Notice 6 falls short of that required by clause 30.1 and in such situations I have been unable to conclude a valuation for the purposes of Interim Application/Payment Notice 6. This is not to say that no value is due on a subsequent application, but rather, that none could be ascertained as due for this Application 6/Payment Notice 6.” iii) At [83], under the heading “Valuation” he wrote: “My valuation is set out in summary terms in Appendix 1 to this decision for the Variations that Sisk identify …. . The appendices are copies of the schedules provided in Referral Section E with additional columns added for my Valuation and comments.” iv) At [89] under the heading “Directions”, he wrote (as amended on18 April 2016 ): “I therefore Decide, Declare and Direct: (a) The correct valuation of each of the items in dispute that have been referred to me in this adjudication, being the items in the schedule at Appendix 4 to the Notice of Adjudication is as set out in Appendices 1 and 2 to this Decision, namely [£37,003.59 ] for Variations ….; (b) [Hitachi] shall pay to Sisk the sum of [£332,222.27 ] plus such VAT as is due at law; …” v) As indicated in the main text of the decision, Appendix 1 replicated Sisk’s claim as set out in its referral for Events, with the sum allowed by the adjudicator and what was described as the “Adjudicator’s Decision” in two columns at the right hand side of the Appendix. The sum allowed for Event 1176 was£0.00 . The Adjudicator’s decision first addressed whether Sisk was instructed to accelerate its works as claimed. The adjudicator concluded that it was and “that this is a variation that requires valuation.”
“Sisk provide some cost details but with limited exceptions they comprise unreferenced abstracts of daily and weekly resources or extracts from sub-contract accounts without the necessary context to satisfy the requirements of Clause 30.1. I do not have sufficient details to value the works and hence for the purposes of Payment Notice 6 my value is £nil.” vi) There were other Events (e.g. 1332, 1357, 1372) where the substance of the adjudicator’s decision was that Sisk had not satisfied the contractual requirements of proof under Clause 30.1 and therefore no sum would be or was awarded. The wording used by the adjudicator to express this conclusion was not the same in all cases, but in each case the substance of his decision was clear. In at least one case (Event 700) the adjudicator used a rather different formulation, saying that the event was “not before [him] but for the purposes of this Payment Notice 6 the value for Event 700 is nil.” ; vii) One other Event which has figured in submissions was Event 378, which was a claim for the costs of erecting safety barriers and retaining walls in the sum of£110,150.76 . The adjudicator’s decision was that these works constituted a variation under the contract but that “The cost details provided by Sisk do not comply with the requirements of Clause 30.1 and thus I cannot determine the correct valuation for Payment Notice 6”
“(a) decided liability for Event No. 378 – stating that “the additional Permanent car park was instructed on or about8 October 2012 ” and this was “a Variation”; and (b) did not decide quantum – stating that the “cost details provided by Sisk do not comply with the requirements of clause 30.1 and thus I cannot determine the correct valuation for Payment Notice.””
“Sisk requests that the Adjudicator should make the following declarations: 10.1.1 Declare that a Variation Order should have been issued by [Hitachi] in relation to the Instruction and the Event 1176 works as a result of [the binding decision in the second adjudication] that the Instruction was a variation to the Contract or that a Variation Order should other wise be issued as decided by the Adjudicator in respect of the Event 1176 Works;” 10.1.2 Order that [Hitachi] shall pay to Sisk the sum of£994 , 572.19 plus VAT, or such other sum as the Adjudicator shall determine plus VAT in respect of Sisk’s entitlement in relation to the Instruction within 7 days of the date of the Adjudicator’s Decision. …”
“… In the Second Adjudication I decided that Event 1176 was a Variation that required valuation. Thus I cannot adjudicate now on whether Event 1176 was or was not a Variation as that has been decided. In addition I decided that for the purposes of Application 6 that Sisk had not complied with the provisions of clause 30.1 and stated that “I do not have sufficient details to value the works and hence for the purposes of Payment Notice 6 my value is £nil.”
“249. My decision was that the Event 1176 Works I [sic] constituted a Variation that require a valuation, that is, I decided the liability issue as between the parties. 250. I cannot and do not reconsider that decision here, but I accept that in reaching a decision as to the valuation of the Event 1176 Works, such decision having not been made in the Second Adjudication, I do need to consider whether the requirements of the Contract have been met as regards that valuation.”
“Having decided in the Second Adjudication that Event 1176 is a Variation that requires valuation and decided here that the valuation is£825,703.17 plus interest, it follows that a Variation Order should be issued to that effect. In any event a Variation Order for the Event 1176 works should have been issued following my Second Adjudication given that I had there decided on liability and the basis of payment.”
“I therefore Decide, Declare and Direct (a) A variation Order should have been issued by [Hitachi] in relation to the Instruction and the Event 1176 Works as a result of my binding Decision that the Instruction was a variation to the Contract and in any event a Variation Order should be issued now in respect of the Event 1176 Works; (b) [Hitachi] shall pay to Sisk within 7 days of the date of this Decision the sum of£825,703.17 plus such VAT as is due at law in respect of Sisk’s entitlement in relation to the Instruction. (c) [Hitachi] shall pay to Sisk within 7 days of the date of this Decision£34,035.33 in relation to interest up to the date of the Referral and continuing until the date of this Decision at a daily rate of£192.29 …”
“Appendix C is a far cry from the two application letters dated2 September 2004 and22 April 2005 . It is perhaps regrettable that Appendix C was not advanced in the first adjudication. Appendix C identifies a number of causes of delay which do not feature in the two application letters. Further, Appendix C appears to be a structured and logical document, which sets out to demonstrate what the critical path was and how individual events did or did not impact upon the final date for completion. Whether, at the end of the day, the submissions in Appendix C will prevail, I do not know. This will be a matter for the adjudicator or, possibly, the arbitrator to decide. I am, however, quite satisfied that Vascroft’s alleged entitlement to an extension of time as set out in Appendix C is substantially different from the claims for extension of time which were advanced, considered and rejected in the first adjudication.”
“31. Section 108(3) of the 1996 Act and para 23 of the Scheme provide for the temporary binding finality of an adjudicator’s decision. More than one adjudication is permissible, provided a second adjudicator is not asked to decide again that which the first adjudicator has already decided. Indeed para 9(2) of the Scheme obliges an adjudicator to resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication and a decision has been taken in that adjudication. 32. So the question in each case is, what did the first adjudicator decide? The first source of the answer to that question will be the actual decision of the first adjudicator. In the present appeal, Mr Holt did not even take us to the first adjudicator’s decision, although he was invited more than once by the court to do so. He was conscious, no doubt, that it would show, as it does, that the decision was limited to the grounds for extension of time in the two letters. 33. The scope of an adjudicator’s decision will, of course, normally be defined by the scope of the dispute that was referred for adjudication. This is the plain expectation to be derived from section 108 of the 1996 Act and paras 9(2) and 23 of the Scheme. That is also the plain expectation of para 9(4) of the Scheme, which refers to a dispute which varies significantly from the dispute referred to the adjudicator in the referral notice and which for that reason he is not competent to decide. There may of course be some flexibility, in that the scope of a dispute referred for adjudication might by agreement be varied in the course of the adjudication.”
“47. Whether dispute A is substantially the same as dispute B is a question of fact and degree. If the contractor identifies the same Relevant Event in successive applications for extensions of time, but gives different particulars of its expected effects, the differences may or may not be sufficient to lead to the conclusion that the two disputes are not substantially the same. All the more so if the particulars of expected effects are the same, but the evidence by which the contractor seeks to prove them is different. 48. Where the only difference between disputes arising from the rejection of two successive applications for an extension of time is that the later application makes good shortcomings of the earlier application, an adjudicator will usually have little difficulty in deciding that the two disputes are substantially the same. 49. In the present case, I am in no doubt that the judge reached the right conclusion. The first disputed claim which was the subject of the first adjudication was different from the second disputed claim. The written notices which formed the basis of the second claim identified Relevant Events which were substantially more extensive than those which formed the basis of the first claim. The particulars of expected effects were very different too. There will be some borderline cases where it is a matter of judgment whether the two claims are substantially the same and where there may be room for more than one view. In my view this is not a borderline case.”
“57. It is quite clear from the authorities that one does not look at the dispute or disputes referred to the first adjudicator in isolation. One must also look at what the first adjudicator actually decided. Ultimately it is what the first adjudicator decided, which determines how much or how little remains available for consideration by the second adjudicator.”