“IT IS DECLARED THAT: “1. The accounting exercise provided for by clauses 8.7.4 and 8.7.5 of the Contract has not been agreed, established, ascertained or otherwise conducted by and/or as a result of the execution of the Acceptance Agreement dated19 April 2017 between Aviva and Swiss Cottage. “2. Save to the extent that it dealt with the costs of the adjudication, the decision of Rowan Planterose dated14 June 2019 was wrong and is no longer binding upon the Claimant or the Defendant. “3. The Claimant is entitled to launch a fresh adjudication to refer the dispute about the sums owing between the parties under the Contract to another adjudicator.”
“If the Contractor’s employment is terminated under clause 8.4, 8.5 or 8.6… “following the completion of the Works and the making good of defects in them (or of instructions otherwise, as referred to in clause 2.35), an account of the following shall within 3 months thereafter be set out in a statement prepared by the Employer: “.1 the amount of expenses properly incurred by the Employer, including those incurred pursuant to clause 8.7.1 and, where applicable, clause 8.5.3.3, and of any direct loss and/or damage caused to the Employer and for which the Contractor is liable, whether arising as a result of the termination or otherwise; “.2 the amount of payments made to the Contractor; and “.3 the total amount which would have been payable for the Works in accordance with this Contract.”
“if the sum of the amounts stated under clauses 8.7.4.1 and 8.7.4.2 exceeds the amount stated under clause 8.7.4.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor.”
“31. In my view the matter has been settled by the agreement under the Bond [i.e. the Acceptance Agreement]. That the settlement was at a lower sum than the full amount of the [Bond] is of no relevance. “32. [Hart] were signatories to the Bond. They agreed its terms. Those terms include the establishment of the account taking in ‘all sums due or to become due to [Hart].’ As the Bond also says: ‘the liability of [Aviva] shall be coextensive with the liability of [Hart] under the Contract’. The exercise under clause 8.7.4 [of the Contract] has been done. That seems to me to be an end to the matter. Essentially I accept the points made by [Swiss Cottage] in this respect in paragraph 2 of their Response in the June 2018 adjudication.”
“1. The Surety entered in a Conditional Bond number 24937477 CBO (“the Bond”) supporting the obligations of M L Hart Builders Limited (“The Contractor”) to the Employer in respect of a contract for 14 apartments and a commercial shell at 75 Page Street, London for the original contract sum of£3,325,000 . “2. The Employer has terminated the employment of the Contractor following the appointment of liquidators to that company. The Employer has completed the contract works and claims that its damages sustained as per condition 1 of the bond are in excess of the Bond Amount of£332,500 and calls upon the Surety to comply with its obligations under condition 1 of the Bond (“the Bond Call”). “3. The Parties have agreed terms for the full and final settlement of the Bond Call and wish to record those terms of settlement on a binding basis in this Acceptance Agreement. Agreement: “4. The Employer hereby agrees to accept the sum of£235,000 (two hundred and thirty five thousand pounds) (“the Settlement Sum”) in full and final settlement of the Bond Call and all and any other actions, claims, rights, demands and setoffs in whatever jurisdiction (whether or not presently known to the Parties or to the law, and whether in law or equity) that the Employer ever had, may have or hereafter can, shall have against the Surety arising out of or in connection with the Bond. “5. The Settlement sum is fully inclusive of any and all legal costs interest and the like incurred or to be incurred by the Employer. “6. In consideration of and conditional upon payment of the full Settlement Sum, the Employer releases and forever discharges all and any actions, claims, rights, demands and set-offs in whatever jurisdiction (whether or not presently known to the Parties or to the law, and whether in law or equity) that the Employer may have or hereafter can, shall or may have against the Surety arising out of or in connection with the Bond and the Bond Call.” …. “10. Each party warrants and represents to the other with respect to itself that it has the full right, power and authority to execute, deliver and perform this Agreement.”
“A bond of this sort is an instrument of secondary liability. The surety cannot be in a worse position, as against the employer, than the contractor. In Tower Housing Association Limited v Technical and General Guarantee Co. Limited(1998) 87 BLR 74 , Judge Humphrey Lloyd QC said: “As the claim is made on the bond, certain basic principles have to be born in mind in approaching a bond of this kind. First of all, it is well established and it must, I assume, be taken as common ground that a bondsman in the position of the defendant is entitled to avail itself of all the defences that might have been available to the contractor had the contractor either not been insolvent and obviously, where it is either insolvent or in financial difficulties, the defences available to the administrative receivers. Secondly – and this was prayed in aid by Mr. Darling in the course of his submissions – that, in general terms, one would approach the terms of the bond on the basis that they are to be ‘strictly construed and no liability is imposed which is not clearly and distinctly covered by the terms of the agreement’…” “As the claim is made on the bond, certain basic principles have to be born in mind in approaching a bond of this kind. First of all, it is well established and it must, I assume, be taken as common ground that a bondsman in the position of the defendant is entitled to avail itself of all the defences that might have been available to the contractor had the contractor either not been insolvent and obviously, where it is either insolvent or in financial difficulties, the defences available to the administrative receivers. Secondly – and this was prayed in aid by Mr. Darling in the course of his submissions – that, in general terms, one would approach the terms of the bond on the basis that they are to be ‘strictly construed and no liability is imposed which is not clearly and distinctly covered by the terms of the agreement’…”
“28. The importance of the contractual ascertainment exercise was restated in Paddington Churches Housing Association v Technical and General Guarantee Co Limited[1999] BLR 244 . Again, that was a claim on a bond in the absence of any ascertainment of the debt due under clause 27. Judge Bowsher QC reiterated both the secondary liability that arose under the bond and the importance of the contractual mechanism. At paragraph 24 he said: “The defendants are liable as surety only, and it seems to me to be plain on the face of the bond that the defendants are liable to pay the amount (if any) shown to be due to the plaintiffs on a statement made by the employer in accordance with the terms of the contract. That contract was imported into the bond by the recitals. Clause 27 of that contract is referred to specifically in the conditions. Both in case of default and in case of determination on insolvency (or indeed in any case where it were relevant, for corruption) the damages are calculated by reference to the code of the contract, which are in any event unlikely to be different from the damages at general common law. The accuracy of the employer’s statement might be challenged in the courts, but the employer’s statement is required before the damages can be said to be ascertained and there is no liability on the defendants until those damages are ascertained. The plaintiffs submit that the employer’s statement is only a mechanism and not a condition precedent to payment, but no other mechanism for ascertaining the net damages is put forward or relied on by the plaintiffs.” “29. The judge said that the absence of the statement was fatal to the employer’s claim. At paragraph 30 he said that, “When such a statement is provided, if it shows a net sum due to the plaintiffs, the defendants will become liable up to the amount of the bond.” “The defendants are liable as surety only, and it seems to me to be plain on the face of the bond that the defendants are liable to pay the amount (if any) shown to be due to the plaintiffs on a statement made by the employer in accordance with the terms of the contract. That contract was imported into the bond by the recitals. Clause 27 of that contract is referred to specifically in the conditions. Both in case of default and in case of determination on insolvency (or indeed in any case where it were relevant, for corruption) the damages are calculated by reference to the code of the contract, which are in any event unlikely to be different from the damages at general common law. The accuracy of the employer’s statement might be challenged in the courts, but the employer’s statement is required before the damages can be said to be ascertained and there is no liability on the defendants until those damages are ascertained. The plaintiffs submit that the employer’s statement is only a mechanism and not a condition precedent to payment, but no other mechanism for ascertaining the net damages is put forward or relied on by the plaintiffs.”
“Paragraph 2 of the Bond refers to damages “payable under this Guarantee Bond…following the insolvency…of the contractor.”
“55. The original debate under the umbrella of Declaration 2 ranged far and wide. At one point, the defendant was suggesting that the claimant needed either to get a judgment against County, or at least get County’s agreement that they were liable for the debt, before any claim could be made under the Bond. That is wholly incorrect: the decisions in Tower Housing and Paddington Churches make plain that what is required to trigger a claim under the Bond is the completion of the ascertainment exercise under clause 8.7. Once that has happened, a claim can be made under the Bond. “56. Once the process under clause 8.7 of the building contract is concluded, it is not only quite unnecessary for the claimant to pursue County before making a claim against the defendant, but it is also unnecessary for the claimant to have any further communication of any kind with County. The claimant can look to the defendant for payment. “57. Any other result would destroy the commercial value and purpose of the Bond. The Bond is required to provide the claimant with the ability to recover at least some of its losses against a solvent party. It would circumvent that commercial purpose if the claimant was then required to issue separate proceedings against that insolvent party (and get the necessary permission to do so) and/or to reach an agreement with the insolvent party, in order to establish either liability or quantum under the Bond.”
“He was not a party to the action, but an estoppel will bind those who are privy to the parties bound: Carl Zeiss Stiftung v Rayner & Keeler (No.2) [1967] 1 A.C. 853. The requisite privity is said to be privity of either blood, title or interest: per Lord Reid in the Carl Zeiss case, at p. 910. The only relevant one is privity of interest. It is not easy to detect from the authorities what amounts to a sufficient interest. It has been held that judgment against a defendant in one capacity does not bind him in another capacity (Marginson v Blackburn Borough Council [1939] 2 K.B. 426), though I would wish to reserve my opinion as to whether on the facts of that case the plaintiff’s representative claim might not have been struck out as an abuse of process. A mere interest in the outcome of the litigation is not sufficient. In Gleeson v J. Whippell & co. Ltd. [1977] 1 W.L.R. 510, 515, Sir Robert Megarry V.-C. propounded this test: “but it does seem to me that, having due regard to the subject matter of the dispute, there must be a sufficient degree of identification between the two to make it just to hold that the decision to which one was party should be binding in proceedings to which the other is party. It is in that sense that I would regard the phrase ‘privity of interest.’” “He continued, at p. 516: “A defendant ought to be able to put his own defence in his own way, and to call his own evidence. He ought not to be concluded by the failure of the defence and evidence adduced by another defendant in other proceedings unless his standing in those other proceedings justifies the conclusion that a decision against the defendant in them ought fairly and truly to be said to be in substance a decision against him. Even if one leaves on one side collusive proceedings and friendly defendants, it would be wrong to enable a plaintiff to select the frailest of a number of possible defendants, and then to use the victory against him not merely in terrorem of other and more stalwart possible defendants, but as a decisive weapon against them”.” “but it does seem to me that, having due regard to the subject matter of the dispute, there must be a sufficient degree of identification between the two to make it just to hold that the decision to which one was party should be binding in proceedings to which the other is party. It is in that sense that I would regard the phrase ‘privity of interest.’”
“(d) Estoppel of the various different types can of course, on the facts of any given case, come into play in the field of guarantees or indemnities. “(e) Where what is being guaranteed or indemnified against includes claims, proceedings or judgements against the beneficiary, the giving of notice to the guarantor or indemnifier may form at least one basis for or strand of a case in estoppel. The active participation of the guarantor or indemnifier in the proceedings, may, depending on the circumstances, level and scope of the participation, go much further to establish an estoppel against it. The positive concurrence by the guarantor or indemnifier with a consent judgement against the beneficiary will go further still. “(f) Given the wide range of factual permutations which may arise in any particular case, it is inappropriate for this court to lay down any specific requirements needed to establish an estoppel in these types of circumstances. Whilst the giving of notice to, the active participation by and the giving of approval to a consent judgement by the guarantor or indemnifier may in many cases give rise to an estoppel against it so as to prevent it from denying an obligation to indemnify against or pay out for the amount of the consent judgement, it would be wrong to be absolutely prescriptive. It is necessary to look at all the relevant evidence and circumstances before deciding whether there is or is not an estoppel.”
“4.66 …. If the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that earlier adjudication, then paragraph 9(2) is unequivocal: in such circumstances, the adjudicator must resign. Doubtless as a result of this finality, there have been a large number of reported cases in which the responding party has sought a declaration or a finding that the adjudicator should have resigned and that, in consequence, he had no jurisdiction to give the decision that he did … “4.67 Perhaps unsurprisingly, the majority of the reported cases dealing with what might be called attempted readjudication demonstrate a general desire to find that the disputes in question were not the same or substantially the same ….” …. “7.150 It is instructive to note that, just as with the cases in which the argument has been advanced that the adjudicator dealt with more than one dispute and therefore did not have the appropriate jurisdiction, the submission that the adjudicator was dealing with a matter previously decided by another adjudicator, although regularly made, has also been largely unsuccessful….”
“57. It is quite clear from the authorities that one does not look at the dispute or disputes referred to the first adjudicator in isolation. One must also look at what the first adjudicator actually decided. Ultimately, it is what the first adjudicator decided, which determines how much or how little remains available for consideration by the second adjudicator. “58. In my view Mr Sears’ argument is correct. The word “decision” in paragraph 9(2) means a decision in relation to the dispute now being referred to adjudication. I arrive at this interpretation as a matter of construction rather than implication. It is what the paragraph obviously means. Parliament cannot have intended that if a claimant refers twenty disputes or issues to adjudication but the adjudicator only decides one of those disputes or issues, further adjudication about the other matters is prohibited.”
“39. Hitachi submits that, in deciding the sum to which he considered Sisk to be entitled to payment in respect of Event 1176 and directing payment of that sum the adjudicator in the eighth adjudication decided the same claim that he had considered and decided in the second adjudication (in the sum of £nil). “40. I disagree. The referred dispute in the eighth adjudication was the valuation of Event 1176. That was precisely what the adjudicator declined to decide in the second adjudication, for want of substantiating evidence at that time. The dispute referred to in the eighth adjudication was therefore not the same as the dispute in the second adjudication. “41. In my judgment the dispute referred to in the eighth adjudication was also not “substantially the same” as the dispute decided in the second. It is important to bear in mind that the comparison to be made is between what was referred in the eighth adjudication and what was decided in the second. Once it is recognised that there was no valuation decision at all in the second adjudication, it become clear that, in the matter of the value to be attributed to and recovered for Event 1176, there is no overlap at all ….”