“By your submission dated28th April 2003 it appears that you hold [the Sub-Contractor] solely responsible for their extended time onsite… We must therefore state that due to the contents of your letter in your submission of28th April 2003 , and your ‘threats’ therein, we can only conclude that a dispute has existed since receipt of this letter and document. As it is apparent that we are unable to resolve this dispute amicably, we feel compelled to instigate adjudication proceedings in an effort to settle this account without further delay. By this referral notice, we have requested the Chartered Institute of Arbitrators… to appoint an adjudicator to carry out the following:- 1) Ascertain the value of [the Sub-Contractor’s] submission dated 31st of January 2003… 2) Ascertain the value of the interest on outstanding sums in accordance with the statutory entitlement. 3) Ascertain the date of completion of [the Sub-Contractor’s] works. 4) Instruct [Carillion] to award an extension of time for the extended contract period from27th October 2000 to6th May 2001 inclusive, or such other time as the adjudicator may ascertain. 5) Ascertain whether the submission of [Carillion] dated 28th 2003 and the contents therein constitute a valid notice of set off in accordance with the contract and ascertain the validity of the contents of the document submitted by [Carillion] dated28th April 2003 . 6) Instruct [Carillion] to pay all monies due to [the Sub-Contractor] within 28 days of his award…”
“In accordance with the requirements of the Contract Conditions this submission, documents, [sic] details and quantifies the entitlement of [the Company] in regards to an Extension of Time and associated Prolongation and Disruption costs (loss and expense). This document confirms: 1) The total reliance that [the Company] had upon the timely provision of access/egress to the site in order to COMMENCE their works. 2) The total reliance that [the Company] had upon the timely provision of Trenches in order to PROGRESS their works. 3) The total reliance that [the Company] had upon the timely receipt of complete, accurate and finalised design information in order to COMPLETE their works. And then, in breach of such FUNDAMENTAL REQUIREMENTS: 1) The late completion of [Carillion’s] other preceding (trenching) contractors, which effectively restricted [the Company’s] areas of work. 2) The delay in the provision of the trenches thereby restricting/preventing [the Company’s] ability to effectively and economically progress the works. 3) The failure of the M&E Engineer to issue such critical design information in a timely and co-ordinated manner to suit [the Company’s] Construction Programme (i.e. changes in design of the gas and water mains). This document describes, despite their very best endeavour’s [sic], the total and unavoidable detrimental EFFECT of the aforementioned factors upon [the Company’s] ability to commence, progress and complete their works in a TIMELY, LOGICAL, CONTINUOUS and ECONOMIC manner. Such detrimental conditions imposed upon [the Company] THROUGHOUT the currency of works are described and evidenced within this submission by reference to correspondence, as-built programme information, Minutes of Meetings, Site Reports, Requests for Information, Site Letters and Site Instructions issued and revised drawings issued in connection with the work. The cumulative detrimental effect of such disruptive impositions has been to delay the critical progress of [the Company’s] work by a total of 26 WEEKS (on an original Contract Period of 24 weeks) for which an Extension of Time is required in accordance with the Conditions of Contract including, most notably, clause 6. Despite their very best endeavours to mitigate, the following costs have been unavoidably incurred by [the Company] as a direct effect of such adverse circumstances:£380,589.53 …for which reimbursement is required by [the Company] in accordance with the subcontract Conditions, most notably, clause 8, 9 and 10. Note: …the disruption calculation incorporated as part of this claim assumes a particular level of certification (and therefore number of man hours recovered) in respect of the Final Account. This certification has been agreed through an Adjudication and the adjudicator’s decision dated2nd August 2002 …”
“Section 3.0 together with [the Company’s] contract log sheets included within Annexure F of this submission confirm and document the EXCEPTIONALLY ADVERSE CONDITIONS imposed upon [the Company] throughout the course of their works. Moreover, this detrimental climate was greatly exacerbated by the nature of the site. As conveyed within Section 3, herein the site was within a working hospital and bounded by roads/existing buildings. Thus, there were considerable access, storage, laydown restrictions - combined with the restriction of a relatively congested site and limited available work fronts. Hence the importance of effective planning and continuity for the construction of [the Company’s] work was of paramount importance. Once this plan was deviated from future the aforementioned imposed adverse conditions and their sudden adverse effects (site restriction, work on hold, late information, piecemeal and incomplete information), then [the Company’s] ability to continue the works in a continuous and economic manner became severely disrupted; This unacceptable situation is further confirmed by the as-built programme… which shows how all programme activities were literally stretched over a much longer period while [the Company] were literally forced to wait on site for the late completion of preceding trades (i.e. trench excavation, sand base infill, etc). The elongation of activities has been summarised by the following table which confirms the percentage increase in durations over which [the Company’s] activities were forced to be spread…”
“43. …It seems to me that [the Company] have not been able to distinguish the amount of losses (if any) allegedly incurred in each of the variations which could be attributed to the loss and/or expense rather than the items already recovered in the final account… 48. It is my view that the claim in respect of the loss and/or expense by [the Company] lacks particularisation. The assertions made by [the Company] are mostly on a general basis without proving the causal links which may persuade me that on the balance of probabilities loss and/or expense were incurred by [the Company] and that the loss and/or expense were as a direct result of breaches of Contract by [Carillion]… 50. Based on the submissions made and on the balance of probabilities, it seems likely that due to additional works and variations, regular progress of the Works had been delayed and disrupted. This in itself does not however prove that any direct loss and/or expense were incurred by [the Company] as a result. 51. Furthermore I am not convinced that the alleged loss and/or expense was not recovered through the variation mechanism in the first adjudication which dealt with … all the variations. [The Company] have not adduced persuasive evidence to establish that not all of the contents of the contract log documents were the subject of the adjudicator’s decision in 2002. 52. The burden of proof rests with [the Company] to establish that specific items of variations were in fact losses and/or expenses which were suffered by [the Company]. In my view [the Company] have not been able to establish which actual items of the variations were not allegedly recovered through the final account in the first adjudication. Having investigated the documentation, it appears that at the time of the previous adjudication no evidence existed to suggest that such an extensive amount of variations were outstanding in respect of the alleged loss and/or expense. Considering the extent of the claim, it is reasonable to have expected that some contemporaneous evidence should exist to indicate that the time of the currency of the Contract, loss and/or expense had been incurred by [the Company]… 54. The costs of the claim submitted by [the Company] are generally based on supposition… 58. Based on the evidence submitted by the parties, I am not persuaded that [the Company] suffered a downturn in turnover due to the delay in this particular project. I have no objection to using the formula method; however, I believe that in any event evidence of actual loss and expense is fundamental to its admissibility and proof of the case. 59. I am not convinced that as a matter of fact [the Company] suffered loss and somehow lost the opportunity the bidding for other specific project(s) or turned away other work(s) as a consequence of delay and of having resources tied up on the project in dispute. The evidence submitted by [the Company] is inconclusive. The claim must therefore fail. 60. In my opinion [the Company’s] claim is not apportioned to the matters of the instructions and variations. It appears that elements are included in [the Company’s] claim which clearly cannot be the responsibility of [Carillion], or in respect of which [the Company] have failed to comply with the Contract, since the claim is global in nature, it is impossible to sever the good from the bad. 61. For the reasons described above I therefore find that [the Company] are not entitled to any monies in respect of the alleged loss and/or expense purportedly arising from the variations. I dismiss the claim.”
“(a) [the Company] are not entitled to any monies in respect of their loss and/or expense claim. (b) [Carillion] shall grant an extension of time to [the Company] for the period of27 October 2000 to5 May 2001 the date [the Company] completed the Works…”
“20. Based upon receipt of this new information UPS has reviewed its submissions and also the records and based upon this new information has been able to formulate its submission identifying causal effect due to the issues of delay and disruption to the work of UPS. 21. As was also noted in both the first and second Adjudications, both parties were in agreement that the mechanism of the recovery of any loss and or expense is through clauses 8 and 9 of the subcontract. Clause 8 deals with variations and what constitutes a variation and also clause 9 which deals with the valuation of the variation. 22. It is also common ground that it is for [Carillion] to properly value the variation…In this instance, all information to allow [Carillion] to value the works of this variation (the loss and expense variation) was within the possession of [Carillion] in 2001. Therefore the reason for this third Adjudication is the failure of [Carillion] to properly value this variation. 23. Due to this failing on the part of [Carillion], UPS have been forced to carry out this evaluation of the variation on behalf of [Carillion]. The evaluation of this variation (and substantiation and backup) is included in the files attached to the Referral Notice.”
“Analysis of Labour & plant delay and disruption costs Labour 108,076.51 Plant 129,481.67 Prolongation Costs Staff/Supervision 57,446.93 Site Facilities 5,747.18 Time Related Plant Consumables 1,357.00 Associated Costs Costs to the investigation and submission of the claim on behalf of [Carillion] 320,896.00 Finance Charges 18,921.34”
“30. The contents of the latest submission are substantially different from the information provided in the second Adjudication. It is therefore the contention of UPS that this information (due to being given late in the proceedings of the second Adjudication) could not have been used in the formulation of the UPS documents in either of the first or second Adjudication, and therefore is the basis upon which a new, substantiated submission has been produced… 32. It is common ground that, in general terms, a point cannot be taken to Adjudication more than once. However, UPS consider that they are able to bring this third Adjudication as the information contained within this latest submission has never been Adjudicated [sic] upon before…[there then follows reference to the Quietfield case]”
“3.10.1 The programme…issued by [Carillion], on11th May 2000 identified that the Underground Pipeline Services works in this area were to commence on 26th [was 22nd] May 2000 and be completed by20th June 2000 , with the works to be carried out in two operations. 3.10.2 However, on site, the works could not be carried out in this way. Works in this area actually commenced on 18th May [was 20the June] 2000 some 8 days earlier than anticipated. Completion of this area and all disruption associated with this area, should have been achieved on20th June 2000 . Actual completion was achieved on 26th [was 15th] March 2001, a total of 268 [was 268] days later than originally programmed. The works themselves were carried out in 21 [was 12] visits and works were carried out in this area in a total of 33 [was 20] days. The contract works were only able to be carried out on two or more consecutive days on four [was 2] occasions, variations instructed in this area also delayed and disrupted the works and last, variations were carried out on 9 [was 10] days, again having a disruptive effect on the works of Underground Pipeline Services. 3.10.3 The reasons for the work being carried out on a piecemeal basis was mainly due to the lack of trench excavation having been carried out by the groundwork sub-contractor of the main contract, McAlpine.”
“The following Section 4.0 sets out the costs claimed as being due directly to the Variation (the "Loss and Expense" Variation) which identifies the costs incurred by UPS for the prolongation, disruption and associated costs incurred by Underground Pipeline Services as a direct result of the variation, or in the alternative due to the breaches of contract of [Carillion]. The Second Adjudication Claim stated: “The following Section 4.0 confirmed the loss and expense (prolongation, disruption and associated costs) incurred by UPS as a direct result of such unacceptable conditions imposed by [Carillion].”
“Ref Subject Total 4.4 Analysis of Labour and Plant Delay 4.4.1 Labour 108,076.51 4.4.2 Plant 129,481.67 4.5 Prolongation Costs 4.6 Staff/Supervision 57,446.93 4.7 Site Facilities 5,747.18 4.8 Time Related Plant Consumables 1,357.00 4.9 Delay Costs 4.9.1 Delay Mitigation Included in Disruption Costs Sub-Total 302,109.29 4.11 Associated Costs 4.12 Costs for the Investigation and Submission of the Claim 320,896.00 4.13 Finance Charges on Additional Costs 18,921.34 Sub-Total 641,926.63 VAT (641,926.63 - 18,921.34) =£623,005.29 @ 20% 124,601.06 Sub-Total 766,527.69 Interest accruing on£302,109.29 from22nd March 2002 4.4.1 Labour 108,076.51 4.4.2 Plant 129,481.67 4.6 Staff/Supervision 57,446.93 4.7 Site Facilities 5,747.18 4.8 Time Related Plant Consumables 1,357.00 4.9.1 Delay Mitigation Included in Disruption Costs Sub-Total 302,109.29 4.12 Costs for the Investigation and Submission of the Claim 320,896.00 4.13 Finance Charges on Additional Costs 18,921.34 Sub-Total 641,926.63 VAT (641,926.63 - 18,921.34) =£623,005.29 @ 20% 124,601.06 Sub-Total 766,527.69 to9th May 2011 @ 12% pa 331,343.54 TOTAL AMOUNT DUE (AS AT9TH MAY 2011 )£1,097,871.23 ”
“31. Section 108(3) of the 1996 Act and paragraph 23 of the Scheme provide for the temporary binding finality of an adjudicator's decision. More than one adjudication is permissible, provided a second adjudicator is not asked to decide again that which the first adjudicator has already decided. Indeed paragraph 9(2) of the Scheme obliges an adjudicator to resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication and a decision has been taken in that adjudication. 32. So the question in each case is, what did the first adjudicator decide? The first source of the answer to that question will be the actual decision of the first adjudicator. In the present appeal, Mr Holt did not even take us to the first adjudicator's decision, although he was invited more than once by the court to do so. He was conscious, no doubt, that it would show, as it does, that the decision was limited to the grounds for extension of time in the two letters. 33. The scope of an adjudicator's decision will, of course, normally be defined by the scope of the dispute that was referred for adjudication. This is the plain expectation to be derived from section 108 of the 1996 Act and paragraphs 9(2) and 23 of the Scheme. That is also the plain expectation of paragraph 9(4) of the Scheme, which refers to a dispute which varies significantly from the dispute referred to the adjudicator in the referral notice and which for that reason he is not competent to decide. There may of course be some flexibility, in that the scope of a dispute referred for adjudication might by agreement be varied in the course of the adjudication.”
“(a) The parties are bound by the decision of an adjudicator on a dispute or difference until it is finally determined by court or arbitration proceedings or by an agreement made subsequently by the parties. (b) The parties cannot seek a further decision by an adjudicator on a dispute or difference if that dispute or difference has already been the subject of a decision by an adjudicator. (c) The extent to which a decision or a dispute is binding will depend on an analysis of the terms, scope and extent of the dispute or difference referred to adjudication and the terms, scope and extent of the decision made by the adjudicator. In order to do this the approach has to be to ask whether the dispute or difference is the same or substantially the same as the relevant dispute or difference and whether the adjudicator has decided a dispute or difference which is the same or fundamentally the same as the relevant dispute or difference. (e) The approach must involve not only the same but also substantially the same dispute or difference. This is because disputes or differences encompass a wide range of factual and legal issues. If there had to be complete identity of factual and legal issues then the ability to readjudicate what was in substance the same dispute or difference would deprive clause 39A.7.1 of its intended purpose. (f) Whether one dispute is substantially the same as another dispute is a question of fact and degree.”