"No issue decided by the Adjudicator may subsequently be referred for decision by another adjudicator unless so agreed by the parties."
"3.6 The defects arise out of selection of the defective goods, specifically the selection and installation of door sets which failed to meet the relevant standard. "3.7 Breyer deny responsibility for the defects. "3.9 Breyer have failed to discharge their obligations under the contract when selecting flat entrance door sets."
"4. Breyer shall pay to Lewisham homes the sum of£3.75 million or such other sum as the Adjudicator may decide by way of payment on account for the cost of replacing the door sets manufactured by Manse."
"5.1.6 If the Adjudicator did not decide remedies 2 or 4 there should be a declaration he has declined to decide those remedies by reason of lack of evidence."
"Is Breyer liable to pay to Lewisham Homes a sum on account for the cost of replacing the door sets by Manse and if so by how much?"
"56 In relation to its entitlement to an on account payment, as Rule 25.1 of the CPR empowers a court to grant an order for an interim payment by the defendant in respect of damages which the court may hold a defendant liable to pay, so can an adjudicator."
"57. I agree with Lewisham. The 12-month defects periods commenced at the date of the completion of a task order. I do not accept that defects which are identified as potentially present were the ones which conferred an obligation on Breyer to attend and rectify at no cost."
"58 While I note Lewisham's reference to the CPR, I agree with Breyer that it has no application to adjudication. I therefore find the references toCPR 25 of limited assistance. As there are no express provisions within the contract for Lewisham to recover an interim or on account payment, I also agree with Breyer that Lewisham is limited to a claim for damages as a result of losses caused by Breyer's failure to comply with its obligation to supply and install satisfactory door sets. In that regard, although I accept that in principle an award of damages may be made notwithstanding the costs of implementing a remedial work scheme have not yet been incurred, I have some difficulty in accepting this would be an appropriate course of action in circumstances where a contractor who is still engaged on site on a term maintenance partnering contract and was willing to undertake a remedial work scheme. However, I accept that the question of mitigation, and whether it would be unreasonable for Lewisham to appoint another contractor, is a relevant consideration in this regard."
"The final point which I consider militates against a finding that it would be reasonable for Lewisham to engage another contractor is the fact that the term of the contract had not yet expired such that Breyer is still on site. I therefore see some merit in Breyer's submissions that to engage an alternative contractor on site at the same time is never a good idea. This is especially so in circumstances where Breyer has expressed a willingness to undertake a remedial scheme in the event that it is found liable. Conclusion Absent an express provision entitling Lewisham to an on account payment in circumstances where costs of remedial works have been incurred, Lewisham's entitled is based on its common law right to recovery of damages. While I accept a party may recover damages in advance of the costs being incurred, notwithstanding a finding about the commencement of the defects liability period, my view is that it would not be appropriate to make an award of damages on an on account basis in circumstances where the contract term has not yet expired with Breyer still engaged on site and willing to undertake a remedial scheme. Accordingly I find that Breyer is not liable to pay Lewisham the sum on account."
"3.5. Subsequent to the first decision Lewisham have requested Breyer undertake a comprehensive door replacement programme to replace the door sets with conforming product. 3.6. Breyer have refused to delivery an appropriate remedial scheme that can be supported by Lewisham and its fire expert. Lewisham has no option but to engage alternative contractors to remedy the defects."
"Breyer Remedial Scheme offers a solution which Lewisham Homes is wrong to reject. The Adjudicator is asked to prefer the opinions and conclusions of Mr Quayle..." -- who I take to be their expert -- "... in support of this submission."
"(4) The Adjudicator is further invited to decide that the sum due to Lewisham is nil as there is no evidence put forward by Lewisham that any costs have in fact been incurred. In the alternative the Adjudicator is invited to decide the maximum sum due to Lewisham is the cost of the Breyer Remedial Scheme,£403,000 odd."
"I am satisfied I have not already made a decision in respect of the dispute referred to in this adjudication. The dispute referred to in the previous adjudication encompassed the question of liability and Lewisham's claim for an interim payment on account. I decided that Breyer was liable for non-performance, but that Breyer was entitled to rectify at no cost. The dispute in this adjudication concerns the claim by Lewisham arising from an alleged failure on the part of Breyer to implement and accept the Remedial Work Scheme. Although Breyer explains it is willing to perform a remedial scheme, the scheme proposed is not acceptable according to Lewisham. The sufficiency or otherwise of the remedial scheme and non-acceptance of it are substantive issues. I do not accept objections 1, 2 and 3..."
"34. In answering both these questions there is ample scope for misleading paraphrase and tendentious interpretation. In my judgment, the answer to both questions is to be found in the precise terms of adjudication referrals decisions themselves."
" 'Therefore the normal rule is that judgment sums should be paid within 14 days unless the judge otherwise orders. The judge has an absolute discretion. ... if a party wishes to persuade the court that a period greater than 14 days should be allowed for payment, it is necessary that that application is supported by proper evidence. ... It is unlikely that mere inability to pay will suffice to justify the extension of the normal fourteen-day period; usually, inability to pay is no defence and an insolvent debtor must take the usual consequences of its insolvency."
"20. Short extensions of a week or so for the payment of incidental sums awarded by the court ... are not uncommonly made..." -- but in his experience, apart from stay applications-- these sorts of applications for extensions are virtually unheard of. "