“(1) Where the Act applies, every party shall have a right to refer a dispute to adjudication at any time; (2) Either party may give notice to the other at any time of its intention to refer a dispute to an adjudication. Such notice shall be in writing and clearly headed ‘Notice of adjudication’ and include details of the subcontract, the issues which the adjudicator is being asked to decide, details of the nature and extent of the redress sought, and the grounds on which it is sought; (3) Within seven days of a party giving a notice of adjudication, an adjudicator shall be appointed and dispute referred to the adjudicator for determination.”
“The decision of the adjudicator shall be binding until the dispute if finally determined by legal proceedings in the Northern Ireland court by arbitration or by agreement.”
“Any notices that are given under clause 13 or 28 shall either be delivered personally or by recorded delivery post. Any such notice shall be deemed to have been served, if personally delivered, at the time of delivery or posted at the expiry of 48 hours after posting.”
“M&M may deduct, retain, or set off damages, costs, charges, et cetera due from or payable by the subcontractor, Flexidig, arising out of the subcontractor.”
“The subcontract is subject to the laws of Northern Ireland and the parties agree to submit to the jurisdiction of the Northern Irish courts.”
“We consider the amount due against this application is zero. The notified sum has been calculated on the basis that M&M dispute Flexidig’s submitted measurements used to calculate the application. Furthermore, the works completed by Flexidig have been inspected. The cost of making good the defects has been valued at£1,504,598 and this figure has been submitted to your office previously. Once you have made good the defects and the works signed off by my client, we will evaluate the final account for the project. Please confirm receipt of this formal contract notification.”
“Flexidig has provided all necessary information in support of its referral to allow a merits-based value of the AFP. Accordingly, characterisation of this reference is purely a “smash and grab” is plain wrong. If the adjudicator decides the pay less is valid, there is jurisdiction to make a merits-based assessment of the AFP and order the payment of that assessed sum. M&M has made no attempt to address the value of the AFP at all.”
“We would also like reasons for your decision. We should, however, bring the attached correspondence to your attention. As set out in M&M’s earlier correspondence, M&M maintains there are£1,504,598.49 in defects but provides no evidence. The purported withholding pay less notice seeks£673,374.18 but provides absolutely no breakdown. The attached letter demanding money from Flexidig claims£247,675.56 with no breakdown. It appears that M&M is plucking figures out of thin air to try and shore up its cashflow position rather than have any genuine counterclaim to make that has any proper substantiation, precisely the wrong identified in a document written by Sir Michael Latham which was the genesis of the Act.”
“Our client is currently undergoing the process of remedying the defects and, to date, has spent£247,000 . Clause 6 of the Contract allows M&M to deduct any costs or expenses as a result of making good any subcontract works. The purpose of the letter was to advise of our client’s intention to recover those sums and put you on notice that unless it is fully paid by return, we have instructions to issue legal proceedings.”
“We acknowledge your email. Without.. any disrespect to your directions, we sent an email to you to a data room holding the information you request…. We should make you aware of the surrounding legal context. The alleged defects were generated in September 2018 and were the subject of the adjudicator’s decision… He came to a markedly different conclusion. [, that is because he had awarded£462,000 -odd.] In any event, we attach a sealed order from Mr Justice Horner, the court determining that apart from£12,679.52 , Mr Horner’s decision was unenforceable. Flexidig has attended to defect rectification for the past 15 months. This was made difficult because M&M’s principal contractor withdrew the site set up and stopped applying for permit, thereby preventing Flexidig doing any defect rectification work. Between February and May this year, Flexidig did manage to do some works which significantly reduced the number of defects. It had to take over the principal contractor role. From June onwards, M&M refused to apply for any further permit to allow Flexidig to perform any further defect rectification works and, instead, in breach of contract employed others to undertake those works.”
“The proposition now advanced by Flexidig at this late stage is that the sum for defective works, which is the subject matter of a valid pay less notice, has been be artificially reached by [M&M]. [Flexidig ] hopes that by raising such contention, the adjudicator will find the pay less notice submitted on time and in accordance with the terms of the Contract…is invalid. In effect, what the referring party is advising the adjudicator to do is to make an assessment of the true value of the works, i.e. the defects. The adjudicator is reminded of the scope and extent of his jurisdiction confirmed by notice of adjudication. The adjudicator did not have the necessary jurisdiction to make any assessment. Any decision which does so will be unenforceable. It is respectfully submitted that submissions by the parties have fully settled the fact the Responding Party [M&M] issued a valid pay less notice which operates as a full defence to the dispute referred... Any entertainment of the value of defective works is outwith the scope of this dispute and the adjudicator’s jurisdiction. Please see attached assessment of defects which was provided to the referring party more than one year ago. This was the estimated costs last year of remedying the defects. Notably, further defects have now been identified . The letter issued to M&M on 10 December relates to the costs incurred by M&M to date. There remains approximately 2,000 defects to be corrected. While it is M&M’s position that it is not necessary to make any further submissions on this latterly raised contention, or provide further documents on the issue of defective works, the adjudicator is asked finally to note that Flexidig has manifestly misrepresented the issue in what can only be considered a last ditch and disingenuous attempt to mislead the adjudicator. The issue of the value of defective works has been the subject of a number of adjudications, in fact, one, that before Mr Broadman, and they have been referred to the High Court of Justice for enforcement under the relevant provisions. It is correct to state that in the most recent of those hearings, the learned judge held that the adjudication was unenforceable save for£12,000 . What Flexidig has not revealed is that the judge further stated the parties should commence a further adjudication on the merits to determine the true value of M&M’s defective works. The commencement of that adjudication is now imminent and Flexidig acted in bad faith by not disclosing this to the adjudicator. The adjudicator is therefore invited to reach a decision to refuse the requests sought and if Flexidig wishes to establishes a true value of the works, it would be open to do so in the context of the impending adjudication”
“6.44 The question for me is not the true value of the defective works. What sum is M&M entitled to owe from the AFP? In December 2018, MrBaldwin had assessed an estimated amount of£462,000 odd taking account of estimated future costs but Mcildowies, letter of 10 December indicates an expenditure to date of only£247,000 . 6.45 I am satisfied that M&M is entitled to withhold money for the estimated costs of making good the defective works but consider that the maximum amount relates to the£462,000 -odd less the£12,000 already awarded. I calculate the amount to be£449,776.98 excluding VAT and stress it is only an amount to be withheld from the AFP pending an assessment of the true value of the defective works by separate adjudication or agreement of the parties. Then withholding the 449 from the 673 left the sum due of£223,00 -odd.”
“Please confirm by return that you agree the decision of the adjudicator is null and void and, as such, is unenforceable failing which we hold an instruction to commence legal proceedings to seek a declaration in that regard.”
“A declaration that the adjudicator did not have jurisdiction to reach his decision dated29 December 2019 . The said decision was given in breach of natural justice or an abuse of process. The decision was wrong in law and should be set aside as a whole.”
“the claimant may serve a claim form on a defendant in Scotland or Northern Ireland where each claim is one which the court has the power to determine under the 1982 Act and: “(a) no proceedings between the parties concerning the same claim are pending in the courts of any other part of the United Kingdom...and (b) (i) the defendant is domiciled in the UK; (ii) the proceedings are within paragraph 11 of Schedule 4 to the 1982 Act….” (ii) the proceedings are within paragraph 11 of Schedule 4 to the 1982 Act….”
“(3) The court will not give permission unless satisfied that England and Wales is the proper place in which to bring the claim. (4) In particular, where – (a) the application is for permission to serve a claim form in Scotland or Northern Ireland; and (b) it appears to the court that the claimant may also be entitled to a remedy in Scotland or Northern Ireland, the court, in deciding whether to give permission, will – (i) compare the cost and convenience of proceeding there or in [this] jurisdiction...” (a) the application is for permission to serve a claim form in Scotland or Northern Ireland; and (b) it appears to the court that the claimant may also be entitled to a remedy in Scotland or Northern Ireland, the court, in deciding whether to give permission, will – (i) compare the cost and convenience of proceeding there or in [this] jurisdiction...”
“(1) Where it appears to the court that there is a good reason to authorise service by a method or at a place not otherwise permitted by this Part, the court may make an order permitting service by an alternative method or at an alternative place. (2) On an application under this rule, the court may order that steps already taken to bring the claim form to the attention of the defendant by an alternative method or at an alternative place is good service...”
“...should not adopt an overly legalistic analysis of what the dispute between the parties is. The ambit of the reference to adjudication can also, unavoidably, be widened by the nature of the defence or defences advanced by the responding party.”
“...there is no rule that a judge, arbitrator or adjudicator must decide a case only by accepting the submissions of one party or the other. An adjudicator can reach a decision on a point of importance on the material before him on a basis for which neither party has contended, provided that the parties were aware of the relevant material and the issues to which it gave rise had been fairly canvassed before the adjudicator.”
“However, I am empowered to decide how the sums to be deducted are to be assessed in the event that I find that deductions can be made, rather than simply stating that some form of deduction can be made in principle and no more…. Accordingly, I find and declare that AECOM is also entitled in principle to deduct the cost of proven defects from the sum due to Staptina at termination. This right is however confined to a deduction of the sum (if any) it would have cost Staptina to carry out the relevant rectification works had the termination not taken place.”
“...that attempting to define a dispute by reference to there being only two permissible answers is one fraught with difficulty for conceptual reasons. It is fraught with even more difficulty when one considers that, almost uniquely in quasi-judicial resolution of disputes, adjudicators are entitled to be wrong in the answers that they give, both in fact and law. If there are only two answers available, yet an adjudicator were to choose (perhaps incorrectly) a third, that does not go to her acting outside her jurisdiction. That would be answering the right question but in the wrong way. That is not the same as answering the wrong question...”
“...wording inviting alternatives of relief, which is often found ... will be part of the material to be considered by the court in each case, as each of the Notice of Adjudication and Referral Notice may contain it. However, such wording is most unlikely to be determinative on its own, and should not be seen by parties as giving any adjudicator carte blanche to go outside the scope of the dispute...”