“Should performance of this contract be prevented, whether partially or otherwise, by an Event of Force Majeure, the performance of this contract shall be suspended for the duration of the Event of Force Majeure, provided that Buyers/Sellers (the affected party) shall have served a notice on the other party within 7 consecutive days of the occurrence or not later than 21 consecutive days before commencement of the period of delivery, whichever is later, with the reasons therefor. … If the Event of Force Majeure ceases before the contract or any unfulfilled part thereof can be cancelled, Buyers/Sellers shall notify Sellers/Buyers without delay that the Event of Force Majeure has ceased. The period of delivery shall be extended, from the cessation, to as much time as was left for delivery under the contract prior to the occurrence of the Event of Force Majeure. If the time that was left for delivery under the contract is 14 days or less, a period of 14 consecutive days shall be allowed.”
“Buyers’ latest message purports to reject our force majeure declaration but does not say that Buyers remain able to perform. Indeed, it is our understanding that Buyers cannot currently have a vessel arrive at the load port for receiving the contractual cargo. At the same time, Sellers are currently unable to accumulate and load the contractual cargo.
“85. The assessment of loss necessarily requires a hypothetical exercise to be undertaken, namely, an assessment of what would have happened had there been no repudiation. That enables the true value of the rights which have been lost to be assessed. The innocent party is claiming damages and therefore the burden lies on that party to prove its loss. That requires it to show that, had there been no repudiation, the innocent party would have been able to perform his obligations under the contract. If the court were to assume that the innocent party would have been able to perform, rather than to consider what was likely to have happened in the event that there had been no repudiation, the court might well put the innocent party in a better position than he would have been in had the contract been performed. The assessment of damages does require an assumption to be made, but it is not the assumption suggested by Mr. Akka. When assessing what the innocent party would have earned had the contract been performed the court must assume that the party in breach has performed his obligations.”
“13.9 The second limb of Sellers’ appeal was the allegation that Buyers themselves were unable or would have been unable to perform their obligations, as the Contract did not afford Buyers any right to substitute their vessel. Relying on clause 6 of GAFTA 49, Mr Rookes argued that Buyers were not in a position to perform as they no longer had an available ship and they had no right to substitute the vessel as any substitution must arrive “no earlier than the estimated time of arrival of the original vessel nominated and always within the delivery period”, and that the notice of substitution should be given “no later than one business day before the estimated time of arrival of the original vessel”. 13.10 Given Sellers had by that time declared Force Majeure, this was an unattractive proposition and we summarily dismiss it accordingly.”
“Buyers shall serve not less than [8] consecutive days’ notice of the name and probable readiness date of the vessel and the estimated tonnage required. The Buyer has the right to substitute any nominated vessel. Buyer's obligations regarding pre-advice shall only apply to the original vessel nominated. No new pre-advice is required to be given in respect of any substitute vessel, provided that the substitute vessel arrives no earlier than the estimated time of arrival of the original vessel nominated and always within the delivery period. Provided the vessel is presented at the loading port in readiness to load within the delivery period, Sellers shall if necessary complete loading after the delivery period and carrying charges shall not apply. Notice of substitution to be given as soon as possible but in any event no later than one business day before the estimated time of arrival of the original vessel.”
“48. Once leave has been granted, the general approach on a s.69 application is to be informed by what this Court has termed three “guiding principles of fundamental importance” (Bunge SA v. Nibulon Trading BV[2013] EWHC 3936 (Comm) ;[2014] 1 Lloyd's Rep 393 , §§ 35-36 per Walker J, referring to statements of the Court of Appeal in MRI Trading AG v Erdenet Mining Corporation LLC [2013] 1 Lloyd's Rep. 638): (i) First, as a matter of general approach, the English court strives to uphold arbitration awards (MRI Trading § 23 per Tomlinson LJ). (ii) Secondly, in order to give effect to the first principle, the court should read an arbitration award in a reasonable and commercial way, expecting as is usually the case, that there will be no substantial fault that can be found with it. It should not approach awards “with a meticulous legal eye endeavouring to pick holes, inconsistencies and faults in awards and with the object of upsetting or frustrating the process of arbitration.” (ibid.) (iii) Thirdly, in cases of uncertainty the court will, so far as possible, construe the award in such a way as to make it valid rather than invalid (ibid.) 49. Walker J in Bunge added, however, that these principles “are not intended to, and do not, enable the court to give to an award a meaning which plainly was not intended by its authors” (§ 36). 50. In relation to a challenge to a GAFTA award, two further relevant considerations apply: (i) The first and second general principles mentioned above will apply a fortiori where "the tribunal comprises market men, since one is not entitled to expect from trade arbitrators the accuracy of wording, or cogency of expression, which is required of a judge" (MRI Trading AG[2012] EWHC 1988 (Comm) ; [2013] 1 All ER (Comm) 1, 8g-h [15(a)] and 9f [16] per Eder J). (ii) Trade tribunal decisions are generally to be accorded deference where the arbitrators' experience assists it in determining a question of law, such as the interpretation of contractual documents or correspondence passing between members of an arbitrator's own trade or industry (Kershaw Mechanical Services[2006] EWHC 727 (TCC) ;[2006] 4 All ER 79 , at § 57(2) per Jackson J).” (i) First, as a matter of general approach, the English court strives to uphold arbitration awards (MRI Trading § 23 per Tomlinson LJ). (ii) Secondly, in order to give effect to the first principle, the court should read an arbitration award in a reasonable and commercial way, expecting as is usually the case, that there will be no substantial fault that can be found with it. It should not approach awards “with a meticulous legal eye endeavouring to pick holes, inconsistencies and faults in awards and with the object of upsetting or frustrating the process of arbitration.” (ibid.) (iii) Thirdly, in cases of uncertainty the court will, so far as possible, construe the award in such a way as to make it valid rather than invalid (ibid.) (i) The first and second general principles mentioned above will apply a fortiori where "the tribunal comprises market men, since one is not entitled to expect from trade arbitrators the accuracy of wording, or cogency of expression, which is required of a judge" (MRI Trading AG[2012] EWHC 1988 (Comm) ; [2013] 1 All ER (Comm) 1, 8g-h [15(a)] and 9f [16] per Eder J). (ii) Trade tribunal decisions are generally to be accorded deference where the arbitrators' experience assists it in determining a question of law, such as the interpretation of contractual documents or correspondence passing between members of an arbitrator's own trade or industry (Kershaw Mechanical Services[2006] EWHC 727 (TCC) ;[2006] 4 All ER 79 , at § 57(2) per Jackson J).”
“Until recently, there have been conflicting dicta and much debate about the proper approach to the assessment of damages in particular where the wrongdoer has committed a wrongful repudiation, anticipatory breach or renunciation and, in response, the innocent party has brought the contract to an end. This has now been resolved, at least at first instance, in favour of what has been described as the ‘compensatory principle’. This approach requires a hypothetical exercise to be undertaken, namely, an assessment of what would have happened had there been no repudiation. The burden lies on the innocent party to prove that, had there been no repudiation, the innocent party would have been able to perform its obligations under the contract.”
“Nevertheless, it may be that there are certain circumstances in which the innocent party may be released from performance of one or more of his obligations under the contract, notwithstanding the fact that he has not terminated further performance of the contract as a result of the wrongdoer’s breach. The first arises where the party in breach has, by words or conduct, represented to the innocent party that he will no longer require performance of a particular obligation under the contract, and the innocent party acts upon that representation. In such a case the party in breach will be estopped from contending that the innocent party still remains bound by that obligation.”
“Of course, it is always open to A, who has refused to accept B’s repudiation of the contract, and thereby kept the contract alive, to contend that in relation to a particular right or obligation under the contract, B is estopped from contending that he, B, is entitled to exercise that right or that he, A, has remained bound by that obligation. If B represents to A that he no longer intends to exercise that right or requires the obligation to be fulfilled by A and A acts upon that representation, then clearly B cannot be heard thereafter to say that he is entitled to exercise that right or that A is in breach of contract by not fulfilling that obligation.”
“if the Event of Force Majeure ceases before the contract or any unfulfilled part thereof can be cancelled, Buyers/Sellers shall notify Buyers/Sellers without delay that the Event of Force Majeure has ceased.”
“Once it is shown that a representation was calculated to influence the judgment of a reasonable man, the presumption is that he was so influenced”
“it is enough if the point is ‘in play’ or ‘in the arena’ in the proceedings, even if it is not precisely articulated… a party will usually have had a sufficient opportunity if the ‘essential building blocks’ of the tribunal’s analysis and reasoning were in play in relation to an issue, even where the argument was not articulated in the way adopted by the tribunal.”
“I think the court should tend to prefer that construction which will ensure performance and not encourage avoidance of contractual obligations.”
“7.108 This principle is not a rule of law; rather it is an aspect of the principle of interpretation that leans against interpretations that produce unreasonable or absurd consequences that could not have been intended. The contractual intention is still to be decided by reference to the ordinary principles applicable to the interpretation of contracts.”
“is [Holbud] entitled to nominate a substitute vessel at any time prior to acceptance of such repudiation?”
“An application or appeal may not be brought if the applicant or appellant has not first exhausted (a) any available arbitral process of appeal or review, and (b) any available recourse under section 57 (correction of award or additional award).” (a) any available arbitral process of appeal or review, and (b) any available recourse under section 57 (correction of award or additional award).”
“The tribunal may on its own initiative or on the application of a party (a) correct an award so as to remove any clerical mistake or error arising from an accidental slip or omission or clarify or remove any ambiguity in the award, or (b) make an additional award in respect of any claim (including a claim for interest or costs) which was presented to the tribunal but was not dealt with in the award.” (a) correct an award so as to remove any clerical mistake or error arising from an accidental slip or omission or clarify or remove any ambiguity in the award, or (b) make an additional award in respect of any claim (including a claim for interest or costs) which was presented to the tribunal but was not dealt with in the award.”