“At the time that BDW first became aware of the Defects and/or first incurred the costs pleaded at paragraph 48.1-48.13 (“the Costs”) (a) BDW no longer had any proprietary interest in the Developments; and (b) BDW did not have an obligation in law to rectify the Defects. BDW’s case is that (i) it owed obligations to third parties in relation to the Defects but (ii) any action brought by third parties against BDW to enforce those obligations would be time-barred.”
“3.3. The Consultant warrants that it has exercised and will continue to exercise in the performance of its duties under this Agreement such reasonable skill care and diligence as is to be expected of a properly qualified and competent member of the relevant profession experienced in carrying out work such as its duties under this Agreement in relation to projects of a similar size scope nature and complexity to the Development and that in the performance of its duties it will act with all such reasonable skill care and diligence to enable programmes and timetables to be met and all work to be completed as soon as practically possible.”
“104. That measurable loss, in the case of a negligently designed structure that has been constructed, for example, is the cost of making it structurally safe. That occurs when the structure is constructed in accordance with the negligent design. It cannot be right to say that the developer of a building has no such loss unless and until he discovers that the building he has had constructed is structurally unsafe. That proposition is not in accordance with fundamental principles in terms of accrual of causes of action in negligence. It also introduces a concept that is not accepted generally in English law, which is that a cause of action accrues upon date of knowledge […] 108. I therefore conclude that the cause of action accrued, with all of its necessary ingredients completed, not later than the date of practical completion of each of the blocks. This conclusion has the following benefits. It is consistent with, and continues, the approach of English law that knowledge is not required to complete a cause of action. It is therefore consistent with orthodoxy. It is also consistent with the other first instance decisions relied upon in argument, in particular New Islington and Co-op v Birse. It is also consistent with the concept of BDW being worse off, or having acted to its detriment, as explained by Hobhouse LJ in the Court of Appeal in Knapp v Ecclesiastical Insurance Group plc [1998] P.N.L.R. 172.”
“I consider that the answer to this question is the risks of harm to BDW, the employer, against which the law imposed upon URS, the structural designer, a duty to take care was the risk of economic loss that would be caused by a construction of a structure using a negligent design such that it was built containing structural deficiencies or defects.”
“I do not accept that characterisation. Remedial works costs of a structurally inadequate building cannot, in my judgment, be properly characterised as not being in the contemplation of the employer and structural engineer at the time they contract, nor are they too remote.”
“…Even if the sub-contractors had not known the terms of the main contract, they knew that part of Birse's obligations under the main contract had been subcontracted to them and that Birse's reasonable expectation was that they would provide design or inspection services that were appropriate to the proper discharge of those obligations as required by the terms of their sub-contracts. Equally, if their design was defective, the risk was that Birse would build in accordance with it, which would have two consequences: first, the building as built would be defective in Birse's hands and would consequently be less valuable because of the need to remedy it in order to bring it to an acceptable standard; and, second, if the building was handed over to the employer in its defective condition, Birse was likely to be placed in breach of contract, whether or not it appreciated it or accepted it at the time.”
“…However, where what is being contemplated is a failure to design or inspect a building under construction, the likelihood is that negligent failures by the sub-contractor will cause the main contractor to incur liabilities that are financially measurable and significant. The consequences of a negligent failure to inspect are predictably similar. I conclude that, in a case where the development is being constructed for someone other than the main contractor, the primary risk that should be in the contemplation of the parties will be that the main contractor will build and hand over a defective building to the employer and thereby incur liability. His liability will usually be measured by the cost to the main contractor of undertaking repairs or the sums necessary to compensate the main contractor for the defects.”
“[…] a claim in tort based on negligence is incomplete without proof of damage. Damage in this sense is an abstract concept of being worse off, physically or economically, so that compensation is an appropriate remedy”
“I think, with all respect to Geoffrey Lane L.J. [in Sparham-Souter], that there is an element of confusion between damage to the plaintiff's body and latent defect in the foundations of a building. Unless the defect is very gross, it may never lead to any damage at all to the building. It would be analogous to a predisposition or natural weakness in the human body which may never develop into disease or injury. The plaintiff's cause of action will not accrue until damage occurs, which will commonly consist of cracks coming into existence as a result of the defect even though the cracks or the defect may be undiscovered and undiscoverable. There may perhaps be cases where the defect is so gross that the building is doomed from the start, and where the owner's cause of action will accrue as soon as it is built, but it seems unlikely that such a defect would not be discovered within the limitation period. Such cases, if they exist, would be exceptional.”
“Counsel for the appellants submitted that the fault of his clients in advising on the design of the chimney was analogous to that of a solicitor who gives negligent advice on law, which results in the client G suffering damage and a right of action accruing when the client acts on the advice: see Howell v. Young (1826) 5 B. & C. 259 and Forster v. Outred & Co. [1982] 1 W.L.R. 86. It is not necessary for the present purpose to decide whether that submission is well founded, but as at present advised, I do not think it is. It seems to me that, except perhaps where the advice of an architect or consulting engineer leads to the erection of a building which is so defective as to be ‘doomed from the start’, the cause of action accrues only when physical damage occurs to the building. In the present case that was April 1970 when, as found by the judge, cracks must have occurred at the top of the chimney, even though that was before the date of discoverability. I am respectfully in agreement with Lord Reid's view expressed in Cartledge v. E.Jopling & Sons Ltd. [1963] A.C. 758, that such a result appears to be unreasonable and contrary to principle, but I think the law is now so firmly established that only Parliament can alter it.”
“In the second branch of the argument it was maintained that a distinction fell to be drawn between the case where the defect in a building was such that damage must inevitably eventuate at some time and the case of a defect such that damage might or might not eventuate. The former case was that of a building "doomed from the start" such as was in the contemplation of Lord Fraser of Tullybelton when he made reference to that concept in his dicta in the Pirelli case, at p. 16. In the present case the houses were doomed from the start because the event showed that damage was bound to occur eventually. My Lords, whatever Lord Fraser may have had in mind in uttering the dicta in question, it cannot, in my opinion, have been a building with a latent defect which must inevitably result in damage at some stage. That is precisely the kind of building that the Pirelli case was concerned with, and in relation to which it was held that the cause of action accrued when the damage occurred. This case is indistinguishable from the Pirelli case and must be decided similarly. The second branch of the architects' argument fails. I understand that all your Lordships agree.”
“The drains, in the physical condition resulting from the defect in design, were not such as to produce at once their damaging effects. They were capable of functioning properly as drains and they did so for some twenty months. When they failed effectively to function as drains because of heavy rainfall in the area they did not merely function unsatisfactorily, e.g. by making noises or emitting smells, but were the cause of physical damage to other parts of the building, The defect in design in this case was, in my judgment, as latent, and as distinct from subsequent physical damage caused by it, as was the negligent incorporation of unsuitable material in Pirelli’s chimney.”
“From the moment when the property was handed over to the plaintiffs by the builders the drainage system suffered from an existing and physical defect: it was incapable of dealing with foreseeable volumes of water which were to be expected to occur from time to time. No change occurred in the system between that time and the event of the first flood. The effect of the flood was to demonstrate the existence of the physical defect: it did not occasion it.”
“If the plaintiffs had happened to discover the defect before any damage had occurred there would seem to be no good reason for holding that they would not have had a cause of action in tort at that stage, without having to wait until some damage had occurred. They would have suffered economic loss through having a defective chimney upon which they required to expend money for the purpose of removing the defect. It would seem that in a case such as Pirelli, where the tortious liability arose out of a contractual relationship with professional people, the duty extended to take reasonable care not to cause economic loss to the client by the advice given.”
“I think that a defect in the construction of the building, be it as a result of a faulty design or construction of part of that building or its services, means and can only mean that a building in that defective state is a damaged building. It is a damaged article in the sense that it is not a sound one. As Mr Vallance pointed out, rightly in my view, a building is a manufactured thing, and if it is unsuitable or defective when it is handed over it seems to me that the cause of action arises when the person acquires it in its defective state. It may well be that to quantify the economic loss that flows or will flow from the defective state will be impossible at that time, but in my judgment that is the time when the cause of action arises. Accordingly, I look to see what evidence there is that the defect existed before17 January 1973 , the writ having been issued on17 January 1979 . It seems to me to be very clear from all that subsequently transpired that if this air-conditioning plant was defective, as it is alleged to have been, it was defective in design and construction from the time that it was installed, and that was in 1972, over six years before the writ was issued. It does not seem to me to matter how the details of the defects manifested themselves with ever-increasing severity over the years. Complaints of its defective operation were made in 1972 and as the years went by details of the defective design came to light which seem to support the view that, if the allegations are right, it very clearly was a defectively designed and constructed plant from the very beginning. It has never been suggested that the plant was satisfactory at the start but only developed defects as time went by. Accordingly I would, as an alternative if necessary, strike out the statement of claim on the ground that it was very clearly statute-barred.”
“38. The fact remains, however, that the House in Murphy did not say that Pirelli was wrongly decided. Accordingly, it remains an authority that is binding on me. In Knapp, the Court of Appeal stated that it was bound by Pirelli, although it appears that Murphy was not cited to it. 39. Since I am bound by Pirelli, it is clear that the Association’s cause of action in the present case did not accrue when they first knew or ought reasonably to have known of the defect. It is true that in the Sutherland case, Deane J. said that the date of knowledge of the defect in the building was his “preferable” approach, and that Lord Keith found the reasoning of Deane J. to be “incontrovertible”
“If I had been free to do so, I would have reached the same conclusion by a different route, but that would have involved the proposition that Pirelli was wrongly decided. It seems to me that, if it is now to be understood as a case on economic loss, then Pirelli cannot stand. That is because it makes no sense to say that the plaintiffs in that case first suffered economic loss when, unknown to them, cracks first occurred in the chimney. There are arguments in favour of saying that the plaintiffs suffered economic loss when the chimney was constructed to the defective design, or alternatively (Deane J.’s preferred approach) when the defect was first discovered or discoverable. On the facts of Pirelli, the first approach would have led to the cause of action accruing in June or July 1969; the second approach would have led to the cause of action accruing in 1977. One advantage of abandoning the Pirelli approach would be to bring the defective building cases into line with the other cases involving latent defects resulting from negligent advice. On the face of it, there is no good reason why building cases should be the subject of special rules. Another advantage would be to avoid the kind of contortions that are exemplified by decisions such as Dove [Dove v Banhams Patent Locks Ltd [1983] 1 W.L.R. 1436] and Harriss. I see the great force of the reasoning of Deane J. Similar reasoning was expressed by the Privy Council in the New Zealand case of Invercargill City Council v. Hamlin [1996] A.C. 624, 646H–649A. But, as Hobhouse L.J. pointed out in Knapp (at page 397), New Zealand, and indeed Australia, have adopted different solutions to the potential injustices which arise from a strict application of the primary limitation period. In those countries judicial solutions have been found. In England the approach has been different: ‘Additional statutory provisions have been introduced designed to achieve similar results. These provisions are premised upon the prima facie application of the primary limitation period and introduced in a defined way certain relaxations of it to avoid injustice.’”
“Within the bounds of sense and reasonableness the policy of the law should be to advance, rather than retard, the accrual of a cause of action. This is especially so if the law provides parallel causes of action in contract and in tort in respect of the same conduct. The disparity between the time and these parallel causes of action should be smaller, rather than greater.”
“135 Limitation periods (1) Aftersection 4A of the Limitation Act 1980 insert— “4B Special time limit for certain actions in respect of damage or defects in relation to buildings (1) Where by virtue of a relevant provision a person becomes entitled to bring an action against any other person, no action may be brought after the expiration of 15 years from the date on which the right of action accrued. (2) An action referred to in subsection (1) is one to which— (a) sections 1, 28, 32, 35, 37 and 38 apply; (b) the other provisions of this Act do not apply. (3) In this section “relevant provision” means— (a) section 1 or 2A of theDefective Premises Act 1972 ; (b)section 38 of the Building Act 1984 . (4) Where by virtue ofsection 1 of the Defective Premises Act 1972 a person became entitled, before the commencement date, to bring an action against any other person, this section applies in relation to the action as if the reference in subsection (1) to 15 years were a reference to 30 years. (5) In subsection (4) “the commencement date” means the day on whichsection 135 of the Building Safety Act 2022 came into force.” (2) Insection 1(5) of the Defective Premises Act 1972 , for “theLimitation Act 1939 , theLaw Reform (Limitation of Actions, &c.) Act 1954 and theLimitation Act 1963 ” substitute “theLimitation Act 1980 ”. (3) The amendment made by subsection (1) in relation to an action by virtue ofsection 1 of the Defective Premises Act 1972 is to be treated as always having been in force. (4) In a case where— (a) by virtue ofsection 1 of the Defective Premises Act 1972 a person became entitled, before the day on which this section came into force, to bring an action against any other person, and (b) the period of 30 years from the date on which the right of action accrued expires in the initial period,section 4B of the Limitation Act 1980 (inserted by subsection (1)) has effect as if it provided that the action may not be brought after the end of the initial period. (5) Where an action is brought that, but for subsection (3), would have been barred by theLimitation Act 1980 , a court hearing the action must dismiss it in relation to any defendant if satisfied that it is necessary to do so to avoid a breach of that defendant’s Convention rights. (6) Nothing in this section applies in relation to a claim which, before this section came into force, was settled by agreement between the parties or finally determined by a court or arbitration (whether on the basis of limitation or otherwise). (7) In this section— “Convention rights” has the same meaning as in theHuman Rights Act 1998 ; “the initial period” means the period of one year beginning with the day on which this section comes into force.”
“1 Duty to build dwellings properly. (1) A person taking on work for or in connection with the provision of a dwelling (whether the dwelling is provided by the erection or by the conversion or enlargement of a building) owes a duty— (a) if the dwelling is provided to the order of any person, to that person; and (b) without prejudice to paragraph (a) above, to every person who acquires an interest (whether legal or equitable) in the dwelling; to see that the work which he takes on is done in a workmanlike or, as the case may be, professional manner, with proper materials and so that as regards that work the dwelling will be fit for habitation when completed. (2) A person who takes on any such work for another on terms that he is to do it in accordance with instructions given by or on behalf of that other shall, to the extent to which he does it properly in accordance with those instructions, be treated for the purposes of this section as discharging the duty imposed on him by subsection (1) above except where he owes a duty to that other to warn him of any defects in the instructions and fails to discharge that duty. (3) A person shall not be treated for the purposes of subsection (2) above as having given instructions for the doing of work merely because he has agreed to the work being done in a specified manner, with specified materials or to a specified design. (4) A person who— (a) in the course of a business which consists of or includes providing or arranging for the provision of dwellings or installations in dwellings; or (b) in the exercise of a power of making such provision or arrangements conferred by or by virtue of any enactment; arranges for another to take on work for or in connection with the provision of a dwelling shall be treated for the purposes of this section as included among the persons who have taken on the work. (5) Any cause of action in respect of a breach of the duty imposed by this section shall be deemed, for the purposes of theLimitation Act 1980 , to have accrued at the time when the dwelling was completed, but if after that time a person who has done work for or in connection with the provision of the dwelling does further work to rectify the work he has already done, any such cause of action in respect of that further work shall be deemed for those purposes to have accrued at the time when the further work was finished.”
“1 Entitlement to contribution. (1) Subject to the following provisions of this section, any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise). (2) A person shall be entitled to recover contribution by virtue of subsection (1) above notwithstanding that he has ceased to be liable in respect of the damage in question since the time when the damage occurred, provided that he was so liable immediately before he made or was ordered or agreed to make the payment in respect of which the contribution is sought. (3) A person shall be liable to make contribution by virtue of subsection (1) above notwithstanding that he has ceased to be liable in respect of the damage in question since the time when the damage occurred, unless he ceased to be liable by virtue of the expiry of a period of limitation or prescription which extinguished the right on which the claim against him in respect of the damage was based. (4) A person who has made or agreed to make any payment in bona fide settlement or compromise of any claim made against him in respect of any damage (including a payment into court which has been accepted) shall be entitled to recover contribution in accordance with this section without regard to whether or not he himself is or ever was liable in respect of the damage, provided, however, that he would have been liable assuming that the factual basis of the claim against him could be established. (5) A judgment given in any action brought in any part of the United Kingdom by or on behalf of the person who suffered the damage in question against any person from whom contribution is sought under this section shall be conclusive in the proceedings for contribution as to any issue determined by that judgment in favour of the person from whom the contribution is sought. (6) References in this section to a person’s liability in respect of any damage are references to any such liability which has been or could be established in an action brought against him in England and Wales by or on behalf of the person who suffered the damage; but it is immaterial whether any issue arising in any such action was or would be determined (in accordance with the rules of private international law) by reference to the law of a country outside England and Wales.”
“15…The primary provision giving rise to the right to claim contribution is section 1(1) of the 1978 Act. There is no suggestion there of any limit or restriction on the right of a person to claim contribution from another person liable in respect of the same damage. Subsections (2) to (4) of section 1 are designed not to restrict the right, but to remove restrictions or defences that might otherwise be raised.Section 10 of the Limitation Act 1980 , albeit that it arises out of an enactment of the 1978 Act, is directed to time limitation and not to narrowing the nature of the right to contribution.”