“New claims in pending actions: rules of court.E+W (1) For the purposes of this Act, any new claim made in the course of any action shall be deemed to be a separate action and to have been commenced— (a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and (b) in the case of any other new claim, on the same date as the original action. (2) In this section a new claim means any claim by way of set-off or counterclaim, and any claim involving either — (a) the addition or substitution of a new cause of action; or (b) the addition or substitution of a new party; … (3) Except as provided by section 33 of this Act or by rules of court, neither the High Court nor any county court shall allow a new claim within subsection (1)(b) above, other than an original set-off or counterclaim, to be made in the course of any action after the expiry of any time limit under this Act which would affect a new action to enforce that claim. … (4) Rules of court may provide for allowing a new claim to which subsection (3) above applies to be made as there mentioned, but only if the conditions specified in subsection (5) below are satisfied, and subject to any further restrictions the rules may impose. (5) The conditions referred to in subsection (4) above are the following — (a) in the case of a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and (b) in the case of a claim involving a new party, if the addition or substitution of the new party is necessary for the determination of the original action.” (a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and (b) in the case of any other new claim, on the same date as the original action. (a) the addition or substitution of a new cause of action; or (b) the addition or substitution of a new party; (a) in the case of a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and (b) in the case of a claim involving a new party, if the addition or substitution of the new party is necessary for the determination of the original action.”
“(2) Where an application to the Court for leave to make the amendment mentioned in paragraph (3), (4) or (5) is made after any relevant period of limitation current at the date of issue of the writ has expired, the Court may nevertheless grant such leave in the circumstances mentioned in that paragraph if it thinks it just to do so. … (5) An amendment may be allowed under paragraph (2) notwithstanding that the effect of the amendment will be to add or substitute a new cause of action if the new cause of action arises out of the same facts or substantially the same facts as a cause of action in respect of which relief has already been claimed in the action by the party applying for leave to make the amendment.”
“Application to set aside or vary order made without notice (1) A person who was not served with a copy of the application notice before an order was made under rule 23.9, may apply to have the order set asideor varied. (2) An application under this rule must be made within 7 days after the date on which the order was served on the person making the application.”
“9.1 Subject to Clause 8.3, the Beneficiary [i.e. RBS] shall give notice to the Main Contractor within that period of not less than 21 days specified in the notice under Clause 8.1: 9.1.1 requiring it to continue its obligations under the Main Contract in relation to the Project; and 9.1.2 acknowledging that the Beneficiary is assuming all the existing and future obligations of the Employer under the Main Contract; then upon determination of the Main Contractor’s employment under the Main Contract the provisions of Clause 9.2 shall apply. 9.2 Subject to Clause 8.3, and in the event that a notice is served in accordance with Clause 9.1, notwithstanding determination of the Main Contractor’s employment as specified in Clause 9.1 the Main Contract shall be deemed (as between the Main Contractor and the Beneficiary or the Beneficiary’s nominee) to continue in full force and effect as if the right of determination on the part of the Main Contractor had not arisen and in all respects as if the Main Contract had been made between the Main Contractor and the Beneficiary to the exclusion of the Employer whereby: (a) the Beneficiary assumes all the existing and future obligations of the Employer under the Main Contract; and (b) the Main Contractor acknowledges all of is obligations under the Main Contract in favour of the Beneficiary.” 9.1.1 requiring it to continue its obligations under the Main Contract in relation to the Project; and 9.1.2 acknowledging that the Beneficiary is assuming all the existing and future obligations of the Employer under the Main Contract; (a) the Beneficiary assumes all the existing and future obligations of the Employer under the Main Contract; and (b) the Main Contractor acknowledges all of is obligations under the Main Contract in favour of the Beneficiary.”
“Many thanks, and in the circumstances the orders will not be made without a hearing. For that purpose, the claimants must complete and submit a request for a private-room appointment.”
“a. The claims and causes of action set out in the amended Claim Forms and the amended and re-amended Particulars of Claim in the Actions were brought within 3 years of the starting date as defined insection 14A of the Limitation Act 1980 . b. Both Defendants were joined into the Actions upon their commencement on18 May 2009 , both Defendants have been parties ever since and both Defendants remain parties to the Actions at the date of this Order.”
“For my part I am doubtful whether there is any sufficient legal basis for holding in favour of the simple doctrine of ‘abandonment’ which was referred to in the Lewis case. Cargill’s case, as I think, was different. That was one, properly looked at, of election between two inconsistent remedies, and of course when one looks at it in that way, there was an abandonment of that which one has not elected. Be that as it may, I would wish to avoid these subtleties in this sort of context. When a plaintiff seeks leave to serve a re-amended statement of claim, and one has to consider and contrast it with the earlier amended statement of claim for the purposes, for instance, ofs.35 of the Limitation Act 1980 , one realistically looks at the two statements of claim. One does not look truly to the endorsement on the writ – in which the plaintiff by Order 6,r2(1)(a) need not ‘plead’ any cause of action at all (if ‘plead’ is the correct word).”