“Concealed pipework-Chilled To-insulate with Class ‘O’ Armaflex sections, joints glued and covered in bright Class ‘O’ foil with the joints taped…”
“The fan coil chilled water insulation sample on the 15th floor was inspected…on the 8th February and was considered satisfactory, subject to revising the chilled water block/hangar detail ie continuous foil between block and hanger, as previously noted to yourselves… Brian Wilding has previously pointed out the foil needs to be continuously around two halves of a wooden block to achieve the vapour barrier that these need to be corrected in most cases before the insulation is applied elsewhere…”
“1. I think that we were all amazed at the extent of the corrosion to the section of pipework that was replaced following discovery of the leak…and I will arrange this pipework to be tested to provide supporting information and confidence that the leak was from the outside and the laboratory analysis should tell us a lot more about the cause. 2. …my initial reaction is that the pipework is suffering from a lack of continuity in the vapour seal to the installation…I am researching the paint product that was used [on the pipes]…the three layers [of Armaflex]…[were] not glued to each other or the outer layer of foil. I believe the potential for air gaps and an ineffective vapour seal will result and my first reaction is that the method of insulating the shell and core risers is the cause of your problem… 4. With PME I did a wider scan of the risers and found a mixture of equally bad pipework and some that was not as bad but still gives me serious concerns about longevity…”
“Radiography of damaged/corroded area on 6” chilled water pipe. Radiographs confirm loss of wall thickness due to corrosion with pinhole sized pitting at the various depths”
“3.1.1…The central area of the section was heavily corroded with a thick layer of corrosion products and little evidence of any paintwork remaining. Missing patches of this thick layer of corrosion product were evident. 3.1.3 Examination of the microsection taken through the region of heavy corrosion showed a thick layer of corrosion deposit…Underneath this deposit was a network of corrosion pits…The remaining wall thickness at the worst point was measured at approximately 4.17 mm. Examination of the microsection taken through a blistered region showed a number of large pits with varying characteristics…the approximate wall thickness on this section was measured at 4.82 mm…. 4.0 The majority of the fracture surface has been subject to general corrosion, with dispersed deep pits observed… A band of heavy corrosion was observed in the centre of the pipe section received on closer examination showed the pipe surface to be covered in a thick layer of corrosion product, beneath which was a network of wide pits… Loss of wall thickness was approximately 0.75 mm at the worst point and assuming the original wall thickness is 5 mm, this loss is 15% of the original wall thickness. No breach of the inner wall surface was observed or reported by the client and no evidence of cracking was found associated with pitting. It is not deemed an excessive amount of material loss to this pipe material in the situation described…”
“The report highlights the exposure of the pipework to surface water causing the corrosion and the accelerated corrosion (which led to the initial leak) under a strap or clamp.”
“7.14 The installation as it currently stands presents a major risk to the tenants business. Loss of chilled water will render the space unoccupiable and the damage caused by major leaks could have far reaching impact and disruption of power and data systems as well as the physical damage. 7.15 Major leaks and periodic renewal of sections of corroded pipework will necessitate, in an emergency, to introduce fresh water into the system to replace that drained off to carry out the repairs [sic] 7.18 The risk to the tenants business is high as over time the corrosion will increase and penetration into the pipework wall thickness will become greater leading to potentially disastrous leaks. 7.21 A major part of the strategy will concentrate on risk assessments and the continuity of business by the tenants. The replacement exercise will present a risk of water quality problems as well but the strategy should allow for "doing things right" rather than "making do and mend" in an emergency situation.”
“…I am writing to confirm the previous advice relating to the chilled water pipework installation…. Having reviewed both bids from the contractor [for “make do and mend” and replacement], it is the team’s recommendation to instruct a full replacement. The cost saving is small when measured against the risks involved with part renewal and part wire brush and paint scenario. We know that pipework adjacent supports is [sic] seriously corroded and needs to be replaced. The insertion of numerous new mini sections of pipework in the riser is illogical and presents potentially greater risks to the week to week programming of the work, the recommissioning and water treatment processes. Whilst the tender exercise demonstrates the potential saving, I consider this will be eroded by the need to issue instructions to deal with discovery items during the course of the work which would not be if a pipework renewal option is implemented. When considering the value of both options, it is clearly the correct choice to have a replacement pipework system rather [than] one that has suffered corrosion.”
“2.1.1 The Contractor shall upon and subject to the Conditions carry out and complete the Works in compliance with Contract Documents. 2.1.2 For the purpose of so carrying out and completing the Works, the Contractor shall, in accordance with the Contract Drawings and the Contract Bills where and to the extent that the same relevant, complete the design for the Contractor’s Designed Portion including the selection of any specifications for any kinds and standards of the materials and goods and workmanship to be used in the construction of that Portion so far as not described or stated in the Employer’s Requirements or Contractor’s Proposals, and the Contractor shall comply with the directions which the Architect shall give for the integration of the design for the Contractor’s Designed Portion with the design for the Works as a whole, subject to the provisions of clause 2.7. 2.1.3 Where and to the extent that approval of the quality of materials or of the standards of workmanship is a matter for the opinion of the Architect, such quality and standards shall be to the reasonable satisfaction of the Architect. 2.11.1 The Contractor warrants and undertakes to the Employer that: 2.11.1.1 the Works will be carried out using good up-to-date building practice with reference to relevant provisions of current British Standard Specifications and Codes of Practice; 2.11.1.2 the Works will, unless specifically otherwise instructed by the Architect, comprise only materials and goods which are new and of sound and merchantable quality; 2.11.1.3 upon the issue of the Certificate of Practical Completion…the Works as constructed will be in accordance with the Contract Documents as varied by any Architect’s instruction unless otherwise agreed in writing by the Employer.”
“Carry out and complete the design, supply, installation, testing and commissioning of the mechanical, electrical, public health and fire engineering services in accordance with the Sub-Contract.”
“4.1.1 The Sub-Contractor shall carry out and complete the Sub-Contract Works in compliance with the Sub-Contract Documents and in conformity with all reasonable directions and requirements of the Contractor (so far as they may apply) regulating for the time being the reasonable carrying out of the Works. 4.1.2 All materials and goods shall, so far as procurable, be of the kinds and standards described in the Sub Contract Documents or, to the extent that no such standards are specified in the Sub-Contract Documents, shall be the standard appropriate to the Sub-Contract Works provided that where and to the extent that approval of the quality and standards of materials and goods is a matter for the opinion of the Architect such standards shall be to the reasonable satisfaction of the Architect. 4.1.2 All workmanship shall, so far as procurable, be of the kinds and standards described in the Sub Contract Documents or, to the extent that no such standards are specified in the Sub-Contract Documents, shall be the standard appropriate to the Sub-Contract Works provided that where and to the extent that approval of the quality and standards of workmanship is a matter for the opinion of the Architect such standards shall be to the reasonable satisfaction of the Architect. 4.1.3 All work should be carried out in a proper and workmanlike manner. 5.1 [The Sub-Contractor shall] .1 observe, perform and comply with all the provisions of the Main Contract as referred to in the Appendix, part one, on the part of the Contractor to be observed, performed and complied with so far as they relate and apply to the Sub-Contract Works… Without prejudice to the generality of the foregoing, the Sub-Contractor shall observe, perform and comply with the following provisions of the Main Contract Conditions: clauses 2 (where the Sub-Contractor is providing any elements of Design in connection with the Works)… .2 indemnify and save harmless the Contractor against and from .1 any breach, non-observance or non-performance by the Sub-Contractor or his servants or agents of any of the provisions of the Main Contract in so far as they relate and apply to the Sub-Contract… .3 any claim, damage, loss or expense and due to or resulting from any negligence or breach of duty on the part of the Sub-Contractor, his servants or agents…” .1 any breach, non-observance or non-performance by the Sub-Contractor or his servants or agents of any of the provisions of the Main Contract in so far as they relate and apply to the Sub-Contract… .3 any claim, damage, loss or expense and due to or resulting from any negligence or breach of duty on the part of the Sub-Contractor, his servants or agents…”
“Only first class workmanship will be accepted…Insulating material, however fixed, shall be in contact with the surface to which it is applied. Sectional pipe insulation…sections shall fit snugly on the diameter of the pipe to be insulated. Where ‘foil-faced laminate’ is specified this shall mean a factory produced laminate of craft paper and suitable aluminium foil finish, with a minimum thickness of 0.008 mm, sandwiching a glass fibre reinforcing mat, all having a Class ‘O’ surface spread of flame fire rating. Factory applied or site applied ‘foil-faced laminate’ and sectional pipe insulation shall be sealed on all longitudinal and circumferential joints with manufacturer’s selfseal overlap all with 100 [mm] wide self adhesive ‘foil-faced laminate’ tape adding a minimum thickness of 0.05 mm. Care should be taken to ensure that the services to be jointed are free from dust and moisture etc. Additional suitable adhesive shall be applied to the joint as necessary to provide a neat, firm and continuous joint. For all pipework…specified as having a ‘double vapour barrier’ it shall be formed as follows: .1 First barrier-the insulation plus vapour sealant. .2 Second barrier-the special ‘foil-faced laminate’. Both insulation and facing materials shall be impervious and continuous and shall not be punctured or fouled by the supports. The insulating material shall be cellular and all circumferential and longitudinal joints shall be sealed with a suitable waterproof bonding adhesive (reference B.S. 5970) which also acts as a filler. The supporting insulation at supports shall be a material suitable for the temperature condition and of sufficient compressive strain to take the load is transmitted to the supports without deforming. The load bearing insulation shall be extended on each side of the point of support and a short section of the insulation finish shall be fixed in place when the pipework…and saddle are installed to ensure an unbroken vapour seal finish is achieved. This requirement necessitates co-ordination between the thermal insulation installer and the pipework…installer. The outer ‘double vapour barrier’ is a technical requirement and it shall not be used as the exposed surface finish where there is a risk of damage… To complete the ‘double vapour barrier’ 100mm wide self adhesive ‘foil-faced laminate’ tape adding a minimum total thickness of 0.05mm shall be applied to ‘foil-faced laminate’, and should be over lapped onto itself at terminations by at least 50 mm. A suitable primer shall be applied on the foil surface before applying the tape, [as] recommended by the manufacturer…The ‘vapour barrier’ shall be continuous unless the pipework…is alternatively protected. All sectional pipe…shall be further secure with aluminium alloy bands of not greater than 300 mm intervals…. Standards and types of materials and workmanship not specifically covered by this specification shall be as B.S. 5970.”
“Class ‘O’ (ie. Grey), CFC free, closed cell, flexible, elastomeric nitrile rubber base material and covered with a ‘foil-faced laminate’. Suitable adhesive shall be used as recommended by the manufacturer, providing both a secure bond and a continuous vapour seal.”
“Rule 2 Attach each end of the Armaflex tube to the pipe with Armaflex adhesive, and make sure the adhesive joints [are applied to] critical points such as flanges, T-sections, elbows, supports, etc… Rule 4 On chilled water and refrigeration pipework use Armaflex in conjunction with pre-insulated Armaflex Pipe Supports whenever possible…”
“MR JUSTICE AKENHEAD: What is it that has caused the ingress or presence of water on the pipes that has led to the corrosion there (in the basement)? A. I didn't find anything, any information that I could determine during my inspections and the preparation of my report that assisted me in that matter, my Lord. MR JUSTICE AKENHEAD: So is this right: can you say whether the corrosion in the basement is attributable to some bad workmanship or not? A. I cannot, my Lord. MR TURNER: If you cannot say what has caused the ingress or presence of water on the pipes that has led to the corrosion in the basement, does it follow from that that you cannot say that it is the absence of the double vapour barrier that was critical? A. I can say that a double vapour barrier wasn't applied. I cannot say that the absence of the second vapour barrier was the cause of the corrosion.”
“32. I conclude therefore that on the pleaded facts there is a concurrent duty of care owed by Southern to How to exercise reasonable care and skill in carrying out the insulation works which it was contractually engaged by How to execute. The scope of the duty is such as to enable How to recover from Southern as damages the losses which it is liable to pay McAlpine and to Linklaters in relation to the reasonable costs of putting right negligently executed insulation work carried out by Southern.”
“If I buy a second-hand car to which there has been fitted a pneumatic tyre which, as a result of carelessness in manufacture, is dangerously defective and which boasts, causing injury to me or the car, no doubt the negligent manufacturer is liable in tort on the ordinary application of Donoghue v Stevenson…”
“Since all but the very simplest of machines have component parts, [a contrary] holding would require a finding of ‘property damage’ in virtually every case where a product damages itself. Such a holding would eliminate the distinction between warranty and strict product liability.”
“57. Damages for breach of contract are a compensation to the claimant for the loss of his bargain: McGregor onDamages, 17th ed, (2003), para 2-002. He is entitled to be placed, as far as money can do it, in the position which he would have occupied if the contract had been performed: Sally Wertheim v Chicoutini Pulp Co[1911] AC 301 , 307, per Lord Atkinson.”
“The quantum of damage is a question of fact, and the only guidance the law can give is to lay down general principles which afford at times but scanty assistance in dealing with particular cases ... Subject to these observations I think that there are certain broad principles which are quite well settled. The first is that, as far as possible, he who has proved a breach of a bargain to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed. The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach; but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach ...”
“...the learned editors of HUDSON'S BUILDING AND ENGINEERING CONTRACTS (8th edn, 1959) say, at p. 319, that there are in fact three possible bases of assessing damages, namely, (a) the cost of reinstatement; (b) the difference in cost to the builder of the actual work done and work specified; or (c) the diminution in value of the work due to the breach of contract. They go on (ibid.): "There is no doubt that wherever it is reasonable for the employer to insist upon re-instatement the courts will treat the cost of re-instatement as the measure of damage." In the present case it could not be disputed that it was reasonable for the employers to insist on re-instatement and in these circumstances it necessarily follows that on the question of damage the trial judge arrived at the right conclusion.”
“Where the sufferer from a breach of contract finds himself in consequence of the breach placed in a position of embarrassment the measures which you may be driven to adopt in order to extricate himself ought not to be weighed in nice scales at the instance of the party whose breach of contract has occasioned the difficulty. It is often easy after an emergency has passed to criticise the steps which have been taken to meet it, but such criticism does not come well from those who have themselves created the emergency. The law is satisfied if the party placed in a difficult situation by reason of the breach of the duty owed to him had acted reasonably in the adoption of remedial measures, and he will not be held disentitled to recover the cost of such measures merely because the party in breach can suggest that other measures less burdensome to him might have been taken.”
“Next, chronologically, is a decision of the High Court of Australia. In Bellgrove v Eldridge(1954) 90 CLR 613 the builder built a house with defective foundations, as a result of which the house was unstable. The building owner brought an action against the builder claiming the cost of reinstatement. His claim was upheld on the facts. But the statement of principle is instructive. Having said that the building owner is, as a general rule, entitled to have a building which conforms with the contract plans, the High Court continued (at 618-619): 'The qualification, however, to which this rule is subject, is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute "economic waste" ... We prefer, however, to think that the building owner's right to undertake remedial works at the expense of a builder is not subject to any limit other than is to be found in the expressions "necessary" and "reasonable", for the expression "economic waste" appears to us to go too far and would deny to a building owner the right to demolish a structure which, though satisfactory as a structure of a particular type, is quite different in character from that called for by the contract. Many examples may, of course, be given of remedial work, which though necessary to produce conformity would not constitute a reasonable method of dealing with the situation and in such cases the true measure of the building owner's loss will be the diminution in value, if any, produced by the departure from the plans and specifications or by the defective workmanship or materials. As to what remedial work is both "necessary" and "reasonable" in any particular case is a question of fact." Once again one finds the court emphasising the central importance of reasonableness in selecting the appropriate measure of damages. If reinstatement is not the reasonable way of dealing with the situation, then diminution in value, if any, is the true measure of the plaintiff's loss. If there is no diminution in value, the plaintiff has suffered no loss. His damages will be nominal.”
“...in the case of a building contract, the prima facie rule is cost of cure, i.e., the cost of remedying the defect: East Ham Corporation v. Bernard Sunley & Sons Ltd. ([1965] 3 All ER 619 ,[1966] AC 406 ). But where the cost of remedying the defects involves expense out of all proportion to the benefit which could accrue from it, the court is entitled to adopt the alternative measure of difference of the value of the works ...”
“It seems to me that in the light of these authorities - and many other authorities cited were to the same effect, including CR Taylor (Wholesale) Ltd v Hepworths Ltd[1977] 2 All ER 784 ,[1977] 1 WLR 659 , Minscombe Properties Ltd v Sir Alfred McAlpine & Sons Ltd (1986) 2 Const LJ 303 and leading textbooks both here and in the United States—Mr McGuire QC was right when he submitted, and Dillon LJ was right when he held, that mitigation is not the only area in which the concept of reasonableness has an impact on the law of damages.”
“In my view, the reason why Vala should not be entitled to recover can be put very simply on the basis that the assumption that Vala and its experts made that damage had been caused to a comprehensive waterproofing system was not reasonable, and it was thus not reasonable to replace what was there with such a system. That being the simple answer it is not really necessary to explore the situation that the judge had in mind on the basis that the assumption that there was a comprehensive waterproof system prior to the flood, was reasonable. But since some argument was addressed to us on this aspect I would simply put the matter in the following way. If there has been an escape of water that causes some physical damage then prime facie it is only the cost of reinstatement of that physical damage which is recoverable. If a plaintiff is to recover damages for something beyond the cost of reinstatement of physical damage then he must on any view show that it was reasonable to incur expenditure beyond that quantifiable figure. It might in certain circumstances be reasonable to assume that physical damage had been incurred where a full investigation of the same was not reasonably possible. It would certainly be appropriate that a plaintiff should recover the reasonable costs of investigating the damage inflicted. During argument for example, the question arose as to what would be the situation if a plaintiff was advised that certain wiring hidden in the wall might have been damaged. If the advice was that it was impossible to check the accuracy or otherwise of that advice then the cost of putting in fresh wiring might well be recoverable. What should be emphasised is that it must be rare if ever that a plaintiff will be able to establish the reasonableness of any assumption of damage to something which is accessible and inspectable. Certainly, simple reliance by a plaintiff on an expert cannot be the test as to whether a plaintiff has acted reasonably in making an assumption, albeit, provided the plaintiff has provided the expert with all material facts and the expert has made all reasonable investigations, the advice will be a highly significant factor.”
“13. We have seen no conclusive evidence that identifies the leak site on the pipe surface. We do not believe external corrosion could have been the sole cause of the leak and it is possible that the leak was not associated with corrosion at all. 14. If the leak was through the pipe we believe this was the result of an existing internal pipe defect of manufacturing origin, for example at a seam weld, in addition to the combined effects of internal and external corrosion. 15. It is also possible that the leak was the result of a malfunctioning Victaulic coupling joint. External and/or internal corrosion may have contributed to such a leak but it could have resulted from other causes such as deterioration of the elastomeric sealing material or possibly leaking valves.”
“to manage the Building and to provide or procure all the provision of the Services and in particular grants to [Linklaters] the right to enter on and remain on any part of the Building (whether or not the relevant part of the Building is subject to the terms of any leads…) to comply with its obligations to provide the Services in accordance with the terms of this Agreement.” (c) Clause 3.1 provided: “During the currency of this Agreement [Linklaters agrees] to provide the Services in a proper and businesslike manner to assure attainment of the highest possible standards in accordance with the principles of good estate management.” (d) Clause 4.5 required the landlord: “To provide to [Linklaters] (in common with the Landlord) the control of and to make available to [Linklaters] (for the provision of the Services on a day-to-day basis): (a) the Common parts; (b) the Landlord’s plant rooms; (c) other appropriate parts of the Building (including the roof).”
“The Contractor has had an opportunity of inspecting the physical conditions of the site and shall have fully acquainted himself with the same and shall have obtained all necessary information as to risks, contingencies and all other circumstances which may influence or affect the execution of the Works. No failure on the part of the Contractor to discover or foresee any such condition, risk, contingency or circumstance, whether the same ought reasonably to have been discovered or foreseen or not, shall entitle the Contractor to an addition to the Contract Sum or to an extension of time. The contractor shall not and shall not be entitled to rely upon any survey, report or other document prepared by or on behalf of the Employer regarding any such matter as is referred to in this clause 2A.1 and the Employer makes no representation or warranty as to the accuracy or completeness of any such survey, report or other document or for any representation or statement contained therein, whether made negligently or otherwise.” (d) Clause 2.15 stated: "If the Contractor becomes aware of…any other discrepancy or divergence in or between any of the following documents, namely: .1 the Contract Drawings; .2 the Specification/Work Schedules… he shall immediately give written notice with appropriate details to the Architect…who shall issue instructions in that regard.” (e) Clause 4.1 was in the following terms: “The quality and quantity of the work included in the Contract shall, in so far as quantities are not contained in the Specification/Work Schedules, be deemed to be that set out in the Contract Documents taken together, provided that if work stated or shown on the Contract Drawings is inconsistent with the description (if any) of that work in the Specification/Work Schedules then that which is stated or shown on the Contract Drawings shall be deemed to prevail…” (f) Clause 5 addressed Variations for which, if instructed by the Architect, the Contractor was entitled to payment. The definition in Clause 5.1 is a relatively standard one: “The term ‘Variation’ means: .1 the alteration or modification of the design, quality or quantity of the Works including: .1 the addition, omission or substitution of any work…” .1 the addition, omission or substitution of any work…”
“Defective chilled water pipework: Linklaters…agree for purposes of all future rent reviews of leases of any parts of One Silk Street and/or Milton House that the defects in the chilled water pipework identified in the course of Lease 2 and 5 rent reviews had been remedied as at20 December 2006 . This is subject to [the landlord] contributing towards the remediation costs the sum of£200,000 (exclusive of VAT) and making the payment referred to in paragraph 4. [The landlord] shall against the provision of a proper tax invoice therefore, pay an amount equal to the sums referred to in this paragraph and paragraph 4 plus VAT to Linklaters…”
“So in return for having our ability to introduce the disrepair in any future reviews, sort of an agreement was reached. I'm afraid it may not have been particularly scientific. Looking at it now, it may seem as if it was put together in that way, but that is how it was negotiated, and nothing more than that, actually.”
“Frequently a claimant will have taken the required steps in mitigation and thereby have avoided such part of the loss as was avoidable. No difficulty arises in such circumstances. But the claimant may have gone further and by sound action have avoided more consequences than the dictates of the law required of him. In such circumstances the position has been definitively stated by Viscount Haldane LC in the leading case of British Westinghouse Co v Underground Ry. He put the rule thus ‘When in the course of his business he [the plaintiff] has taken action arising out of the transaction, which action has diminished his loss, the effect in actual diminution of the loss he has suffered may be taken into account even though there was no duty on him to act’ …He emphasised, however, that the subsequent transaction, if to be taken into account, must be one arising out of the consequences of the breach and in the ordinary course of business.”
“72. In my judgment, despite the submissions of Mr Cross on this issue, it would be wholly inappropriate to make any such deduction. In the first place, I consider that it would be wrong to make any such deduction in light of the wholesome principle identified by Lord Reid in Parry v Cleaver[1970] AC 1 at 14, where he said: "It would be revolting to the ordinary man's sense of justice, and therefore contrary to public policy, that the sufferer should have his damages reduced so that he would gain nothing from the benevolence of his friends or relations or of the public at large and that the only gainer would be the wrongdoer." 73. More recently, that principle appears to have been approved and applied by the House of Lords in Hunt v Severs[1994] 2 AC 350 . 75. It is suggested on behalf of the defendants that this principle is limited to personal injury claims. Although it is true that the cases in which the principle has been considered and applied involve claims for personal injury, I can see no reason, in logic or policy, as to why the principle should be limited to personal injury claims. On the contrary. In essence, it seems to me that the principle can be said to be based on the proposition that the gratuitous payment of money by third parties to the claimant is res inter alios acta, as between the claimants and the defendants. There is no reason why payments made to the claimant by third parties, particularly when those payments are made out of natural love and affection for the claimant, should be credited to the benefit of the person whose negligence has harmed the claimant, and to the disadvantage of the claimant. Indeed, it would seem almost absurd if that were the law.”
“14. The agreement said nothing expressly about whether Fluor was obliged to carry on litigation against PJ Pipe in the absence of a joint decision not to do so, nor did it deal expressly with what was to happen with the first£500,000 , taking that as the figure up to twice the guaranteed minimum payment of any recovery from PJ Pipe. In my judgment that is because the underlying premise of the settlement agreement was that Fluor would continue to be under an obligation, in the absence of a joint decision not to proceed, to carry on litigation against PJ Pipe and that the recoveries from such litigation would continue to go to Mobil, subject to the express term that a recovery over twice the guaranteed payment allowed was to be split 50/50. It was also, in my judgment, the implicit premise of this whole agreement that, pending resolution of the prospective litigation against PJ Pipe, Fluor remained liable to Mobil and that it was in part that liability which might be the subject matter of Fluor's claim against PJ Pipe. This settlement agreement varied but did not entirely supersede the main contract in relation to the problem of the defective valves. Although the agreement was "in full and final settlement" of inter alia any claim against Fluor, that did not mean that the agreement itself did not mean that the agreement itself did not mention a liability of Fluor to Mobil subject to its own terms.”
“In my judgment these are standard and classical principles arising in the context of mitigation. Everything that the learned editors of Chitty in those passages say, everything that Viscount Haldane was talking about in British Westinghouse relate to the context of the rule of mitigation and steps arising out of attempts to mitigate. Of course, in this matter of mitigation an innocent party may either fall behind his obligation or may meet his obligation or may go much further than his obligation. If he falls behind his obligation, then he cannot complain of the loss caused by his unreasonable conduct. Mitigation, although not being the same as causation, is a very closely allied concept. If he meets his obligation of mitigation, then the consequences of his so acting have to be brought into account for good or ill. But if in his attempts to mitigate he even goes beyond his obligation, the position remains the same: he is entitled to bring his loss into account but must give credit for any benefit. If one considers how closely allied the concept of mitigation is with that of causation, one can understand why that is so. As a result of a breach of contract a party is obliged to mitigate. In his attempts to mitigate he may go beyond his obligation, but that is his reaction to the problem caused by the breach and the consequences of the rules of mitigation follow. It is quite different if the transaction, which is relied upon as avoiding loss, is an entirely independent and collateral matter arising not in the context of mitigation at all.”