“[The Claimant] was entitled to receive a Property which was properly designed and constructed, with a certain future in the sense that it was not so uncertain that it still needed to be monitored and investigated many years after completion; which had a normal appearance and performance, not with cracks and other defects; which had a normal value to ordinary residential purchasers; which was safe and convenient to occupy without external peculiarities and which was ready to occupy without inconvenience, distress and loss of amenity. The respective experts have agreed that the house should have a design life of 60 years ….”
“In respect of an award of damages for defective premises: (1) In an action against a contractor for defective work, the appropriate measure of loss is generally taken to be the cost of reinstatement/repair, because that is the foreseeable consequence of the defective work. (2) The cost of reinstatement/repair will not be used as the measure of loss if such cost is disproportionate to the end to be attained. (3) A claimant who carries out either the repair or reinstatement of his property must act reasonably. (4) The court is unlikely to adopt demolition and rebuilding as the correct measure unless two conditions are satisfied: first, the cost of demolition and rebuilding is less than the cost of remediation, and secondly, that remedying the defects represents a reasonable course of action, so that “the amount awarded is objectively fair as between the claimants and the defendants” [Hudson, [7-006]]. (5) If there are two equally efficacious alternative remedial schemes, and one is cheaper than the other, then prima facie the claimant is obliged to put in hand the cheaper of the two schemes. (6) As regards betterment, if a claimant chooses to rebuild to a higher standard than is strictly necessary, it can recover the cost of the works less a credit for betterment.”
“It is, on any view an extreme course: to knock down a newly completed building because it is said to be defective, particularly where the majority of the defects can fairly be described as aesthetic matters only. … If such a course of action is to be justified at all, it will ordinarily be because the building is dangerous or structurally unsound.”
“For the multitude of reasons explained by Mr Dust, (including the lack of construction information), the appropriate remedial scheme will be demolition and reconstruction; this is the only certain way for [the Claimant] to receive what he contracted for – what he would have received had [the Defendant] not breached the Contract and/or had it complied with s.1, DPA [1977]. Damages should reflect this.”
“The work for [Scheme 3] would oversail the existing trench foundations and would all be carried out by working within the existing external walls, which would remain in place. The external walls would be re-supported on a new steel bar reinforced concrete slab with fingers cut into the external wall line around the perimeter such that the new slab can be cast, and would resupport the external walls in the long term, i.e. the external walls would be ‘pinned up’ such that they are supported on the new reinforced concrete piled raft. Any connection with the existing mass concrete foundations would be removed by carefully breaking out the original concrete walling blocks beneath the piled raft slab by an amount sufficient to ensure that there are no long-term effects due to clay ‘heave’ or swelling. A gap of circa 75-100mm is all that is likely to be needed. These works could very easily be carried out in sequence, working around the building externally. Thus, the existing substructure and mass concrete foundations would remain in place for at least as long as the life of the building. The line of the load bearing walls at ground floor can then be reinstated, supported on the new piled raft slab, and the temporary support removed.”
“[6.2.2] In general, the extent of construction distortion, damage and fracturing to the buildings and external works including construction damage and fractures is slight or moderate damage. However, there is serious and/or severe damage affecting the main entrance front porch and the associated front porch masonry piers. … [6.2.3] Parts of the Property are unsafe, and without works to make safe, are defects that in my opinion render the Property as not fit for human habitation, these include: The front entrance porch, and the … Public Footpath. …” (Emphasis added.)
“From my point of view it demonstrates what I was seeking to identify – the potential maximum displacement.”