"… all or almost all of the structural damage which is the subject-matter of the plaintiffs' claim had occurred as a result of the 1989 drought not later than March 1990. If, which is not certain, some further cracking took place in the superstructure after that date, that cracking in my judgment was the further consequence of the 1989 to early 1990 damage to the foundations."
"… by cutting a trench approximately 300mm wide and 1 metre deep along the back edge of the pavement, and then back-filling the trench with a PVC liner to reduce re-growth. It was also made clear by the plaintiffs at this meeting that the underpinning works proposed by CSP would nevertheless have to proceed and, as part of those works, a further trench would be cut at basement level. It was not and never has been admitted by Westminster that the structural damage described by CSP had in fact been caused by tree roots."
"In October 1991 root pruning was carried out and a pavement-level root barrier inserted as previously agreed by Westminster. But the plaintiffs adhered to the advice of CSP, and occupiers of some of the basement flats began to move out to enable CSP's programme of underpinning works to be carried out. This work stated in January 1992. On6 March 1992 and again on9 April 1992 the contractors found tree roots beneath the foundations to blocks 10 and 11. These findings powerfully corroborate the evidence of tree roots and desiccation put forward by Mr Quarrell, and they necessitated the insertion of piles instead of underpinning in the locations affected. The work was completed in July 1992 at a total cost to the plaintiffs (including the removal costs of the leaseholders) of£570,734.98 . Westminster agree that this sum was in fact incurred, and that it was a fair and reasonable sum for the works which were actually carried out and for the other heads of expenditure which were in fact incurred. Mr Butcher however stated that in his opinion the scope and extent of the works was excessive if and insofar as they were brought about by the roots of this tree. He could accept that structural works to the stairwells to blocks 10 and 11 were justified. He challenged the need to extend those works beyond those areas, suggesting that the additional work which he was unable to accept was carried out for the sake of protecting the building against possible future damage rather than repairing the damage which had occurred up to that date. Mr Cairns explained to me that this was a matter of professional judgement. He agreed that a line had to be drawn somewhere, and in cross-examination Mr Butcher accepted that Mr Cairns' scheme was a reasonable one, even though he did not agree with it. In my judgment the costs incurred by the plaintiffs were properly and reasonably incurred and, if a legal cause of action can be established, would be recoverable from Westminster."
"22. Thus where there is a continuing nuisance, the owner is entitled to a declaration, to abate the nuisance, to damages for physical injury and to an injunction. He is in my judgment, and on the same principle, entitled to the reasonable cost of eliminating the nuisance if it is reasonable to eliminate it. This does not offend against Lord Lloyd's formulation in Hunter which was not intended to define the remedies of an owner subject to a nuisance by encroachment. 23. A nuisance is present during the second appellants' ownership; acceptance of the need for remedial work establishes that. The actual and relevant damage is the cost of the necessary and reasonable remedial work. Underpinning has been held to be a reasonable way of eliminating the nuisance and the owner can recover the cost of doing it. There is no need to prove further physical damage resulting from the nuisance."
"Where there is a continuing nuisance inflicting damage upon premises those who are in possession of the interest may recover losses which they have borne whether the loss began before the acquisition of the interest, or whether it began after the acquisition of the interest. The test is: what is the loss which the owner of the land has to meet in respect of the continuing nuisance affecting his land?"
"In my view there is no reason to suppose that many of the houses in Shirley Avenue could be eliminated from this risk. We were told that there is an avenue of trees all along that road and the evidence was that pockets of clay might exist anywhere in Shirley Avenue. All the householders, it seems to me, would have to be approached, not only in Shirley Avenue but in any other street in Hampshire where there are trees adjacent to houses."
"Abatement is a privilege, not a duty. An ancient ruling has it that it 'destroys any right of action in respect of the nuisance'. But as now interpreted, it means no more than that the act of abatement has the effect of removing the nuisance so that the claimant is not entitled to future damages. He may, however, recover damages for past injury. And although some dicta assume that the cost of removing the nuisance is also irrecoverable, it has been held that this does not preclude reimbursement for the cost of mitigating future damage"
"In a case such as this, as a general rule, I think it is highly desirable that persons in the position of the defendants be given notice of this kind, and thus have a fair opportunity to abate the nuisance themselves before large sums of money are spent on such works as building barrier walls."
"Also, in addition to the depreciation measure of damages, the plaintiff in a nuisance case may recover the reasonable cost of his own efforts to abate the nuisance or prevent future injury. For example, where a sewer line backed up and overflowed into the plaintiff's theater, the plaintiff hired a contractor to re-lay lateral sewer lines to avoid the problem in the future, and the contractor's charges being reasonable, the plaintiff was allowed to recover them. Such decisions seem correct, though it should also be noted that to the extent the plaintiff is in fact able to abate the nuisance by his own efforts, or to the extent it is abatable by injunction, permanent damages are not assessed."