“Any liability that the First Defendant may have to the Claimants undersection 1 of the Defective Premises Act 1972 or as a result of a building safety risk is also the joint and several liability of each of the [BLO Defendants].”
“In my view the evidence relied upon by Mr Perry and his identification of noncompliance with the Employer’s Requirements and Statutory Requirements is compelling. Although I acknowledge that the extent of non-conformance and remedial works required to address the fire safety defects are in issue, there is no doubt in my mind that the extent of combustible materials installed and the evidence of defective fire barriers/stopping is such to render Ardmore in breach of Contract. I also agree with and accept Mr Perry’s evidence that the extent of the fire safety defects in the external walls is such to render certain dwellings unfit for habitation. It therefore also follows that Ardmore is in breach of its duty owed to CNR and/or CNO pursuant to Section 1(1)(a) of the DPA. Accordingly, I find that Ardmore is in breach of the Contract and Section 1(1) of the DPA as a result of the fire safety defects in the external walls of the Development. [original emphasis]”
“[ACL] has been working towards mitigating the issues arising and has undertaken a significant amount of remedial work to date, spending in excess of£100 million and had agreed with its principal insurers to pay£75million towards these costs. All of these funds have been expended on making good the defects. In December 2024, the Court issued Judgment in the landmark case of BDW Trading Limited -v- Ardmore Construction Limited[2024] EWHC 3235 . The case revolved around fire safety defects on a particular development that achieved practical completion between 2003 and 2004. Prior to this Judgment, the Company had received and sought to defend all incoming claims and spent huge sums of money on a variety of lawyers in furtherance of this purpose. In February 2025 alone, the Company spent£687,440 . Into the first quarter of 2025 and as a result of the Judgment, the Director and senior Company employees sought advice from solicitors and restructuring professionals. This resulted initially in advice that the Company should consider a restructuring plan but with the process of administration in reserve. They also concluded that expending further sums on defence of claims under BSA22 in the first instance was no longer commercially viable and took steps to withdraw from further engagement. It continued to defend actions which were believed cost effective to do so to mitigate the potential creditor exposure and had also undertaken some work to pursue recovery claims and opportunities. The Company sought to maximise realisations in the interim and with significant projects reaching practical completion which would allow the release of bonds being completed and debtor and retention monies to be undisputed, other projects were novated to other companies within the group (in addition to the associated liabilities) and the Company proceeded to wind down operations. A restructuring plan was considered but ultimately aborted. The Company continued trading for a short time but ultimately was running out of cash to discharge liabilities and with many court deadlines looming, sought to deal with procedural documents in house to save on costs or otherwise which it could no longer engage with. At the same time, the Company was suffering cash depletion and consequently only business critical costs only were being met, with no short term funding or recovery imminent. Ultimately, on27 August 2025 it was sent a threat of winding up petition by a retention creditor with a deadline of midnight to pay the sums due. The following day, the Director concluded that time had run out and provided instructions to proceed with the appointment of administrators resulting in the Company’s entry into Administration on28 August 2025 .”
“130 Building liability orders (1) The High Court may make a building liability order if it considers it just and equitable to do so. (2) A “building liability order” is an order providing that any relevant liability (or any relevant liability of a specified description) of a body corporate (“the original body”) relating to a specified building is also— (a) a liability of a specified body corporate, or (b) a joint and several liability of two or more specified bodies corporate. (3) In this section “relevant liability” means a liability (whether arising before or after commencement) that is incurred— (a) under theDefective Premises Act 1972 orsection 38 of the Building Act 1984 , or (b) as a result of a building safety risk. (4) A body corporate may be specified only if it is, or has at any time in the relevant period been, associated with the original body. (5) A building liability order— (a) may be made in respect of a liability of a body corporate that has been dissolved (including where dissolution occurred before commencement); (b) continues to have effect even if the body corporate is dissolved after the making of the order. (6) In this section— “associate”: see section 131; “building safety risk”, in relation to a building, means a risk to the safety of people in or about the building arising from the spread of fire or structural failure; “commencement” means the time this section comes into force; “the relevant period” means the period— (a) beginning with the beginning of the carrying out of the works in relation to which the relevant liability was incurred, and (b) ending with the making of the order; “specified” means specified in the building liability order.”
“Beyond stating the obvious, that the power is discretionary and should therefore be exercised having regard to the purpose of the 2022 Act and all relevant factors, it is not possible to identify a particular approach which should be taken.”
“The obvious purpose behind the association provisions is to ensure that where a development has been carried out by a thinly capitalized or insolvent development company, a wealthy parent company or other wealthy entity which is caught by the association provisions cannot evade responsibility for meeting the cost of remedying the relevant defects by hiding behind the separate personality of the development company. It seems to us that the situation of SVDP, with its relatively precarious financial position and its dependence for financial support upon Get Living, its wealthy parent, constitutes precisely the sort of circumstances at which these association provisions are targeted.”
“The increase in value of Get Living’s investment in East Village is not a matter to which we give great weight, although to the extent that it is relevant at all it is obviously a point in favour of making an order. It is common ground that Get Living has the resources to enable it to comply with any order the tribunal may make, but even if there had been doubt about that we think it would be an unusual case in which the source or extent of a respondent’s assets or liabilities will carry much weight when deciding whether it is just and equitable to order it to bear the cost of remediation.”
“the FTT were right that it was not necessary for them to resolve any issues as to Triathlon’s motivation. In general parties who have legal rights or remedies are entitled to pursue them without having to explain why they have decided to do so, and a litigant’s subjective reasons for litigating (save in the unusual case where a litigant is acting out of malice or the like) are usually irrelevant to the merits of its claim. What may be relevant is whether an applicant has a legitimate interest in pursuing an application, but here I do not think there is any difficulty.”
“this is I think to take too narrow a view of the statutory purposes of the Act. I accept that one of those purposes is to ensure that works that are required are actually done. But another purpose is to deal with the ‘who pays’ question, and as set out above, the Act provides a complex set of answers to this question with a number of facets.”
“Those who can be required to contribute by means of an RCO include (by section 124(3)(d)) associates of the developer (or of a landlord), and the effect of section 121(5)(a) is that a body corporate is associated with another body corporate if at any time in the relevant period (the 5 years before the qualifying time of14 February 2022 ) a person was a director of both of them. Suppose a case where a director of a landlord was also a director of other companies which have no other connection with the landlord or its group; such companies might have had nothing to do with the development and be engaged in entirely different businesses, or might include a charitable company to which the director had given his time voluntarily. It is not obvious that it would always be just and equitable to make RCOs against such associated companies even if the effect of refusing to do so was to leave the costs to be borne by the public. …”
“A central goal of the legislation is to seek to ensure that safety risks in multi-occupied residential buildings resulting from historical building defects are remedied by those who were responsible for the defects in the first place, and without the leaseholders having to bear the (potentially very large) costs. To achieve that goal, Parliament has decided to enable claims to be brought against property developers, contractors and others responsible for the construction of unsafe residential buildings even when the construction work was completed many years ago.”
“In his oral submissions in reply Mr Warwick invited me to provide some guidance, whatever the outcome of the Appeal, as to how the FTT should approach the just and equitable question. The invitation was extended in good faith, but I do not think that it is one to which I can or should accede. I do not think that it is either possible or sensible to seek to catalogue the factors upon which the FTT may rely in determining, in any particular case, whether it is just and equitable to make the order sought against any particular respondent. I say this essentially for two reasons. First, the breadth of the discretion conferred upon the FTT, namely whether the FTT “considers it just and equitable” to make the order sought, is very wide. The factors which may be taken into account in any particular case are not limited by the terms of Section 124(1) and are not, in my view, capable of exhaustive classification. Second, and if I was to attempt this task, it seems to me that I would be at risk of committing the basic error of attempting to re-write Section 124(1). In Section 124(1) Parliament has chosen not to list or limit the factors which can be taken into account in the exercise of the just and equitable discretion. In these circumstances it is not appropriate for me to attempt to do so.”
“A primary purpose of the jurisdiction in Section 124 is to ensure that a wealthy parent company or other wealthy entity which is caught by the association provisions cannot evade responsibility for meeting the cost of remedying the relevant defects by hiding behind the separate personality of the development company.”
“I cannot, however, see anything that requires me to quantify the liability in respect of the relevant liabilities as set out in my judgment at the point of making the Building Liability Order. That is particularly relevant here because of the potential issues in identifying what losses, beyond the cost of remedial works, flow from the relevant liability and not the water ingress. It may in future often be the case that such a Building Liability Order will be made in terms of liability for an amount, particularly if, as here, the order is being made following a trial which has identified the extent of the liability in monetary terms. But it does not seem to me that I am required to do that and to make an order in an amount. At present, there are no figures before me which would enable me to do so, or at least to do so without considerable further interrogation of the spreadsheets that have been produced for the purposes of this hearing. That is not a reason not to make the order in terms that reflect the wording of section 130.”
“17. As a matter of principle, it seems to me that the legislation does not require a party against whom a Building Liability Order is sought to be made a party to what I would call the main claim or to participate in those proceedings. That is because, for example, the company against whom the order is sought may be one that does not even exist at the time of the proceedings, or because the circumstances in which the order is sought are not even in contemplation at the time of those proceedings. However, if the making of an application for a Building Liability Order is contemplated, it will generally be sensible and efficient for the company against whom that order is going to be sought to be made a party to the litigation and for that application to be heard together with the main claim, although, as I indicated during the course of this hearing, that does not and would not in any way bind a judge to determine that application as part of the main claim and leave it open to the judge as a matter of case management to direct a further hearing in that respect.”
“13. Certain features of a building liability order may be noted. First, it concerns a relevant liability ‘relating to a specified building’: section 130(2). A building liability order cannot make associated companies liable for the entire liability of the original body to the applicant across a number of developments. The court can, of course, make any number of individual building liability orders in respect of the relevant liabilities of one original body, but each such order will be discrete. Second, the precise and in that sense carefully confined definition of ‘associate’ is nevertheless relatively extensive on account of the definition of ‘the relevant period’. 14. Third, I can see nothing in section 130 that makes it a precondition to the making of a building liability order that the relevant liability of the original body shall already have been established. Recent decisions of Jefford J illustrate that applications for such orders may be made before the trial of the original body's liability, that such applications may proceed in tandem with the litigation against the original body, and that it may in a given case be convenient to defer consideration of an application for a building liability order until after the trial against the original body; see Willmott Dixon Construction Ltd v Prater[2024] EWHC 1190 (TCC) , 214 ConLR 164; 381 Southwark Park Road RTM Company Limited v Click St. Andrews Limited[2024] EWHC 3179 (TCC) . However, I do not read any of the Judge’s observations in those cases, made in specific factual contexts, as meaning that a building liability order cannot be made before the existence of a liability of the original body is established. If they did have such a meaning, I would respectfully be of a different opinion, for the following reasons. (1) There are many simple and obvious ways in which such a condition could have been expressed, but it was not. (2) It is unnecessary to imply such a condition. (3) It makes perfectly good sense to allow a building liability order to function as what might be termed an indemnity (‘If this original body has any relevant liability in respect of this specified building, this associate shall also have that liability’). In a given case, it may be very convenient to know in advance that an associate will be liable, if the original body's liability is subsequently established, so that the associate knows where it stands when it seeks to defend the substantive allegations. (4) The use of the word “any” in section 130(2), rather than merely “a”, suggests that an indemnity is permissible. Especially in view of the definition of “relevant liability”, “a” would have done very well to refer to an established liability. (5) The use of the word “is” (“…specified building is also… ”), rather than “shall also be”, is not a significant contraindication, in view of (a) the use of “any”, (b) the fact that a liability may be said to be extant though it is (falsely) disputed and not yet established by judicial determination, and (c) the next reason. (6) Subsection (5) makes clear that a building liability order can be made even if the original body has been dissolved. This clearly envisages that the original body does not have to be restored to the register if it were restored, mention of its dissolution would be pointless. There is nothing to suggest that the original body must have had liability established against it before its dissolution, and in view of the circumstances in which the Act was passed (the appreciation, after Grenfell, that many buildings had serious but hitherto latent safety issues) and the extended limitation periods provided for in section 135 of the Act (15 or 30 years), section 130 is clearly designed to catch the situation where the original body has passed into history and either could not be restored to the register or, if it were restored, would be a mere empty shell. (7) The example of a building liability order in the Explanatory Notes supports this construction. For reasons mentioned below, any reliance on such an example can only be cautious, because the example of an information order is badly flawed. But in this case the example is consistent both with the wording of section 130 and with good sense. Of course, the construction here advanced does not at all mean that a building liability order cannot be made after liability has been established against the original body, only that it is not available only in such circumstances.”
“We are also introducing an ambitious toolkit of measures to allow those directly responsible for defective work to be pursued. Those measures include … provisions removing the protections afforded by special purpose vehicles and shell companies…”
“…A practice used in property development is where a subsidiary company (which may be thinly capitalised) is set up to own and manage a development on behalf of the corporate group it is a part of. The subsidiary is often wound up once the development has been completed … Building liability orders have been designed to address the consequence described above …”
“The freeholder applies to the High Court for a building liability order to be applied to the parent company. The freeholder must show that the parent company is associated with the development company. The High Court must consider whether it is just and equitable to grant the building liability order, for example whether the parent company can receive a fair trial. In this example, the request for a building liability order is granted. The freeholder can now make a claim under the Defective Premises Act against the parent company. The court proceedings would then proceed as normal.”
“The court would ordinarily expect that, if issues are to be dealt with by way of a PI hearing, there would be either no or relatively limited oral evidence. If extensive oral evidence was required on any proposed PI, then it may not be suitable for a PI hearing.”
“Crest is not a ‘truly innocent’ party. Crest was (or ought) itself to have been a knowledgeable developer, which owed its own duties and obligations to PNBC, including a duty under section 1 of the DPA. Crest engaged consultants, including Wintech, to review, inspect and approve the design and the Works. It is likely that Wintech and other consultants would have provided reports to Crest. Crest is required to prove, and disclose documents showing, its involvement in and/or knowledge of the elements of the design which it now alleges are defective during the Works.”
“Section 130 is engaged where a body corporate has a relevant liability, of a kind described in Section 130(3). That liability can then be made transmissible from the original body to a specified body corporate, or it can be made transmissible as the joint and several liability of two or more specified bodies corporate. The transmission of liability takes place pursuant to paragraph (a) or paragraph (b) of subsection (2), depending upon whether a building liability order is sought against one specified body corporate or two or more specified bodies corporate, and provided, in each case, that there is the required association with the original body.”
“If any dispute or difference arises under this Contract either Party may refer it to adjudication in accordance with clause 39A.”
“Any dispute which by virtue ofPart II of the Housing Grants, Construction and Regeneration Act 1996 is to be referred to adjudication shall be referred to adjudication in accordance with the Technology and Construction Solicitors Association Adjudication Rules (TeCSA Adjudication Rules) current at the time of reference.”
“A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section.”
‘A person taking on work for or in connection with the provision of a dwelling (whether the dwelling is provided by the erection or by the conversion or enlargement of a building) owes a duty— (a) if the dwelling is provided to the order of any person, to that person; and (b) without prejudice to paragraph (a) above, to every person who acquires an interest (whether legal or equitable) in the dwelling; to see that the work which he takes on is done in a workmanlike or, as the case may be, professional manner, with proper materials and so that as regards that work the dwelling will be fit for habitation when completed.’
‘In my judgment, the parties, by including in the heads of agreement the arbitration clause in the narrow form which it took, demonstrated their intention to refer to arbitration any disputes which might arise regarding the rights and obligations created by or incorporated in the heads of agreement themselves…’
“There are obvious differences between arbitration and adjudication, but they are both types of dispute resolution procedures for which provision is made by a contract between the parties, in which recourse to that procedure is conferred by way of contractual right. I am not persuaded that the statutory compulsion lying behind the conferral of the contractual right to adjudicate points at all towards giving the phrase ‘a dispute arising under the contract’ a narrow meaning, by comparison with a similar phrase in a contract freely negotiated. The fact that, after due consideration of the Latham Report, Parliament considered that construction adjudication was such a good thing that all parties to such contracts should have the right to go to adjudication points if anything in the opposite direction. Indeed, the fact that the right to adjudicate is statutorily guaranteed is a powerful consideration favourable both to its recognition as a matter of construction, and to the caution which the court ought to employ before preventing its exercise by injunction.”
“[12] I do not propose to analyse these and other such cases any further because in my opinion the distinctions which they make reflect no credit upon English commercial law. It may be a great disappointment to the judges who explained so carefully the effects of the various linguistic nuances if they could learn that the draftsman of so widely used a standard form as Shelltime 4 obviously regarded the expressions ‘arising under this charter’ in cl 41(b) and ‘arisen out of this charter’ in cl 41(c)(1)(a)(i) as mutually interchangeable. So I applaud the opinion expressed by Longmore LJ in the Court of Appeal (at [17]) that the time has come to draw a line under the authorities to date and make a fresh start. I think that a fresh start is justified by the developments which have occurred in this branch of the law in recent years and in particular by the adoption of the principle of separability by Parliament in s 7 of the 1996 Act. That section was obviously intended to enable the courts to give effect to the reasonable commercial expectations of the parties about the questions which they intended to be decided by arbitration. But s 7 will not achieve its purpose if the courts adopt an approach to construction which is likely in many cases to defeat those expectations. The approach to construction therefore needs to be re-examined. [13] In my opinion the construction of an arbitration clause should start from the assumption that the parties, as rational businessmen, are likely to have intended any dispute arising out of the relationship into which they have entered or purported to enter to be decided by the same tribunal. The clause should be construed in accordance with this presumption unless the language makes it clear that certain questions were intended to be excluded from the arbitrator’s jurisdiction. As Longmore LJ remarked, at [17]: ‘[i]f any businessman did want to exclude disputes about the validity of a contract, it would be comparatively easy to say so.”
‘The reason is that the words “arising under a contract” have been held by the Court of Appeal’— ‘he quotes the case of Fillite Runcorn Ltd. v. Aqua-Lift in 1992—might be construed “to exclude jurisdiction for such matters as negligent misstatement and misrepresentation.” ‘Arising under a contract' is not an all-encompassing phrase.’
“(3) Unless parliamentary statements are indeed clear and unequivocal (or, as Lord Reid put it in Warner v Metropolitan Police Comr[1968] 2 All ER 356 at 367,[1969] 2 AC 256 at 279, such as ‘would almost certainly settle the matter immediately one way or the other’), the court is likely to be drawn into comparing one statement with another, appraising the meaning and effect of what was said and considering what was left unsaid and why. In the course of such an exercise the court would come uncomfortably close to questioning the proceedings in Parliament contrary to art 9 of the Bill of Rights 1689 and might even violate that important constitutional prohibition.”
“I agree with Edwards-Stuart J that in the context of a single dispute or difference it can often be difficult to divorce any significant flaw in the adjudication from the balance of the decision. Indeed, significant breaches of natural justice are particularly prone to infect and therefore undermine the entire decision. In my judgment, the proper question is not, however, to focus on whether there was a single dispute or difference but upon whether it is clear that there is anything left that can be safely enforced once one disregards that part of the adjudicator’s reasoning that has been found to be obviously flawed. Such analysis need not be detailed and, in many cases, it may remain the position that the entire enforcement application should fail. It would, however, further the statutory aim of supporting the enforcement of adjudication decisions pending final resolution by litigation or arbitration if the TCC were rather more willing to order severance where one can clearly identify a core nucleus of the decision that can be safely enforced.”
“In support of its position regarding the ability of an agent to sue under a contract to recover losses of its undisclosed principal (or of a trustee in respect of a beneficiary), Crest has referred me to Darlington BC v Wiltshier Northern Limited[1995] 1 WLR 68 and Alfred McAlpine Construction Limited v Panatown Limited [2001] 1 A.CX. 518 (HL). Based on these authorities I agree with Crest that, as a matter of principle, CNR is entitled to advance a claim on behalf of CNO for breach of the duty owed by Ardmore under Section 1 (1) (a) of the DPA, and it therefore follows that the fact that CNR may not have actually incurred and/or be incurring the cost of remedial work does not preclude it from recovering losses incurred or to be incurred by CNO as its principal and/or beneficiary. I therefore reject Ardmore’s ‘no loss’ argument in respect of CNR such that, to the extent that CNO is entitled to recover losses against Ardmore pursuant to Section 1 (1) (a) of the DPA, then CNR is entitled to recover those losses on behalf of CNO. However, having found that CNO is entitled to advance a claim for its losses pursuant to Section 1 (1) (a) via adjudication, this may be an academic point as for present purposes it follows that both parties are entitled to recover the losses on a joint and several basis.”
“Adjudication is often about achieving a quicker and cheaper resolution to the parties’ disputes. Where one party regards an adjudicator’s decision as a real miscarriage of justice, it has the right to take the dispute to litigation or arbitration to have that decision effectively overturned; where, as is so often the case, the parties regard the decision as a decent attempt to arrive at a fair resolution of the competing positions, the parties generally treat the decision as binding or negotiate a settlement around it. This is good for the overall administration of justice and no doubt many cases which would otherwise end up in the TCC are resolved without burdening public resources as a result of the practical utility of adjudication, notwithstanding its temporary nature.”