“The TRADA Wood Information Sheet WIS 4-14 of June 2016 referred to a 'Moisture Content Control Plan" or "MCCP''. I had never prepared a MCCP or been instructed by clients, contractors, project managers, construction managers or anyone else in projects to prepare a MCCP for a timber roof or other timber structure. I did not see, on any WTA project, a MCCP being prepared or mentioned by anyone. I refer to other parts of WIS 4-14 below. I do not recall anyone involved in projects referred to in 100 Projects, which were comparable to the Vitsoe project, telling me or anyone else at WTA that a MCCP was prepared by anyone during those projects.”
"Skill and Care all the reasonable skill care and diligence to be expected of a properly qualified and competent architect, design team leader and principal designer experienced in performing duties similar to the Services on projects of a similar size, scope and complexity as the project and, for the purpose of the standard of reasonable skill, care and diligence the degree of competence shall be judged in the light of professional knowledge and standards current at the time the relevant service was provided."
"You shall use Skill and Care to provide the Services to us so that the Services are Fully Co-ordinated with the design and work being carried out by us, other consultants, our trade contractors and sub-contractors and other consultants for the various specialist work packages relevant to (or which be affected by) the Services and by third parties in relation to the Development (such as statutory undertakers or their equivalent)."
“(a) Design. Defendant was foremostly the designer and was under a duty to provide design information. It did so in the form of drawings and both outline and detailed specifications (clauses 1.5 and 3.2 of Schedule 1). However, Hess completed the detailed design of the timber frame and Stoneleigh completed the detailed design of the roof coverings. (b) Co-ordination. Defendant owed a duty to coordinate designs (clause 18.5 of Schedule 1 to the WTA Appointment), but not the programmes of other consultants. Hess and Stoneleigh were not only obliged to co-ordinate with JCA, as Construction Manager, they were also obliged to co-ordinate with other Trade Contractors, i.e. each other (Clause 30). (c) Protection. Defendant did not owe a duty to protect the Trade Works during their construction. Hess and Stoneleigh owed precisely these obligations. Further, both Hess and Stoneleigh were obliged to use reasonable skill and care to satisfy the performance requirements or specifications for the Trade Works, namely the requirements of Defendant's Timber Frame and Combined Specifications, which stipulated performance requirements for protection of works, adverse weather working and membrane work.”
“In breach of contract, the Defendant failed to take reasonable skill and care in the performance of its services in that it: PARTICULARS OF BREACH PARTICULARS OF BREACH 31.1.AFailed to identify when appraising and reporting upon Hess' tender and those of the other contractors, that they contained no, or adequate moisture protection during construction. This was required by the Defendant's own performance specification dated16 March 2016 . The Defendant should have been aware that the erection or a temporary shelter over the works area was the only reliable and effective way of protecting the works during construction (from the moisture content control plan and/or risk assessment referred to in Paragraph 31. 1 above) and should have advised the Claimant that a temporary shelter needed to be provided by one of the works contractors. Further, in the absence of an earlier moisture content control plan/risk assessment the need to properly appraise Hess' tender and those of other contractors should have been a further trigger to produce one. (1) Advised Stoneleigh and/or JCA, and/or the Claimant not to install the VCL in the existing wet conditions. (2) Instructed and/or advised the Claimant and/or JCA that moisture levels of the CLT should be tested in order to determine its moisture content. Had this been done, it would have been identified that some elements would need to dry out before the VCL was applied (thereby locking in any moisture which the CLT had absorbed and that some elements to which the VCL had already been applied had already absorbed an excessive amount of moisture. (3) Instructed and/or advised the Claimant and/or JCA that a raised tarpaulin cover or temporary canopy be constructed over the building (or the incomplete sections of the roof) to permit the CLT to dry out as fully as possible before application of the VCL and then to enable the roof works to be completed in a dry environment. (4) Insofar as any of the above matters were raised by the Defendant it should have followed up with JCA to ensure that they were being carried out and, if not, advised the Claimant that necessary steps to ensure the satisfactory completion of the works were not being undertaken. (1) The CLT consisted of thick sheets which were a composite of wood and adhesive. It was unlikely that water which had entered the upper surface and edges of the timber would dry out through evaporation from the lower surface. (2) Hess was best placed to determine whether the CLT would dry out from the inside and when the Defendant asked Hess whether this would occur (on22 December 2016 ), the Defendant received the negative response summarised in Paragraph 27 above.”
"At no point have seen an MCCP nor been required to prepare such a document. Nor am I aware of any projects upon which such document has been prepared."
"Brief review of concerns arising from prolonged exposure of the timber to the new Vitsoe building in Royal Leamington Spa."
"This is brief high level overview of concerns"? A. Yes. Q.Then he continues -- "
“On16 Nov 2016 , at22:59, Adrian Kenny <ade.mkconstiUction@gmail.com> wrote: Tom, xmas shutdown will be 23rd- 3rd Jan 17 Our working programme will deal ·with the phasing and coordination with other trades.” xmas shutdown will be 23rd- 3rd Jan 17 Our working programme will deal ·with the phasing and coordination with
"Alastair Ogle" <alastair@waughthistleton.com>, "
"Andrew Waugh" <andrew@waughthistleton.com>, "
“ From:Alastair Ogle Subject:Re: Water protection of Vitsoe RLS over Christmas To:Andrew Waugh; Tom Westwood Sent:December 23, 2016 11.30AM (UTC+00:00) I have just received a phone call from Simon at Vitsoe to tell us that his is happy with the protection methods employed by plotform and JCA onsite over the christmas break and that we can stop panicking. Other points raised. -The forecast is looking mild over the christmas period. -The end grain in the parapets will be covered however the windows will not be covered or protected, stating he is happy to allow the air to blow through the building to naturally dry out any timber rather than cover them -The moisture content has been continuously monitored by plotform onsite as is currently at 12% Alastair Ogle Associate”
“Alastair, As already discussed on the phone please understand that we had clarified (back in October) and agreed with JCA that the roofing company needs to install the VCL membrane 1-2 days after we have installed the CLT rood panels partially. We have tried to support JCA by trying to explain the importance of the roof cover. We just tried to get a hold of Clive/ Andy to clarify when the roofing company will cover the roof. So far it is our understanding that JCA was trying to get the roofing company on site up from 27th December. Unfortunately the roofing company left the site today at 11:00 AM. Clive has also taken pictures to proof that the roofing company was not doing the works properly. Regarding the moisture content I think that the torch process for the roof membrane is helping to dry the timber surface. However, it is my opinion that the roofing company should quickly come and apply the roof membrane. As you see we are trying to help as much as we can but HESS and Plotform are not responsible in this matter. I will also call Mark Adams to explain where we are.”
“- the moisture content has been continuously monitored by Plotform on site and is currently at 12%” [T5/862/4] to [T5/863/23]: “THE JUDGE: Go back to page 1668. As I understand it, this was a record of a conversation from Simon Garwood, who was the representative of the claimant, telling Alastair Ogle that the moisture content has been continuously monitored by Plotform on site that is currently at 12%. Do you think there is any reason why WTA should have challenged that information? A. I think if that was delivered to them, I do not know that it needed challenging. It might have been helpful to understand what "continuously monitored" meant and where those measurements had been taken to understand whether it was representative, you know, whether they were taken from panels just laid one day or whether they had been laid for two weeks previously, whether it was in the middle of a panel or near a joint which was vulnerable. I think more information would have been useful to understand what that sentence really meant. Q. So what would you have done if you had received this information from the client and wished the content to be continuously monitored? A. I might have asked to understand what that meant. "Do you have any further information or can Plotform provide some information?" It was a rapidly developing scenario – every time there was rainfall, certain panels were getting wetter depending on where you were in the installation process. The later panels may not have got as wet as the earlier panels. Some of the earlier panels had been covered with a VCL. So that statement, as it is, gives me some comfort but it would not provide me with information as to whether they were monitoring something that had just been laid and therefore not subject to much wetting. Q. Would you criticise the architect for being incompetent if he took this at face value without asking any questions? A.I think it just needed some following up, whether it wasimmediately there and then. Q. It is whether -- by not following it up, are you criticising them for being negligent and incompetent? A. I think their obligation to determine whether the works are in accordance with their own -- with the works contracts in their own design, given the difficulties that there were on site, it is not possible for them to assess that adequately without more information as to the moisture content. Q. So you say they are incompetent? A. I say that not acting with reasonable skill and care. THE JUDGE: Thank you.”