"the amount at which an asset or liability could be exchanged in an arms' length transaction between informed and willing parties, other than in a forced or liquidation sale." (2) Estimated Fair Value of the Contract is defined as: "the amount determined in accordance with clause 58.3 (No Retendering Procedure)) [sic] that a third party would pay to the Councils as the market value of the Deemed New Contract". (3) Adjusted Estimated Fair Value of the Contract (or AEFV) is defined as: "the Estimated Fair Value of the Contract, less an amount equal to the aggregate of: (a) where relevant any Post Termination Service Amounts paid to the Contractor (if a positive number); (b) the Tender Costs; and (c) amounts that the Councils are entitled to set off or deduct under clause 71 (Set Off) plus an amount equal to the aggregate of: (d) all credit balances on any bank accounts held by or on behalf of the Contractor in connection with this Contract on the date that the Estimated Fair Value of the Contract is calculated; (e) any insurance proceeds and other amounts owing to the Contractor (and which the Contractor in connection with this Contract is entitled to retain), to the extent not included in (d); and (f) the Post Termination Service Amounts (if a negative number) to the extent that: (i) (d), (e) and (f) have not been directly taken into account in calculating the Estimated Fair Value of the Contract; and (ii) the Councils have received such amounts under (d) and (e) in accordance with the Contract or such amounts are standing to the credit of the Joint Insurance Account". (4) Deemed New Contract [C/1/35] is defined as: "an agreement on the same terms and conditions as this Contract, as at the Termination Date, but with the following amendments: (a) if this Contract is terminated prior to the NWTF Planned Completion Date then the NWTF Planned Completion Date shall be extended by a period to allow a new contractor to achieve NWTF Services Commencement; (b) any accrued Performance/ Deductions and/or Unavailability Deductions, warning notices and/or default notices shall for the purposes of termination only, and without prejudice to the rights of the Councils to make financial deductions, be cancelled; (c) the term of such agreement shall be for a period equal to the term from the Termination Date to the Expiry Date or the Extended Expiry date (as the case may be); (d) in the event that any New Contractor Rectification Works are required (in relation to a Facility that has, at the Termination Date, had a Completion Certificate issued) to enable the New Contractor to provide the Services to the full specification and standards required by this Contract, then provided that the New Contractor complies with the New Contractor Rectification Plan the Councils shall not exercise their rights to terminate the Contract under clause 57 (Termination on Contractor Default) by reason of any failure to achieve some or all of the Specification and/or standards required by this Contract during the New Contractor Rectification Period solely as a consequence of the New Contractor Rectification Works being required. Such provision shall for the avoidance of doubt not affect the Councils' entitlement to make adjustments and/or Deductions in accordance with Schedule 3 (Payment Mechanism) as a result of failure to achieve the Specification and/or standards required by this Contract during the New Contractor Rectification Period; (e) (only if it is practically impossible to achieve 100% following the implementation of the Upgrade Plan) vary the level of default applicable for the purposes of paragraph (r) of the definition of Contractor Default to an amount 10% above the average at which the Contractor was performing in the two years prior to the Termination (or where Termination occurs within two years from the NWTF Completion Date, the average at which the Contractor was performing since the NWTF Completion Date)". (5) New Contractor Rectification Works are defined as: "such works (including new and rectification works) and implementation of such new systems as shall be required to enable the New Contractor to achieve the standards and targets set out in Schedule 1 (Specification)." (6) Tender Costs are defined as: "the reasonable and proper costs of the Councils incurred in carrying out the Tender Process and/or in connection with any calculation of the Estimated Fair Value of the Contract". (7) Unitary Charge is defined as: "the fee notionally payable by the Councils as consideration for the delivery of the Services calculated in accordance with paragraph 1 of Schedule 3 (Payment Mechanism) on the basis of complete performance of the Services in accordance with the Specification and without allowing for over performance". (8) Deduction is defined as: "any deduction from or reduction in the Unitary Charge made pursuant to Schedule 3 (Payment Mechanism) resulting from the Contractor's failure to deliver the Service in accordance with the requirements of Schedule 1 (Specification)". (9) Clause 30.2.1.2 “30.2.1 Subject to: 30.2.1.1 any other express right of the Councils pursuant to this Contract; and 30.2.1.2 the Councils' right to claim, on or after termination of this Contract, the amount of its reasonable costs, losses, damages and expenses suffered or incurred by it as a result of rectifying or mitigating the effects of any breach of this Contract by the Contractor (provided that where the breach is one in respect of which the Councils are able to make a Deduction, the making of such Deduction shall be the sole remedy of the Councils in relation to such breach), save to the extent that the same has already been recovered by the Councils pursuant to this Contract or has been taken into account to calculate any compensation payable by the Councils pursuant to clauses 60 (Compensation on Termination for Force Majeure), 58 (Compensation on Termination on Contractor Default), 56 (Compensation on Council Default) 64 (Compensation on Voluntary Termination) or 62 (Compensation on Termination on Corrupt Gifts, Fraud) and 66 (Compensation on Termination for Breach of the Refinancing Provisions); the sole remedy of the Councils in respect of a failure to provide the Services in accordance with this Contract shall be the operation of Schedule 3 (Payment Mechanism) and Schedule 14 (Performance Mechanism).” 30.2.1.1 any other express right of the Councils pursuant to this Contract; and 30.2.1.2 the Councils' right to claim, on or after termination of this Contract, the amount of its reasonable costs, losses, damages and expenses suffered or incurred by it as a result of rectifying or mitigating the effects of any breach of this Contract by the Contractor (provided that where the breach is one in respect of which the Councils are able to make a Deduction, the making of such Deduction shall be the sole remedy of the Councils in relation to such breach), save to the extent that the same has already been recovered by the Councils pursuant to this Contract or has been taken into account to calculate any compensation payable by the Councils pursuant to clauses 60 (Compensation on Termination for Force Majeure), 58 (Compensation on Termination on Contractor Default), 56 (Compensation on Council Default) 64 (Compensation on Voluntary Termination) or 62 (Compensation on Termination on Corrupt Gifts, Fraud) and 66 (Compensation on Termination for Breach of the Refinancing Provisions); the sole remedy of the Councils in respect of a failure to provide the Services in accordance with this Contract shall be the operation of Schedule 3 (Payment Mechanism) and Schedule 14 (Performance Mechanism).” (10) Clause 58 : “58.1 Retendering Election 58.1.1 Subject to clause 58.1.2, the Councils shall be entitled either to: 58.1.1.1 retender the provision of the Project in accordance with clause 58.2 (Retendering Procedure); or 58.1.1.2 require an expert determination in accordance with clause 58.3 (No Retendering Procedure). ….. 58.3 No Retendering Procedure If the Councils are not entitled to re-tender the provision of the Project under clause 58.1 or the Councils elect to require an expert determination in accordance with this clause 58.3 or clause 58.2.19 applies, then the following procedure shall apply: 58.3.1 Subject to clause 58.3.2, the Contractor shall not be entitled to receive any Post Termination Service Amount. 58.3.2 If the Councils elect to require an expert determination in accordance with this clause 58.3 after they have elected to follow the procedure under clause 58.2, then the Councils shall continue to pay to the Contractor each Post Termination Service Amount until the Compensation Date, in accordance with clause 58.2. 58.3.3 In agreeing or determining the Estimated Fair Value of this Contract, the Parties shall be obliged to follow the principles set out below: 58.3.3.1 all forecast amounts shall be calculated in nominal terms at current prices, recognising the adjustment for indexation in respect of forecast inflation between the date of calculation and the forecast payment date(s) as set out in this Contract; 58.3.3.2 the total of all future payments of the full Unitary Charge (without Deductions) forecast to be made and Third Party Income forecast to be earned shall be calculated and discounted to the Termination Date at the Termination Date Discount Rate; 58.3.3.3 the total of all costs forecast to be incurred by the Councils as a result of termination shall be calculated and discounted at the Termination Date Discount Rate and deducted from the payment calculated pursuant to clause 58.3.3.2 such costs to include (without double counting): (a) any loss of Third Party Income to which the Councils would otherwise have been entitled under paragraph 5.5 of Schedule 3 (Payment Mechanism) assumed at Base Case levels; (b) a reasonable risk assessment of any cost overruns that will arise, whether or not forecast in the relevant Base Case; (c) the costs of the Service (including any assessment of costs of generating any Third Party Income) forecast to be incurred by the Councils in providing the Project to the standard required; and (d) any rectification costs required to deliver the Project to the standard required (including any costs forecast to be incurred by the Councils to complete construction or development work and additional operating costs required to restore operating services standards), in each case such costs to be forecast at a level that will deliver the full Unitary Charge referred to in clause 58.3.3.2. 58.3.3.4 where any element of the Capital Contribution has not been paid as at the Termination Date (the "
“118. Therefore, the formula in clause 58.3 is the product of: 118.1 Income: "the total of all future payments of the full Unitary Charge (without Deductions) forecast to be made and Third Party Income forecast to be earned…discounted…at the Termination Date Discount Rate" (clause 58.3.3.2). less 118.2 Costs: "the total of all costs forecast to be incurred by the Councils as a result of termination…discounted…at the Termination Date Discount Rate … forecast at a level that will deliver the full Unitary Charge" (clause 58.3.3.3). plus 118.3 where, as in the present case, the Termination Date falls after the NWTF Planned Completion Date, the full Unpaid Contribution under the Project Agreement (which is£50,000,000 ) (clause 58.3.3.4(b)). Income 119. In relation to income, clause 58.3.3.2: 119.1 assumes full payment of the Unitary Charge without any Deductions; and 119.2 requires there to be a forecast of the Third Party Income to be earned, which is not fixed by a particular standard or by the level assumed in the Base Case. Costs 120. In relation to costs: 120.1 clause 58.3.3.3 refers to four heads of cost, namely (emphasis added): (a) "any loss of Third Party Income to which the Councils would otherwise have been entitled under paragraph 5.5 of Schedule 3 (Payment Mechanism) assumed at Base Case levels" (clause 58.3.3.3(a)); (b) "a reasonable risk assessment of any cost overruns that will arise, whether or not forecast in the relevant Base Case" (clause 58.3.3.3(b)); (c) "the costs of the Service (including any assessment of costs of generating any Third Party Income) forecast to be incurred by the Councils in providing the Project to the standard required" (clause 58.3.3.3(c)); and (d) "any rectification costs required to deliver the Project to the standard required (including any costs forecast to be incurred by the Councils to complete construction or development work and additional operating costs required to restore operating services standards)" (clause 58.3.3.3(d)). 120.2 the costs in clause 58.3.3.3 are the costs that the Defendants are forecast to incur; and 120.3 these costs are not the very lowest or highest costs that could be incurred; first, the likely costs are forecast and then a reasonable risk assessment of any cost overruns is applied as set out in clause 58.3.3.3(b).” 118.1 Income: "the total of all future payments of the full Unitary Charge (without Deductions) forecast to be made and Third Party Income forecast to be earned…discounted…at the Termination Date Discount Rate" (clause 58.3.3.2). less 118.2 Costs: "the total of all costs forecast to be incurred by the Councils as a result of termination…discounted…at the Termination Date Discount Rate … forecast at a level that will deliver the full Unitary Charge" (clause 58.3.3.3). plus 118.3 where, as in the present case, the Termination Date falls after the NWTF Planned Completion Date, the full Unpaid Contribution under the Project Agreement (which is£50,000,000 ) (clause 58.3.3.4(b)). Income 119.1 assumes full payment of the Unitary Charge without any Deductions; and 119.2 requires there to be a forecast of the Third Party Income to be earned, which is not fixed by a particular standard or by the level assumed in the Base Case. Costs 120.1 clause 58.3.3.3 refers to four heads of cost, namely (emphasis added): (a) "any loss of Third Party Income to which the Councils would otherwise have been entitled under paragraph 5.5 of Schedule 3 (Payment Mechanism) assumed at Base Case levels" (clause 58.3.3.3(a)); (b) "a reasonable risk assessment of any cost overruns that will arise, whether or not forecast in the relevant Base Case" (clause 58.3.3.3(b)); (c) "the costs of the Service (including any assessment of costs of generating any Third Party Income) forecast to be incurred by the Councils in providing the Project to the standard required" (clause 58.3.3.3(c)); and (d) "any rectification costs required to deliver the Project to the standard required (including any costs forecast to be incurred by the Councils to complete construction or development work and additional operating costs required to restore operating services standards)" (clause 58.3.3.3(d)).
“153.2 The starting point for any assessment of the costs under clause 58.3.3.3(c) and (d) is: (a) an assumption that the Defendants would actually perform (or procure the performance of) the Service to meet the output/performance targets in the Specification and a forecast of the costs that the Defendants would incur if they did so; (b) a forecast of the rectification costs the Defendants actually would incur in doing so; and (c) in each case, assuming the Defendants act reasonably and consistently with their overall obligation to achieve Best Value by planning and implementing a reasonable methodology which delivers the full Unitary Charge in the most economic manner reasonably attainable.” reasonably attainable.”
‘147. As the language of clause 58.3 expressly requires… the starting point in any assessment under that clause will always be to: 147.1 Identify the work / services that the Defendants intend to undertake to achieve the targets in the output / performance specification which will deliver the full income stream credited to the Claimant in clause 58.3.3.2 (or, in the event that they do not intend to undertake such works /services, the work / services that they would intend to undertake if they were to achieve the targets in the output / performance specification); 147.2 Identify the costs forecast to be incurred in providing those works /services; 147.3 Assess the proposed works/services/costs on evidence against the standard of whether they are: (a) Required to deliver the Project to the level that will deliver the full Unitary Charge; and (b) Meet the Fair Market Value test.’
‘the judge should have followed his original instinct. It is not uncommon for an application under Part 24 to give rise to a short point of law or construction and, if the court is satisfied that it has before it all the evidence necessary for the proper determination of the question and that the parties have had an adequate opportunity to address it in argument, it should grasp the nettle and decide it. The reasons is quite simple: if the respondent’s case is bad in law, he will in truth have no real prospect of succeeding on his claim or successfully defending the claim against him, as the case may be. Similarly, if the applications’ case is bad in law, the sooner that is determined, the better.’
‘23. In considering whether to exercise its jurisdiction to grant a summary declaration, the court should take into account justice to the claimant, justice to the defendant, whether the declaration would serve a useful purpose and whether there are any other special reasons for granting or refusing the declaration: Financial Services Authority v Rourke19 October 2001 , unreported (Neuberger J). In this case the existence of the proceedings in Maine, in which judicial indications have been given that the view of this court on questions of English law regarding the three agreements would be welcomed, provides a cogent reason for exercising the jurisdiction provided that the necessary requirements are met. 24.CPR 24.2 provides that the court may give summary judgment against a claimant or a defendant on the whole of a claim or on a particular issue if it considers that the claimant has no real prospect of succeeding on the claim or issue or, conversely, that the defendant has no real prospect of successfully defending the claim or issue. Part of Bee Load’s argument is that on all the issues of construction its argument is tenable, and accordingly the requirements ofCPR 24 are not satisfied. This raises the question how the court should proceed where the issue raised is a pure point of construction which can be as well determined on a summary application as on a full trial (or a trial of preliminary issues), because it will not be affected by evidence. It seems to me that if at the end of the argument the court comes to a clear view as to the correct construction, the court has jurisdiction to grant summary judgment underCPR 24.2 on the basis that a trial would have no realistic prospect of causing it to reach a different judgment. 25. I believe that this approach accords with the underlying objective of Part 24, which superseded RSC O14, O14A and O18 r 19. RSC O14A provided for summary disposal of a case on a point of law. If I were wrong in this approach, an alternative approach in order to minimise the use of court time and the cost to the parties would be to direct the hearing of preliminary issues, reserve the matter to myself (having already heard detailed arguments on the issues) and then give judgment, but I do not believe that this is necessary. I agree with Cooke J's observation that if summary judgment is given on points of construction, it is because they appear to the judge to be clear as a matter of English law.’
‘I would add that the court should still consider very carefully before accepting an invitation to deal with single issues in cases where there will need to be a full trial on liability involving evidence and cross examination in any event, or where summary disposal of the single issue may well delay, because of appeals, the ultimate trial of the action: see Potter LJ in Partco v Wragg[2002] EWCA Civ 594 ;[2002] 2 Lloyds Rep 343 at 27(3) and cases there cited. Removing road blocks to compromise is of course one consideration, but no more than that. Moreover, it does not follow from Lewison J's seventh principle that difficult points of law, particularly those in developing areas, should be grappled with on summary applications; see Partco at 28(7). Such questions are better decided against actual rather than assumed facts. On the other hand it may be possible to say that the trajectory of the law will never on any view afford a remedy: see for example Hudson and others and HM Treasury and another[2003] EWCA Civ 1612 .’
‘It is open to the court to deal with a point of law or construction on the hearing of an application for summary judgment. In Easyair and in Mellor v Partridge[2013] EWCA Civ 477 at [3 (vii)] Lewison J said it was open to the court to determine "a short point of law or construction". This description usually prompts the applicant to submit the point is short, and is therefore capable of being dealt with on an application for summary judgment, and the respondent to submit it is anything but short. Quite where the boundary lies between a point with which it is acceptable for the court to deal on a summary basis, and one that is unsuitable, is not easy to draw. As it appears to me, the notion of shortness does not relate to the length of the document to be construed or the length of the material passage in that document; but it may relate to the length of the hearing that will be required and the complexity of the matrix of fact the court will have to consider. In my experience the court regularly deals with points of law and of construction of real difficulty on the hearing of an application for summary judgment. I would only add that there may be some overlap between the idea of a point of construction not being 'short' and the second limb ofCPR rule 24.2 . There may be some points that the court is capable of grappling with (or grasping the nettle as it is sometimes put) that, nevertheless due to the context in which they arise or other factors are best left to be dealt with at a trial.’
‘Estimated Fair Value computations are conducted by forecasting the full Unitary Charge from the date of termination to the expiry of the Contract (ignoring any deductions for performance or availability), from which the estimated costs of delivering the service to the required standard in the output specification (this includes the running costs, lifecycle costs and any rectification costs) are deducted to arrive at the estimated operating cash-flow stream which, had a liquid market existed and the project been re-tendered, a hypothetical bidder would have valued to determine the amount to bid for the project.’
‘21.2.6.1 The required approach follows the principle set out in Section 21.2.5.4. It facilitates the Senior Lenders’ rights to step–in, manage and rescue or sell the Project if the Contractor defaults, but, if they fail to do so, offers compensation on termination based on the market value of the unexpired term of the Contract. 21.2.6.2 The approach: … - ensures that the Authority is no worse off as a result of the termination where Senior Lenders elect not to step–in; - does not give the Authority a windfall gain on termination; …’
“3.4—(1) In this rule and rule 3.5, reference to a statement of case includes reference to part of a statement of case. (2) The court may strike out a statement of case if it appears to the court— (a) that the statement of case discloses no reasonable grounds for bringing or defending the claim; (b) that the statement of case is an abuse of the court’s process or is otherwise likely to obstruct the just disposal of the proceedings; or (c) that there has been a failure to comply with a rule, practice direction or court order. (3) When the court strikes out a statement of case it may make any consequential order it considers appropriate.” order it considers appropriate.”
“A subsequent statement of case must not contradict or be inconsistent with an earlier one; for example a reply to a defence must not bring in a new claim. Where new matters have come to light a party may seek the court’s permission to amend their statement of case.”
‘Not only is the proposition that one can advance a new claim in a Reply contrary to the clear terms of the Practice Direction, but it is also inherently undesirable and contrary to the overriding objective of dealing with cases justly and at proportionate cost. If such practice were to be condoned, claimants would not need to be precise in their formulation of the Particulars of Claim since they could always have a second bite of the cherry when pleading the Reply. Defendants would have to seek permission from the court in order to answer by way of Rejoinder any new claims pleaded in the Reply, which might in turn call for a Surrejoinder from the claimant.’
“1. Claim forms and particulars of claim must identify the nature of the claim and the remedies sought. 2. Particulars of claim must contain the basic facts on which the claimant relies to support its claim or claims. 3. The remedies sought must relate to the claim or claims made and the basic facts pleaded by the claimant. 4. Generally at least there should be no half measures taken in the claim or in particulars of claim in terms of pleading matter which is immaterial to the relief or remedies sought. 5. It would be wrong, at least generally, in principle, to plead a matter which does not support or relate to any of the remedies sought. 6. It would be wrong in principle to plead a matter which is immaterial to the claim or claims made or relief sought for the purpose of securing disclosure of documentation relating to such immaterial matter. 7. Whilst infelicities in pleadings will not usually justify striking out, where no cause of action is pleaded then the court must give serious consideration to striking out that part of the pleading, particularly where its presence complicates and confuses the fair conduct of the proceedings. 8. Either through the CPR or through its inherent jurisdiction the court has wide powers to strike out parts of a pleading if it contains immaterial matter, particularly in circumstances when its continued presence will confuse the resolution of the underlying and properly pleaded claims. 9. A party absent agreement has no automatic right to amend its Particulars of Claim.”
“1. Statements of case must be concise. They must plead only material facts, meaning those necessary for the purpose of formulating a cause of action or defence, and not background facts or evidence. Still less should they contain arguments, reasons or rhetoric. These basic rules were developed long ago and have stood the test of time because they serve the vital purpose of identifying the matters which each party will need to prove by evidence at trial. 2. As commercial transactions have become more complex and more heavily documented (including electronically), adhering to the basic rules of pleading has become both increasingly difficult and all the more important. It is increasingly difficult because it is harder for pleaders to distil what is essential from the material with which they are provided and because they can feel pressure to show their mettle and enthusiasm for their client’s case by treating the pleadings as an opening salvo of submissions in the litigation. It is all the more important because prolixity adds substantial unnecessary costs to litigation at a time when it is harder than ever to keep such costs under control. [Paragraph 3 dealt with the history of the introduction of the 25 page word limit within the Commercial Court and paragraph 4 set out parts of the Commercial Court Guide] 5. The particulars of claim which have been served in the present case flout all these principles. They are 94 pages in length. They include background facts, evidence and polemic in a way which makes it hard to identify the material facts and complicates, instead of simplifying, the issues. The phrasing is often not just contentious but tendentious. For example, the defined term used to refer to three of the defendants is “the Conspirators”
“30. It should not need repeating that Particulars of Claim must include a concise statement of the facts on which the Claimant relies:CPR 16.4 (1)(a). The “facts on which the Claimant relies” should be no less and no more than the facts which the Claimant must prove in order to succeed in her or his claim. …. The Queen’s Bench Guide provides guidelines which should be followed: they reflect good and proper practice that has been universally known by competent practitioners for decades. They include that “a statement of case must be as brief and concise as possible and confined to setting out the bald facts and not the evidence of them”: see 6.7.4(1). A statement of case exceeding 25 pages is regarded as exceptional: experience shows that most cases can be accommodated in well under 25 pages even where the most serious allegations are made. Experience also shows that prolix pleadings normally tend to obfuscate rather than to serve their proper purpose of identifying the material facts and issues that the parties have to address and the Court has to decide. 31. Where statements of case do not comply with these basic principles, the Court may require the Claimant to achieve compliance by striking out the offending document and requiring service of a compliant one: see Tchenquiz v Grant Thornton[2015] EWHC 405 (Comm) and Brown v AB[2018] EWHC 623 (QB) . It has always been within the power of the Court to strike out either all or part of a pleading on the basis that it is vague, irrelevant, embarrassing or vexatious.”
‘One of the issues that caused problems with the set-up, commissioning and optimisation of Energos gasification plants in the United Kingdom (namely, Derby, Milton Keynes and Glasgow) from mid-2016 onwards was that Energos became insolvent. This meant that, certainly in the case of the ACT at Derby, experienced personnel from Energos who should have been involved in the process of setting up, commissioning and optimising the gasification plants were not available and the work had to be undertaken by personnel without particular experience or expertise with the Energos plant and designs. That inevitably resulted in a protracted period in which, in effect, there was a learning curve for many of the personnel involved. In the case of Derby, that period extended beyond the NWTF Long Stop Date and the subsequent termination of the Project Agreement by the Defendants. What is required properly to set up, commission and optimise all parts of the ACT has become much better understood both by the time of termination and, because the Milton Keynes and Glasgow plants have continued to operate. If the Works and Services were undertaken, it would involve consultation with operators of these other Energos plants and drawing on their "lessons learned".’
‘As the Claimant understands the Defendants’ pleaded case, the Defendants’
‘To illustrate how the risk assessment is driven by the Court’s assessment of the basis, amount and likelihood of the Clause 58.3.3.3(c) and (d) costs, and the risk of adverse outcomes of those costs, it is helpful to consider the example of steady state ACT availability, as follows….’