“The standby generator shall be sized to provide the power for all Life Safety Services when running at 80% full load but as a minimum to be rated at 500KVA at stand-by and designed to avoid failure during start-up for inrush currents.”
“(1) Summary judgment pursuant toCPR r.24.2 on the claims for (i) declarations (ii) rectification and (iii) set aside of two adjudicators’ decisions; (2) The remainder of the Claimant’s Particulars of Claim dated16 January 2023 to be struck out pursuant toCPR 3.4 (2). Alternatively, the whole of the Particulars of Claim to be struck out.”
“excessive detail does not detract from an understanding of the essential facts necessary for the purpose of formulating a complete cause of action set out in the body of the pleading.”
“(a) The document must be as concise as possible”; “(c) The document must deal with the case on a point by point basis to allow for a point by point response. In particular, each separate cause of action, or defence, should be pleaded separately wherever possible”; “(d) So far as possible each paragraph or sub-paragraph should contain no more than one allegation”; “(e) Special care should be taken to set out… only those factual allegations which are necessary to establish the cause of action… being advanced, to enable the other party to know what case it has to meet. Evidence should not be included, and a general factual narrative is neither required nor helpful (and is likely to contravene paragraphs (f), (h) and/or (k) below)”; “(k) Where it is necessary to give lengthy particulars of an allegation, this should be set out in schedules or appendices”; “(m) Where it is necessary for the proper understanding of the statement of case to include substantial parts of a lengthy document the passages in question should be set out in a schedule rather than in the body of the statement of case.”
“It is, however, also important to note that in applications such as this, the Court must ultimately take a proportionate and practical view. It is very likely that any pleading, particularly viewed through the eyes of the opposing party, may contain what Akenhead J [in Charter UK Ltd v Nationwide Building Society[2009] EWHC 1002 (TCC) ], describes as ‘infelicities’. A pleading may well stray at times onto the wrong side of the important Guidelines set out in the TCC Guide and other equivalent documents. That is not to be encouraged, but in reality it may happen in complex litigation. There will plainly be occasions where the ‘infelicities’ aggregate to a level which is clearly, and objectively, unacceptable. This will almost certainly be the case where the aggregate effect is to impair the ability of the pleading, or significant parts of it, to serve any useful purpose, or where essential elements (such as a cause of action) are missing. It will also be the case if the pleading is embarrassing or vexatious. Where essential elements are missing, or where the pleading is embarrassing or vexatious, the need for the matter to be cured is obvious and immediate. Where the complaint is that there is immaterial, irrelevant or unnecessary verbiage in a pleading, or that evidence has been pleaded rather than facts, the precise point at which it is necessary and proportionate for the Court to require offending elements to be struck out is more difficult to define. As Akenhead J said, mere infelicities in pleadings will not usually justify striking out. Whilst unnecessary and irrelevant material is in breach of the Guidelines and plainly unhelpful, it is also right that the general administration of justice is not advanced by parties combing the other sides’ pleadings for transgressions which do not in fact materially impact a parties’ ability to understand the case they have to meet or the Court’s ability to manage the case effectively.”
“93. As pleaded above, the proper construction of the Trade Contract requires consideration of: (a) the wording contained in the documents of which it is comprised (or evidenced by), as set out above; (b) the objective facts known to both parties which, in STSD’s case, it either knew itself or is taken to have known on the basis that such facts were known by its agent, Mace (a major international contractor and contract manager, highly-experienced in the construction of significant buildings and MEP design and installation for such projects); (c) the circumstances which led to the execution of the Trade Contract, to identify the purpose of the Trade Contract so as to construe the language used (both in the Contract’s components and as a whole) in the light of that purpose; and (d) the parties’ common intention as at the date of entry into the Trade Contract.” (a) the wording contained in the documents of which it is comprised (or evidenced by), as set out above; (b) the objective facts known to both parties which, in STSD’s case, it either knew itself or is taken to have known on the basis that such facts were known by its agent, Mace (a major international contractor and contract manager, highly-experienced in the construction of significant buildings and MEP design and installation for such projects); (c) the circumstances which led to the execution of the Trade Contract, to identify the purpose of the Trade Contract so as to construe the language used (both in the Contract’s components and as a whole) in the light of that purpose; and (d) the parties’ common intention as at the date of entry into the Trade Contract.”
“by considering the circumstances which led to the execution of the contract, to identify the purpose of the transaction and to construe the language used in the light of that purpose.”
“What is not permissible, as the decision of the House of Lords in [Chartbrook Ltd v Persimmon Homes Ltd[2009] UKHL 38 ;[2009] 1 AC 1101 ] confirms, is to seek to rely on evidence of what was said during the course of precontractual negotiations for the purpose of drawing inferences about what the contract should be understood to mean. It is also clear from the Chartbrook case that it is not only statements reflecting one party’s intentions or aspirations which are excluded for this purpose but also communications which are capable of showing that the parties reached a consensus on a particular point or used words in an agreed sense.”
“The rule excludes evidence of what was said or done during the course of negotiating the agreement for the purpose of drawing inferences about what the contract meant. It does not exclude the use of such evidence for other purposes: for example, to establish that a fact which may be relevant as background was known to the parties, or to support a claim for rectification or estoppel. These are not exceptions to the rule. They operate outside it.”
“the circumstances which led to the execution of the Trade Contract and the purpose of the Trade Contract and its constituent documents (in particular the DRM) in light of the above included”
“97. It was the common intention of the parties, as at the date that the Conditions were signed, that in respect of the Works where the DRM categorised Chapman’s design responsibility as “P” and Halsion’s as “E1”, and the “RIBS Workstage Delivery” as “4” (or including “4”), and specifically in respect of the Generator: (a) The design of the Works (save in relation to the CDP elements) was completed to RIBA Work Stage/BSRIA Stage 4. (b) Halsion would only be responsible for carrying out the RIBA Work Stage/BSRIA Stage 5 design (unless Halsion changed elements of the Work Stage 4 design that had been provided to it). (c) Halsion was not responsible for: (i) The Work Stage 4 design produced by Chapman (unless Halsion changed elements of that design); or (ii) The sizing of any plant (including the Generator), where Halsion was to be (or had been) provided with a Work Stage 4 design. (iii) Validating or otherwise checking the Work Stage 4 design provided to it (save where it had specifically agreed to: Halsion had offered to spot- check 10% of Chapman’s cable calculations in return for an additional fee of£15,000 ). (d) In the event that the Work Stage 4 design produced by Chapman proved to be inadequate or deficient, Halsion would be entitled to a written instruction varying the Trade Contract in respect of any additional work that was required.” (a) The design of the Works (save in relation to the CDP elements) was completed to RIBA Work Stage/BSRIA Stage 4. (b) Halsion would only be responsible for carrying out the RIBA Work Stage/BSRIA Stage 5 design (unless Halsion changed elements of the Work Stage 4 design that had been provided to it). (c) Halsion was not responsible for: (i) The Work Stage 4 design produced by Chapman (unless Halsion changed elements of that design); or (ii) The sizing of any plant (including the Generator), where Halsion was to be (or had been) provided with a Work Stage 4 design. (iii) Validating or otherwise checking the Work Stage 4 design provided to it (save where it had specifically agreed to: Halsion had offered to spot- check 10% of Chapman’s cable calculations in return for an additional fee of£15,000 ). (d) In the event that the Work Stage 4 design produced by Chapman proved to be inadequate or deficient, Halsion would be entitled to a written instruction varying the Trade Contract in respect of any additional work that was required.”
“amending the Trade Contract in such terms as the Court may decide common intention at the date when they entered into the Trade Contract.”
“In the event that Halsion changes the Stage 4 design prepared by Chapman, the standby generator shall be sized [by Halsion] to provide the power for all Life Safety Services when running at 80% full load but as a minimum be rated at 500KVA at stand-by and designed to avoid failure during start-up for excessive inrush currents.”
“(a) By mistake the wording does not reflect the parties’ common intention (as pleaded at paragraph 97 above) as to their respective obligations for the responsibility for Work Stage 4 design and the sizing of plant. (b) There was an outward expression of accord as to that common intention. (c) The accord was continuing as of the date on which Halsion signed of the Trade Contract Conditions (for the reasons set out in paragraphs 12 to 67 above).”
“In the further alternative, by reason of the matters set out in paragraphs 12 to 67 and/or paragraphs 68 to 71 above, an estoppel by convention arose, there being a common assumption or understanding between the parties as to their respective obligations for the Work Stage 4 design and sizing of plant in the terms pleaded at paragraph 97 above. This assumption or understanding was made and shared by both parties, alternatively made by Halsion and known about and acquiesced in by STSD, as evidenced by, inter alia:”
“the exchanges between Halston and Mace after the ITT, in which Halsion’s intention in this regard was clearly and repeatedly communicated to Mace”
“While there are other categories of abuse that are not relevant to this application, the court may strike out Particulars of Claim under r.3.4(2)(b) where they are so badly drafted that they fail to identify the case that the defendant has to meet. In such cases, strike out is, however, very much a remedy of last resort and the court should usually first allow the claimant an opportunity to file a coherent and intelligible claim.”
“CPR 3.4 (2) is not the appropriate route for debating pleading points which do not materially affect the understanding of the claim (or defence)”
“the circumstances which led to the execution of the Trade Contract so as to establish the parties’ objectives in the transaction (per Elmfield Road Ltd v Trillium (Prime) Property Group Ltd[2016] EWHC 3122 (Ch) at [52] and Merthyr (South Wales) Limited v Merthyr Tydfil County Borough Council[2019] EWCA Civ 526 at [50].”
“The genesis and aim of a particular provision may be sufficiently important to qualify as part of the genesis and aim of the whole transaction. If so, it will be admissible pursuant to Prenn v Simmonds; if not, it is contrary to Prenn v Simmonds to allow it to be admitted.”
“Sir Kim Lewison considers this approach to be correct (see The Interpretation of Contracts, 2017 supplement, at 3.09), and so do I.”
“Given the historic dispute between the parties as to what was and was not decided by the Adjudicator in his decisions in Adjudications 4 and 5, there is real utility in such a declaration being granted Halsion’s favour”
“When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to “what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean”, to quote Lord Hoffmann in Chartbrook Ltd v Persimmon Homes Ltd[2009] AC 1101 , para 14. And it does so by focussing on the meaning of the relevant words … in their documentary, factual and commercial context.”
“There was an outward expression of accord as to that common intention.”
“by reason of the matters set out in paragraphs 12 to 67 and/or paragraphs 68 to 71 above”