‘We are advised by Mr Porter that: 7.1 It will take at least 3 weeks for him to fully understand the substantial report prepared by Mr Hughes- Phillips and his team to enable him to be able to undertake a useful review of the Referring party's documents. 7.2 He, and his team, will require to attend at the Referring Party's offices for at least 3 days to inspect the source material on which Mr Hughes-Phillips' report is based and to have access to the software that Mr Hughes-Phillips and his team were provided with. 7.3 It would then be useful for him to meet with Mr Hughes-Phillips in order to fully understand the basis upon which his report has been written, and to try and narrow the issues in dispute. 7.4 Thereafter it would take at least 4weeks for him to prepare his report.’ 16. Various communications between the adjudicator and the parties, and between the parties, then followed. On22 March 2023 , Mr Pye wrote: ‘Ms Morean/Mr Gerstein, I acknowledge receipt of your further emails of this afternoon. I note that Home Group's change in the quantum was over one month ago. I also note that MPS has not yet taken up Home Group's previous invitations to visit Home Group's offices to inspect the electronic data. The current situation is that Home Group is, subject to final confirmation, prepared to keep open its offer of an extended timetable as set out below: Date for Response11 April 2023 Date for Reply21 April 2023 Date for Rejoinder28 April 2023 Date for Decision22 May 2023 The alternative position is for a 14 day extension to the date for my Decision to2 May 2023 . If the alternative position is the one implemented, I would be prepared to extend the date for the Response from30 March 2023 to5 April 2023 with the date and permission for further submissions to be decided by me at a later stage. I, therefore, request both Parties to confirm by noon tomorrow whether they accept the timetable set out in the box above with a revised date for my Decision of22 May 2023 . Failing agreement by both Parties, the alternative timetable with a Response date of5 April 2023 and a Decision date of2 May 2023 will apply. For the avoidance of doubt, I advise the Parties that I do not consider resignation to be warranted whichever timetable is adopted.’ 17. On23 March 2023 Home Group confirmed its agreement to the timetable concluding on 22 May as set out in letter quoted immediately above. On the same day, MPS confirmed that it was not prepared to agree to the proposed timetable and said its position was maintained that: a) The dispute had not crystallised when the Notice was served; b) Multiple disputes have been referred to you; and c) The case is too complex to be resolved in adjudication. 18. As confirmed by the Adjudicator the following day, as a result of a strategic decision to maintain its jurisdictional objections, the Response was to be served on5 April 2023 (rather than11 April 2023 ). 19. MPS served its Response in accordance with the Adjudicator’s timetable on5 April 2023 , accompanied by witness statements and a quantum expert report from Mr Porter. Mr Porter gave evidence about the impact of what he said was inadequate time to prepare the report on his evidence: ‘13. The timescale for producing my report has been to say the least, extremely challenging. Given the amount of data and material, in order to form a detailed and complete assessment of the losses and accompanying expert report, I would have needed a period of 10 to 12 weeks, with some assistance. This would have been on the basis of remote or supported access in person to the raw data contained in the spreadsheets which was provided by HG to DHP. In contrast, I am advised that DHP and his team had 9 months to prepare their assessment and accompanying report. This included remote access to the various IT systems, which has been denied to me and my assistants. 14. As a result of the limited time available I have been unable to provide a complete assessment of the loss. There are some elements of the loss I have simply not had time to review and others I have had limited time to review the detail. Accordingly, I have not been able to arrive at opinion on the quantum of loss. Under such circumstances, in order to best assist the Adjudicator, which is where my primary duty lies, I have provided a detailed commentary on DHP’s report, in particular his approach, methodology and assessment, highlighting the points I consider incorrect and / or I disagree with and have an alternative opinion and why.’ 20. In addition to the evidence of Mr Porter, MPS relied upon five factual witnesses. These included Mr Smith, the Chief Financial Officer of Mears Group plc. As pointed out at paragraph 107 of the Decision, Mr Smith’s evidence was more a combination of a further Response containing legal submissions, opinion evidence on quantum and general comment. As tabulated in the Decision, MPS was through the combination of witness evidence able to advance the following positive case as to the required adjustments to Home Group’s claim (taken from the witness statement of Mr Smith): 21. In its Reply served on14 April 2023 , Home Group conceded in its entirety one of MPS' proposed significant deductions relating to 'Duplications' and proposed alternative reductions for certain other categories. In its Rejoinder MPS made clear that it did not accept that it was liable to pay Home Group the amount of£1,645,885 from its Response but that further adjustment should be made by the Adjudicator. In particular, it contended that its adjustments did not reflect the more significant concerns expressed in the Response concerning duplication and data integrity, and that Home Group's claim remained poorly analysed and evidenced. The Decision 22. In a decision running to 74 pages, Mr Pye concluded that MPS was liable to Home Group in the sum of£6,565,831.94 excluding VAT and interest. From his claim for fees, it is clear that Mr Pye spent 92.2 hours on the adjudication. 23. Paragraphs 83 to 94 dealt with jurisdictional issues. He recited the various communications. He concluded: ‘I have kept my jurisdiction under review throughout the adjudication and there is nothing which changes my non-binding view expressed in my emails of 16 March and20 April 2023 and, as also set out above, whilst the strict timetable of adjudication may have been a challenge for both Parties, for my part I have had sufficient time to appreciate the dispute and, at least, do broad justice between the Parties in this temporarily binding Decision.’ 24. Before dealing with each of the sub-issues upon which money turned within the account, the Adjudicator included a general section which dealt with expert opinion evidence and quantum generally. 25. In relation to expert evidence, he pointed out that there had been an acceptance by Mr Hughes-Phillips in his Second Report that there were errors in his First Report because of matters such as duplication of claimed items (double counting), incorrect allocation of costs and, more significantly, an apparent willingness on Mr Hughes-Phillips’ part to accept data provided to him by Home Group as factually correct without carrying out any or any sufficient verification of that data. Whilst the Adjudicator said that this was a potentially significant shortcoming in Mr Hughes-Phillips’ evidence, he considered but rejected the contention that this was indicative of a lack of impartiality. The willingness with which Mr Hughes-Phillips was prepared to change his opinion after considering Mr Porter's opinion evidence indicated to the contrary. 26. The Adjudicator noted that MPS accepted that a sampling process was appropriate, and recognized that Mr Porter was maintaining that he may have used a different selection basis if he had been given more time than was available to him in the adjudication. He then stated, in a paragraph relied upon by Mr Neuberger in written and oral submission: ‘The problem with Mr Porter's First Report is that he does not arrive at an alternative valuation in respect of Mr Hughes-Phillips quantum and it is clear that his reluctance to do so, from reading his report, is the time available to him and his team within the strict timetable of adjudication.’ 27. Noting this, the Adjudicator continued: ‘123. Mr Porter says that if he had been afforded the necessary time to undertake a full and detailed assessment his opinion of the quantum of Home Group's loss would be "substantially different and lower than DHP's view." 124. Notwithstanding Mr Porter's reluctance to offer an alternative valuation in his 112- page First Report, MPS has, through its witness of fact statements and the Response, proposed alternative valuations albeit heavily caveated. MPS provided a structured spreadsheet of proposed deductions to enable a comparison with Mr Hughes-Phillips production in the H-P First Report, albeit that the setting out of the MPS table does not follow the same detailed format. 125. MPS' table in respect of its valuation totals£1,645,885 , being a reduction of some£7.7m from Home Group's claim.’ 28. In this section, the Adjudicator also set out 7 respects in which, in general terms, the criticisms made of Mr Hughes-Phillips’ approach by Mr Porter were accepted; he also indicated that certain personal unsubstantiated submissions about Mr Hughes-Phillips by Mr Porter were not accepted. 29. The Adjudicator then, in his section on quantum generally, included a table which effectively set out the structure for the remainder of his Decision. This identified the various contended-for adjustments, the extent to which the adjustments were accepted (in whole or in part) by Home Group and thus the key areas of dispute. 30. Whilst it is not necessary for the purposes of this Judgment to describe in detail the approach of the Adjudicator to each issue (save in respect of duplication, to which I will return), it is plain that the Adjudicator took each category of claimed adjustment, and considered the relevant factual and expert evidence. It is to be noted that a number of the issues turned on either points of principle (i.e. whether a head of loss was properly recoverable) or factual issues rather than ‘quantum expert’ evidence. Ultimately, a significant reduction was made in the claimed sums by the Adjudicator having considered MPS’ factual and expert evidence. 31. In relation to duplication, the Adjudicator recognised at paragraph 179 that MPS were contending that the figure which had been identified as duplicative was the ‘low watermark’ of the likely level of duplication. In contrast, Mr Hughes-Phillips, in accepting the adjustment (of£366,339 ), contended that this was the ‘high watermark’
“182. I accept this proposal by Mr Brewer in principle as being logical given the actual findings in respect of the 149 properties. The fact that Mr Hughes-Phillips accepted the initial figure of£336,339.00 without variation suggests that a further duplication reduction might be warranted. 183. However, Ms Barkes explanation in her fourth witness statement in respect of duplication was persuasive as to why: • A cancelled Order does not mean the works were not required. • Duplicate Order numbers do not mean duplication or that the same work was claimed twice. • Home Group did interrogate the quotations after Home Group received after the surveys were carried out via Plentific. 184. Mr Brewer's response to the above was to say that Ms Barkes' explanation misrepresented the situation, but I do not agree. Ms Barkes' explanation is more detailed and plausible and demonstrates her knowledge of how the Home Group system works. 185. Additionally, there is no real verifiable basis to Mr Brewer's proposal of an£888k reduction. 186. Doing the best I can, I decide that Home Group's claim, is to be subjected only to the concession already made by Home Group in the amount of£366,339.00 . This amount is exclusive of the amount of£12,484.00 conceded by Home Group in respect of the 'Application of Administration Fee' item below.”
‘(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose ‘dispute’ includes any difference. (2) The contract shall include provision in writing so as to (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; …’