“The amounts claimed for loss and/or expense are summarised below.”
“11.1.2 The above amounts are estimated and based on incomplete [Bovis] and sub-contractors’ costs and other data and on the current preliminary report of Mr Marshall. They are therefore subject to amendment when further and better information is available.”
“You will note that we have found no grounds to fix a later completion date than the date we gave notification of by cover of our letter … dated23 March 2005 .”
“We give you and your client notice that should the differences between us proceed to adjudication, then we will seek a direction from the Adjudicator that, if we have not been provided with the report upon which you subsequently seek to rely, your client should be prevented from adducing the same.”
“I refer to [the Architect’s] letter dated16th March 2007 , by which they notified BLL of their decision that there are no grounds to fix a later completion date than that notified on23rd March 2005 , namely22nd July 2005 . BLL have applied for an extension of time by letter dated18th May 2006 . BLL relied on the expert reports issued to you on30th November 2006 and4th December 2006 . There is clearly a dispute between … the … Clinic and us in respect of our application and extension of time. BLL claims: (1) an extension of time of 40.2 weeks (over and above the four weeks previously granted), (2) reimbursement of the Liquidated and Assessed Damages paid during this period in the sum of£1,608,000 , (3) loss and expenses arising from this delay and disruption in the sum of£3,437,245.44 less£150,000 already paid by you on account for loss and expense, i.e.£3,287,245.44 . Please pay BLL the total sum of£4,895,245.44 by 12 noon on Monday21st July 2008 . If the Trustees fail to do so, BLL will proceed to refer this dispute to adjudication forthwith … in accordance with Clause 41A of the JCT Standard Form … Please find attached BLL’s Draft Referral Notice together with supporting documentation for your consideration. BLL is ready to refer this dispute to adjudication and will do so if the Trustees fail to pay the sums claimed by 12 noon, as stated above. Please notify us as soon as possible if you do not intend to pay the sums claimed. In the event that you do not intend to pay the sums claimed, it would be sensible for us to agree upon an adjudicator without delay. Please indicate whether you agree to proposal of one of the following three adjudicators …”
‘We acknowledge receipt of your letter of7 July 2008 and confirm that it did not enclose the documents referred to at paragraphs 4.3 and 5 in the draft Referral Notice. Please forward copies as soon as possible. We are in the process of reviewing the documentation enclosed with your letter and our file for this project … … our file indicates that your application for an extension was dated21 October 2006 , the “Interim Case” (your letter of21 December 2006 refers, copy attached) to which was attached two reports issued to us on 30 November (from Mr Marshall, dated27 November 2006 and from Mr Sworder, dated30 November 2006 ) and a further report issued on4 December 2006 (from Mr Wort, dated30 November 2006 ). On the basis of the material enclosed with your letter of7 July 2008 , it appears that you now rely on a different application for an extension of time as well as two further reports that we had not previously seen dated 2 April (Mr Marshall) and10 June 2008 (Mr Wort) respectively. We would be grateful if you could please clarify our understanding of your position and confirm the status of the “Interim Case”. As you will appreciate, there is a substantial amount of documentation to get through and we are doing our best to consider and digest their contents as soon as possible. We will similarly aim to review the documents referred to in paragraphs 4.3 and 5 of the Draft Referral Notice. Accordingly, we would be grateful if you would allow us until 18 August to provide you with our considered response to your letter of 7 July. We consider this a reasonable request in the circumstances. We propose to also, at that time, address the appointment of the Adjudicator.
“… I accept that in the case of Mr Wort’s report you have not seen this before. Mr Marshall’s report you will have seen as it is essentially the same document delivered previously. It has, of course, been updated to address the report prepared by [the Architect] delivered by letter dated16th March 2007 and their refusal to grant any additional extension of time and clearly you will have to consider what we say in response. Additionally, you now have the benefit of our witness statements. The documents referred to within the draft Referral Notice at paragraphs 4.3 and 5.0 are apart from our list of case authorities documents that you will have seen before and which are within your care, custody and control. In those circumstances, I do not propose to furnish you with these documents, but they will, of course, be supplied in support of our referral when served. Our letter of 7th July clearly sets out the areas where there is a dispute between the parties and is the basis upon which we propose to proceed. Given the passage of time since completion of this project your request for yet another month in which to provide us with your considered response to the claim, the existence of which you were well aware, is surprising but given the nature of your request I am prepared to accede to this and allow you until close of business on Monday18th August 2008 .”
“The dispute comprises the following inter-related issues: (1) Whether and to what extent delay and/or disruption was caused by BLL’s Contract works by reason of matters for which the Clinic was responsible; (2) The period of any Extension of Time to which BLL is entitled; (3) BLL’s entitlement to reimbursement of Liquidated and Ascertained Damages deducted during the period of this Extension of Time in the sum of£40,000 per week; (4) The losses and expenses incurred by BLL by reason of the delay and disruption to the Contract Works.”
‘It is sensible to ignore the element of BLL’s claim for loss and expense for the reasons that you say. However, more importantly, simply, BLL is not in any event entitled to loss and expense under the contract. Clause 30.1.1 (as amended) provides that “as a condition precedent to the issue of any such Interim Certificate, the Contractor shall have submitted to the Architect and to the Quantity Surveyor a claim for payment in respect of amounts eligible for inclusion in an Interim Certificate in accordance with the provisions of clause 30.2. Such claim should be supported by a detailed valuation”. A quick review of the history of BLL’s “loss and expense position”, demonstrates that BLL haven’t complied with these relevant provisions and therefore have not satisfied the condition precedent. Their interim applications have singularly failed to substantiate claims for loss and expense items by way of detailed valuation … The first that the Clinic knew of BLL’s current claim for loss and expense and Mr Wort’s10 June 2008 report on which the claim is based was when the Clinic received a draft referral notice under cover of the letter dated 7 July containing a “loss and expense” section. The nature of this claim was materially different to that which was the subject of the 2006 report from Mr Wort. Indeed, the Mr Wort’s (sic) subsequent report is significantly larger than the November 2006 document. In short, the Clinic maintain that BLL has never submitted an application for payment pursuant to clause 30.1.1.1 for monies allegedly due as loss and expense and as set out in Mr Wort’s 2008 report. Further, by letter dated 22 July, BLL confirmed to the Clinic that Mr Wort’s report upon which they rely to support this element of the claim had not previously been submitted. Accordingly, the Clinic would agree that the loss and expense elements of the referral be disregarded entirely by the Adjudicator and the Clinic. Alternatively, if the loss and expense elements are not disregarded entirely, the Clinic submits that the dispute on loss and expense become the subject of a further adjudication in respect of which the contractual rules would of course apply …’
“TB [the Adjudicator] queried why we’d asked this point, was it to gain more time? I said that we did want more time. He said that up until two weeks ago, he may not have had any discretion to grant extensions, however, following recent guidance from Akenhead J, TB now has that discretion. He queried what sort of extension I was seeking and I said until Friday would be suitable, 5 September. SB [Counsel for Bovis] said that although he cannot understand the grounds upon which are being relied to request an extension his view would be that no extension is warranted because the Clinic has had the claim for almost two months. I said that although we had the claim and the expert reports and witness statements, we’d not been provided with the documents relied upon and forming the bundle. SB said those were common to the parties. I said that regardless, it was a big job to try to get the documents together. I said that we needed time to get through the documents and to consult with the members of the professional team to consider the points in the Referral. I said we were doing our best to get a Response out. He [SB] then agreed to the extension until midnight, Thursday. This extension was then agreed and the procedure became regularised, in other words, there were no points that were going to be taken on the contents of the Referral Bundle and the Adjudicator’s appointment. TB raised the issue of a meeting with experts. He said that this was something he might like to do and felt could be very productive. He felt that lawyers need not attend. However, he was not going to exclude them. He said that the appropriate time for these meetings would be following the Response. On the material that he has read to date, he would like to definitely meet with Mr Marshall and possibly Mr Wort. I said that the Clinic had not yet made a decision on expert evidence for the Response … I said that a decision had not yet been taken. However, that as stated we were discussing the points in the Referral with the professional team. I said that if there was not sufficient time to obtain expert reports, then expert evidence could be incorporated into a Response. If the Clinic was not going to include expert evidence with its Response, the nature of the case was going to be opening up the Award/Certificate and in that regard, TB would still want to meet with TFB and Marshall …”
“6.3 The Clinic has employed experienced and competent solicitors. It has obviously taken care with the drafting of its Response. Costs have clearly not been an issue. It has been given every opportunity to put its best foot forward in this Reference and it has taken it; 6.4 It is all the more revealing, then, that the Response is almost entirely unsupported by factual or expert evidence …”
‘5. “No dispute”. 5.2 The correct characterisation of the dispute is of course fundamental to this, and any Adjudication. The Clinic’s position is that the Adjudicator had no jurisdiction to consider this issue because a loss and expense dispute has not crystallised. 5.3 There is clear authority for the contention that a dispute does not arise unless and until it emerges that a claim is not admitted … 5.5 Whilst the Clinic admits it received the draft Referral Notice, it denies that the failure to admit the claim for loss and expenses crystallised the dispute. The Clinic also denies that BLL must comply with clause 26. 5.6 The draft Referral contained the report from Mr Wort dated10 June 2008 which the Clinic had never seen. BLL rely on Mr Wort’s report to quantify the claim for loss and expense. The documents provided to the Clinic along with the draft Referral did not contain the necessary information to support a claim for loss and expense … 5.9 The Clinic submits that this 18 August letter did not crystallise the dispute on loss and expense. It is self-evident that further information was required in order for the claim to be considered as an application under clause 26. Rather than “not admit the claim”, the intention of the letter was to request further and necessary information. The Clinic’s view is that the true meaning and effect of this letter will be apparent to the Adjudicator … 5.10 Notwithstanding that a dispute had not crystallised (and without providing further information requested) BLL proceeded to refer a dispute to Adjudication and this dispute includes the claim for loss and expense in the sum of£3,287,245.44 . 5.11 On the basis that a dispute regarding this element of the claim has not crystallised, the Clinic submits that the Adjudicator has no jurisdiction.’
“As stated in our email of 2 December, the Clinic has repeatedly made the point that the Adjudicator lacked jurisdiction to decide the loss and expense elements of the Referral. In addition, the Clinic will challenge your application on the basis that the timing and manner in which your claim was presented and subsequently prosecuted and dealt with (by way of adjudication) amounted to an abuse of process and a breach of natural justice.”
“(1) The claim for loss and expense made in the Adjudication was new and based on new expert evidence. Therefore, there was no crystallised dispute in respect of the claim and the Adjudicator had no jurisdiction to determine the claim. (2) The nature and volume of new evidence served by Bovis for the purpose of the Adjudication and the timetable imposed on the Clinic in the Adjudication did not give the Clinic a fair or effective opportunity to respond to the new case. As such, the Decision was in breach of the rules of natural justice and invalid.”
“… has not in fact been told and is unaware in what respects it is alleged to have broken his obligations.”
“The common law rules of natural justice or procedural fairness are two-fold. First, the person affected has the right to prior notice and an effective opportunity to make representations before a decision is made. Secondly, the person affected has the right to an unbiased tribunal. These two requirements are conceptually distinct. It is quite possible to have a decision from an unbiased tribunal which is unfair because the losing party was denied an effective opportunity of making representations. Conversely, it is possible for a tribunal to allow the losing party an effective opportunity to make representations, but be biased. In either event, the decision will be in breach of natural justice, and be liable to be quashed if susceptible to judicial review, or (in the world of private law) to be held to be invalid and unenforceable.”
“Unless you agree to an extension of time I will not be able to produce my decision within 28 days.”
“On the severability issue, I conclude, albeit obiter in the result, as follows: (a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises. (b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so. (c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s). (d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference. (e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced. (f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court.” (a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises. (b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so. (c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s). (d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference. (e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced. (f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court.”
“If the Contractor makes written application to the Architect stating that he has incurred … direct loss and/or expense (of which the Contractor may give his quantification) in the execution of this Contract for which he would not be reimbursed by a payment under any other provision in this Contract … or because the regular progress of the Works or of any part thereof has been … materially affected by any one or more of the matters referred to in Clause 26.2; and if and as soon as the Architect is of the opinion that the direct loss and/or expense has been incurred … or that the regular progress of the Works or any part thereof has been or is likely to be so materially affected as set out in the application of the Contractor then the Architect from time to time thereafter shall ascertain, or instruct the Quantity Surveyor to ascertain, the amount of such loss and/or expense which has been or is being incurred by the Contractor; provided always that: 26.1.1 The Contractor’s application shall be made as soon as it has become, or should reasonably have become, apparent to him that the regular progress of the Works or of any part thereof has been or was likely to be affected as aforesaid; and 26.1.2 The Contractor shall in support of his application submit to the Architect upon request such information as should reasonably enable the Architect to form an opinion as aforesaid; and 26.1.3 The Contractor shall submit to the Architect or the Quantity Surveyor upon request such details of such loss and/or expense as are reasonably necessary for such ascertainment as aforesaid.” 26.1.1 The Contractor’s application shall be made as soon as it has become, or should reasonably have become, apparent to him that the regular progress of the Works or of any part thereof has been or was likely to be affected as aforesaid; and 26.1.2 The Contractor shall in support of his application submit to the Architect upon request such information as should reasonably enable the Architect to form an opinion as aforesaid; and 26.1.3 The Contractor shall submit to the Architect or the Quantity Surveyor upon request such details of such loss and/or expense as are reasonably necessary for such ascertainment as aforesaid.”