“[12] … the adjudicator did obviously err as he was not entitled to award any sum on account for work to be carried out [13] … This clause [Clause 6] does not permit the recovery of prospective costs on account. It permits only the recovery of incurred costs either by way of a set-off or by way of recovery of the debt. [14] Under the sub-contract the adjudicator should obviously not have produced the formulae he did to estimate the prospective costs of repair of the disputed defects. He was obviously wrong in respect of awarding a payment on account. It is agreed that the balance due in respect of the actual work is the sum of£12,679.52 . … [16] If I am wrong on the first issue and the defendant could have enforced the award straightaway for the full amount, then once the parties entered into an agreement for a standstill to allow the plaintiff to carry out the works and the plaintiff did carry out the works, the defendant then on the face of it is estopped from enforcing the award in respect of those works in respect of which an award was made on account. So again the same result is achieved. The defendant is entitled only to the sum of£12,679.52 which I order should be paid into court. It would be unconscionable in all the circumstances for the defendant to receive more. [17] What is required is another adjudication to assess what works have been carried out defectively or not carried out at all. [18] Having reached a settlement that required the plaintiff to carry out what were agreed works, it would be both unfair and unjust to allow the defendant once those works had been completed to turn the clock back to enforce the earlier adjudication award in respect of those very same works…”
“(1) a Post-Judgment Freezing Order (on notice) in the terms of the first attached order or such other terms as the Court deems fit. “(2) an Order in the terms of the second attached draft order or such other terms as the Court deems fit, including: “(a) a final Third Party Debt Order (“TPDO”), further to Flexidig’s application dated27 January 2021 and O’Farrell J’s interim TPDO dated29 January 2021 ; “(b) an Order in a similar vein as ordered in Blight and others v Brewster [2012] 1 W.L.R. 2841; “(c) an Order for the appointment of a receiver by way of equitable execution pursuant tosection 37 of the Senior Courts Act 1981 and/orCPR Part 69 .” “(a) a final Third Party Debt Order (“TPDO”), further to Flexidig’s application dated27 January 2021 and O’Farrell J’s interim TPDO dated29 January 2021 ; “(b) an Order in a similar vein as ordered in Blight and others v Brewster [2012] 1 W.L.R. 2841; “(c) an Order for the appointment of a receiver by way of equitable execution pursuant tosection 37 of the Senior Courts Act 1981 and/orCPR Part 69 .”
“3. The Respondent must not remove, or deal with or diminish the funds held on behalf of the Respondent by the Third Party in account ….. in the sum of£329,531.00 and frozen since3 February 2021 . “4. The Respondent must not: “(a) remove from England and Wales any of his assets which are in England or Wales up to the value of £[(1) if para 3 above is ordered, the additional sums owed by the Respondent to the Applicant, namely: (1) further interest to date; (2) the costs of the Claimant applying to this Court; and (3) sums owing further to the orders of the Northern Ireland High Court (including£12,993.73 for the fees of Mr White (the adjudicator in Adjudication 1) and£152,979.63 for costs further to the two orders of17 August 2020 ); or (2) if para 3 above is not ordered, the sum of£329,530.03 should be added to sum (1), producing a total in excess of£500,000 ].” “(a) remove from England and Wales any of his assets which are in England or Wales up to the value of £[(1) if para 3 above is ordered, the additional sums owed by the Respondent to the Applicant, namely: (1) further interest to date; (2) the costs of the Claimant applying to this Court; and (3) sums owing further to the orders of the Northern Ireland High Court (including£12,993.73 for the fees of Mr White (the adjudicator in Adjudication 1) and£152,979.63 for costs further to the two orders of17 August 2020 ); or (2) if para 3 above is not ordered, the sum of£329,530.03 should be added to sum (1), producing a total in excess of£500,000 ].”
“9. That the Receiver shall not without permission of the Judge receive more than the amount required to keep down the interest upon prior incumbrances, and to provide for the allowance to the Receiver and the allowed fees and costs of obtaining this order, and to pay to the Claimant what shall be due to him in respect of the debt and costs due to him, amounting to £[(1)£329,530.03 plus further interest to date; (2) the costs of the Claimant applying to this Court; and (3) sums owing further to the orders of the Northern Ireland High Court (including£12,993.73 for the fees of Mr White (the adjudicator in Adjudication 1) and£152,979.63 for costs further to the two orders of17 August 2020 ). (1) + (2) + (3) total in excess of£500,000 ].”
“Our client will pay the judgement sum of£329,531.00 . “We require your assistance to ensure that this payment is made from the frozen funds. “This is sent in open correspondence.”
“Our client (“M&M”) is committed to paying the sums which it accepts are due to your client (“Flexidig”) and either avoiding the need for a contested hearing on16 March 2021 , or at the very least reducing the scope of the matters which remain in dispute. Flexidig’s response to these attempts thus far appears to involve simply changing the nature and scope of what it is seeking to obtain from the Court in the Second Application. “To be clear, M&M proposes to take the following steps at the earliest possible opportunity: “1. To pay in full the order of Mr Justice Waksman of11 March 2020 . This is a judgment in the sum of£223,597.21 (including interest) plus VAT. Interest was ordered on this sum at a rate of 8% from11 March 2020 to date. Costs of£35,960 were also awarded. The adjudicator’s fees to which paragraph 7 refers have already been paid by M&M. Including interest which has accrued since11 March 2020 , M&M considers the total sum payable to discharge this order is£328,898.30 . This is less than the figure claimed in the application for a Third Party Debt Order. In the event that you consider a [greater] sum to be owing under the order of Mr Justice Waksman, please indicate what you consider that figure to be by return. “2. To pay the sum of£12,993.75 ordered by Mr Justice Horner in the High Court in Northern Ireland on13 December 2018 . “3. To pay the sum of£15,038.20 ordered by Mr Justice Horner in the High Court in Northern Ireland on17 August 2020 . “There are two practical issues in relation to taking those steps. The first is that the sum of£329,531.00 in M&M’s account is currently frozen pursuant to the freezing order made on12 March 2021 . M&M requires Flexidig to confirm in writing that these payments can be made from the frozen funds. The second is that M&M’s account imposes a limit on the amount which can be paid out from that account in a single day. M&M, accordingly, proposes that these payments be made across a period of six days, payments on days 15 being used to discharge the liability under the order of Mr Justice Waksman and the liability under the order of Mr Justice Horner being paid on the sixth day. “This leaves three matters raised in your email of13 March 2020 : “1. By his order of17 August 2020 , Mr Justice Horner made two cost orders, one that M&M pay Flexidig’s costs of an action and an application. Both orders were made on the basis that the costs “shall be taxed in default of agreement”
“The arguments against granting an injunction extending to assets outside the jurisdiction are much weaker in a case where judgment has been obtained than in a case where an interlocutory order is sought before trial (Babanaft International Co SA v Bassatne, op. cit. per Kerr LJ, and Neill LJ, and Republic of Haiti v Duvalier [1990] 1 Q.B. 202; [1989] 1 All E.R. 456 at 465, CA, per Staughton LJ). In the former situation the court is no longer so concerned to protect the defendant.”
“37. We sought to address the matters for which Mr Baldwin had ordered the on account payment. “38. I gave evidence on this in my affidavit to the Northern Ireland High court dated20 November 2019 , at paragraphs 1329. “39. In summary, M & M issued several spurious stop work notices (which as the name suggests forced us to stop work immediately), which we robustly challenged. “40. Much of our work was signed off by the local authority, Lincolnshire County Council. While it was Virgin Media who engaged M&M, Lincolnshire County Council was the owner of the footpath/road assets in which we were excavating. Therefore the Council had final say on the quality of our works. “41. Virgin Media and Lincolnshire County Council seemed happy with our works. “42. Unfortunately M & M’s Chief Executive, Gareth Loye, was not happy, as we were diminishing M&M’s claim against Flexidig. “43. Mr Justice Horner referred to what happened in his judgment on2 December 2019 ….. He stated at paragraph 6 of his judgment: “Mr Lloye [sic – Loye] of the defendant on28 August 2019 allegedly told Mr Bett of the plaintiff that he could not allow the plaintiff to proceed with any remedial work because it was diminishing the value of the adjudication award and that he intended to instruct other contractors presumably to run up costs until the plaintiff was “buried.”
“13. I find this allegation particularly surprising in the current context because I do not understand how the liquidation of Flexidig could possibly benefit either me personally or M&M. The dispute between Flexidig and M&M has persisted for a considerable period and has not yet concluded. I understand that if Flexidig were to enter liquidation (or some other insolvency process) M&M would still be liable for any debts owed to Flexidig and could be pursued by the liquidator (or other officeholder) to recover those debts. “14. Conversely, if Flexidig entered liquidation, M&M would, in my experience, be faced with limited prospects of recovering anything from the liquidation as an unsecured creditor in respect of liabilities from Flexidig to M&M. “15. In fact, not only do I expressly hope that Flexidig remains solvent, I am particularly concerned, on behalf of M&M, that Mr Bett intends, over the coming months, to liquidate Flexidig and to transfer its business and assets to another company.”
“Good grounds for alleging that the defendant has been dishonest is relevant, taking into account any answers to the allegations. If and to the extent the substantive claims cast any light on the risk of dissipation, the fact that a defendant has respectable defences to those claims has a bearing on the existence of a real risk of dissipation. Dishonesty is not essential to the exercise of the jurisdiction and there is no need to show an intention to dissipate assets. But if there is a good arguable case in support of an allegation that the defendant has acted fraudulently or dishonestly (e.g. being implicated in an ingenious scheme for the misappropriation of funds belonging to the claimant), or with an unacceptably low standard of commercial morality, whether dishonest or not, giving rise to a feeling of uneasiness about the defendant, then it is often unnecessary for there to be any further specific evidence on risk of dissipation for the court to be entitled to take the view that there is a sufficient risk to justify granting Mareva relief. For this the dishonesty or other misconduct must be relevant to risk of dissipation, pointing to the conclusion that assets may be dissipated. Not every act of dishonesty is relevant to this. Once the risk of dissipation is shown, the limit of the Mareva relief will take into account claims for which the claimant has a good arguable case, including those which do not involve such an allegation.”
“… in a post-judgment context, the policy of the law weighs heavily in favour of the enforcement of judgments. This is clear from the decision of the CA in Emmott v Michael Wilson & Partners Ltd[2019] 4 WLR 53 , at paragraphs 44 and 53-56 (Gross LJ).”
“The nature of the remedy is more intrusive, more expensive, and less reversible than the granting of an injunction. The receiver has to be paid. The defendant no longer has control of the assets. Irreparable damage may be done to the business of the defendant through the publicity ….”
“These dicta all show that the policy of the law is to enforce judgments (and particularly so where the judgment enforces a London arbitration Award) so that freezing orders can, in an appropriate case, be granted after judgment. They also show that such orders may more readily be made after judgment than before. That may be because it is easier to infer a risk a dissipation. Thus, in Distributori Automatici Italia v Holford General Trading[1985] 1 WLR 1066 at p.1073 Leggatt J. cited with approval the dictum of Farquharson J. in Orwell Steel v Asphalt and Tarmac[1984] 1 WLR 1097 that "in one sense it could be said that there is greater justification for restraining a defendant from disposing of his assets after judgment than before any claim has been established against him." Leggatt J. agreed that "grounds for believing that the judgment debtor would dispose of his assets before execution might perhaps be more readily established after judgment than before." It may also be because factors which are said to weigh against the making a freezing order (for example delay or the absence of assets within this country and the presence of related proceedings in another jurisdiction, two of the factors relied upon in this case) have less weight where judgment has already been obtained. In circumstances where judgment has been given and there is solid evidence of a real risk of dissipation there would have to be particularly strong grounds for refusing freezing order relief.” (emphasis added) order: it is by no means necessarily the same in respect of post-judgment orders.