“If the Defendant accepts the offer within 21 days of the date of this letter (the ‘Relevant Period’), the Defendant will be liable for the Claimant’s costs of the Proceedings (including pre-action costs) up to the date on which written notice of acceptance of this Offer is received by the Claimant, in accordance withCPR 36.13 .”
“… the offer will be open for 21 days from the date of this letter (the ‘relevant period’).”
“The court is reluctant to hold that parts of a contract are inconsistent with each other, and will give effect to any reasonable construction which harmonises such clauses.”
“It is artificial to start with an acontextual preconception about the meaning of words used and then see whether that meaning is somehow displaced.”
“The meaning which a document (or any other utterance) would convey to a reasonable man is not the same thing as the meaning of its words. The meaning of words is a matter for dictionaries and grammars; the meaning of the document is what the parties using those words against the relevant background would reasonably have been understood to mean. The background may not merely enable the reasonable man to choose between the possible meanings of words which are ambiguous but even (as occasionally happens in ordinary life) to conclude that the parties must, for whatever reason, have used the wrong words or syntax …”
“Any ambiguity in an offer purporting to be a Part 36 offer should be construed so far as reasonably possible as complying with Part 36. Once it is accepted that a timelimited offer does not comply with Part 36, one must approach the interpretation of the offer in this case on the basis that the party making the offer, and the party receiving it, appreciated that fact.”
“Here the offer was not a Part 36 offer because it failed to comply with the mandatory and highly prescriptive requirements of the current ‘self-contained code.’ In these circumstances it is not necessary to engage in the construction exercise invited by Mr Rivers. No process of construction, however liberal, can bring satisfaction of procedural requirements which were not fulfilled.” 18.3 Pitchford LJ added, at [27]: “In the present case we are not concerned with a Part 36 offer presented as such and ‘otherwise complying with its form’ … We are concerned with an offer that purports to be made under Part 36, but whose terms are completely inconsistent with Part 36 and that fails otherwise to comply with its form.”
“Nothing in this Section prevents a party making an offer to settle in whatever way that party chooses, but if the offer is not made in accordance with rule 36.5, it will not have the consequences specified in this Section.”
“Those consequences are not sought in the present case, even though PHI’s offer was a claimant’s offer. The point therefore does not arise for decision, but for my part I do not see how the court could award the additional interest unless the offer was a Part 36 offer properly so-called. Even a minor formal or technical defect would be fatal to that entitlement. So far as indemnity costs are concerned, they can of course be awarded under the general provisions as to costs, but absent a true Part 36 offer a claimant’s claim for indemnity costs would have to be justified on the relevant general principles, not just by arguing that the offer only just failed to comply with Part 36.”
“Given the facts there can be no quarrel at all with the overall result in the Fitzroy Robinson case; nor can there be any quarrel with the judge having regard to the without prejudice save as to costs offers as part of the relevant material in deciding overall whether to order indemnity costs. But in my respectful view, it goes altogether too far to take into account as a factor that, had only those offers been made as Part 36 offers, then indemnity costs would have been payable as a matter of course. That is a course neither mandated nor permitted either under Part 36 or under r.44.3. Similarly, while the result in the Huntley case may be capable of being justified on the special facts, in my view it is not permissible wholly to discount a number of failures to comply with the requirements of Part 36 as the merest technicality. Perhaps there can be de minimis errors or obvious slips which mislead no one: but the general rule, in my opinion, is that for an offer to be a Part 36 offer it must strictly comply with the requirements.”
“Should the Defendant require any clarification as to the terms of this Offer, or should the Defendant consider this Offer to be in any way defective or noncompliant with Part 36 of the CPR, please notify us by return and in any event within seven days of the date of this letter. Any failure to do so will be relied on by the Claimant to preclude the Defendant from attempting to avoid the adverse costs consequences of Part 36.”
“… in any event the letter of14 May 2010 made it clear that if the offer was in any way defective or non-compliant with Part 36, Mr and Mrs Ho’s solicitors were asked to let them know as soon as possible. It seems to us clear that, not only did the solicitors treat the offer as a Part 36 offer in the light of the hearing of the appeal, but they also accepted it as a Part 36 offer in their letter of21 September 2010 .”
“Although Thomas LJ did not express himself in this way, it appears to me that his reasoning was that Mr and Mrs Ho were estopped from challenging the validity of the Part 36 offer made by Mr and Mrs Seeff. In my judgment, this reasoning is equally applicable to the present case.”
“Nothing in this Section precludes a party making an offer to settle in whatever way the party chooses, but if the offer is not made in accordance with rule 36.5, it will not have the consequences specified in this Section. (Rule 44.2 requires the court to consider an offer to settle that does not have the costs consequences set out in this Section in deciding what order to make about costs.)”
“Basic concepts of offer and acceptance clearly underpin Part 36, but that is inevitable given that it contains a voluntary procedure under which either party may take the initiative to bring about a consensual resolution of the dispute. Such concepts are part of the landscape in which everyone conducts their daily life. It does not follow, however, that Part 36 should be understood as incorporating all the rules of law governing the formation of contracts, some of which are quite technical in nature. Indeed, it is not desirable that it should do so. Certainty is as much to be commended in procedural as in substantive law, especially, perhaps in a procedural code which must be understood and followed by ordinary citizens who wish to conduct their own litigation. In my view, Part 36 was drafted with these considerations in mind and is to be read and understood according to its terms without importing other rules derived from the general law, save where that was clearly intended.”
“(i) The Defendant has failed, in breach of contract, to achieve Service Commencement by the Acceptance Longstop Date under the Contract. (ii) The Defendant’s design for the Facility once executed was at all material times incapable of passing the contractual Acceptance Tests, and has not passed the contractual Acceptance Tests as at the date of the Defendant’s acceptance of this Offer. (iii) The Defendant is not entitled to operate the modifications made to the Facility for the production of QSRF. (iv) The Authority is entitled to terminate the Contract under clause 67. (v) The composition tests carried out by UBB between Q1 2016 and Q3 2018 were not valid Composition Tests as defined by the Contract, and the results of such tests are of no contractual effect and did not engage Clause 21.9A.2 of the Contract. (vi) The Composition Test results are to be determined during the Commissioning Period on a rolling annual average basis using the average results from the four most recent Composition Tests (or, where there are less than four Composition Tests, the average of the available Composition Tests). (vii) The requirements for an Impact and Remedy Report (Clause 21.9A.2 of the Contract) is only engaged if the results of the four most recent Composition Tests (or where there are less than four Composition Tests, the average of the available Composition Tests) confirm, on a rolling annual average basis, that the composition of the input Contract Waste does not fall within Composition Band A.” (ii) The Defendant’s design for the Facility once executed was at all material times incapable of passing the contractual Acceptance Tests, and has not passed the contractual Acceptance Tests as at the date of the Defendant’s acceptance of this Offer. (iii) The Defendant is not entitled to operate the modifications made to the Facility for the production of QSRF. (iv) The Authority is entitled to terminate the Contract under clause 67. (v) The composition tests carried out by UBB between Q1 2016 and Q3 2018 were not valid Composition Tests as defined by the Contract, and the results of such tests are of no contractual effect and did not engage Clause 21.9A.2 of the Contract. (vi) The Composition Test results are to be determined during the Commissioning Period on a rolling annual average basis using the average results from the four most recent Composition Tests (or, where there are less than four Composition Tests, the average of the available Composition Tests). (vii) The requirements for an Impact and Remedy Report (Clause 21.9A.2 of the Contract) is only engaged if the results of the four most recent Composition Tests (or where there are less than four Composition Tests, the average of the available Composition Tests) confirm, on a rolling annual average basis, that the composition of the input Contract Waste does not fall within Composition Band A.”
“That does not, however, indicate that some of the factors I have already mentioned may not be relevant. Moreover, once again I do not regard the award as purely compensatory. As I have also said, different factors may in practice apply to the enhanced interest under [rules 36.17(4)(a)/(c)]. That is because account may need to be taken of how the costs, on which an enhanced rate of interest is claimed, were incurred. It could have been, for example, that despite the fact that it was unreasonable to refuse the Part 36 offer, the conduct of the litigation was itself reasonable, so that the costs on which enhanced interest was sought were not incurred in contesting bad points or dishonesty by the defendants.”
“(4) In deciding what order (if any) to make about costs, the court will have regard to all the circumstances, including– (a) the conduct of all the parties; (b) whether a party has succeeded on part of its case, even if that party has not been wholly successful; and (c) any admissible offer to settle made by a party which is drawn to the court’s attention, and which is not an offer to which costs consequences under Part 36 apply. (5) The conduct of the parties includes– (a) conduct before, as well as during, the proceedings and in particular the extent to which the parties followed the Practice Direction – Pre-Action Conduct or any relevant pre-action protocol; (b) whether it was reasonable for a party to raise, pursue or contest a particular allegation or issue; (c) the manner in which a party has pursued or defended its case or a particular allegation or issue; and (d) whether a claimant who has succeeded in the claim, in whole or in part, exaggerated its claim.” (b) whether a party has succeeded on part of its case, even if that party has not been wholly successful; and (c) any admissible offer to settle made by a party which is drawn to the court’s attention, and which is not an offer to which costs consequences under Part 36 apply. (a) conduct before, as well as during, the proceedings and in particular the extent to which the parties followed the Practice Direction – Pre-Action Conduct or any relevant pre-action protocol; (b) whether it was reasonable for a party to raise, pursue or contest a particular allegation or issue; (c) the manner in which a party has pursued or defended its case or a particular allegation or issue; and (d) whether a claimant who has succeeded in the claim, in whole or in part, exaggerated its claim.”
“(i) The discretion to award indemnity costs is a wide one and must be exercised taking into account all the circumstances and considering the matters complained of in the context of the overall litigation (see Three Rivers DC v. The Governor of the Bank of England[2006] EWHC 816 (Comm) and Digicel. (ii) Dishonesty or moral blame does not have to be established to justify indemnity costs(see Reid Minty v. Taylor [2002] 1 W.L.R. 2800). (iii) The conduct of experts can justify an order for indemnity costs in respect of costs generated by them (see Williams v. Jervis[2009] EWHC 1837 (QB) . (iv) A failure to comply with Pre-Action Protocol requirements could result in indemnity costs being awarded. (v) A refusal to mediate or engage in mediation or some other alternative dispute resolution procedure could justify an award of indemnity costs.”
“Where a claim is speculative, weak, opportunistic or thin, a claimant who pursues it is taking a high risk and can expect to pay indemnity costs if it fails.”
“Plainly, Mr Faraldo was contemplating that UBB might be able to seize upon the latest composition data to blame the waste for all ills and propose the acceptance of the QSRF Line and other modifications as part of the necessary solution, all at the Authority’s cost. It was an audacious plan given that the true causes of the facility’s inability to pass the tests were the serious density design error and the unrealistic BMW reduction bid.”