“41 In relation to the alleged notices. The 2017 notices relate to the delay in commencing the work. There seems to be a disagreement about it, but it is common ground that EAG did commence on11 September 2017 . 42 As for the alleged notice on5 April 2018 , it is of limited consequence as it does not notify all the items now claimed and some of the claims are clearly not within 14 days of the event first occurring. 43 As for the events of 25 to 29 June I can see no evidence that ISG agreed to consider EAG’s entitlement to an extension of time without reference to clause 9. 44 Save for the limited effects of 5th April letter I am aware of no further valid notice.” (4) He referred to the onus and burden of proving a delay claim and, having recorded the arguments as advanced by the parties, said this: “48 The issue about whether the contract places on either party a burden of proof is not the real issue. The point is that in Adjudication as in litigation the party that asserts must prove. 49 That said, the only obligation upon EAG is to give notice of the delay and an estimate of the effect within 14 days of the event first occurring. There is no obligation to provide a programme let alone a critical path network. 50 Whereas the obligation upon ISG is to demonstrate that the alleged losses were incurred or may be incurred in consequence of the breach and the breach caused or contributed to a delay to practical completion. 51 The main assertion in this dispute is ISG’s assertion that EAG are responsible for 20 weeks delay and as a consequence ISG have incurred or may incur£3,183,000 . It is for ISG to prove this liability. 52 EAG’s position is that they have excuses for not performing and that ISG has not proven that EAG caused or contributed to any loss in consequence of any alleged breach. Insofar as EAG seek to demonstrate an extension of time it is for them to prove an entitlement.” (5) He then considered in some detail the respective assertions of the parties as to the causes of delay. Under a section headed “Summary of delay” he stated that: “91 Given the Parties submissions and given the lack of useful programming analysis I have no choice but to form an impressionistic view of the delays. 92 As such whilst there has been some significant delay to the project, I am also satisfied that EAG have some culpability for some of the delay 93 In my view EAG have excuses for their non-performance up to22 October 2018 .” (6) He then considered the respective assertions of the parties as to the bona fide estimate relied upon by the claimant. He stated that: (i) He did have the power to open up and review the bona fide estimate, on the basis that the “final determination” referred to in clause 9(8) was not that of the claimant itself but of the court and, thus, of an adjudicator as well. (ii) As regards causation: (a) the link had to be between the breach in failing to give notice and the delay to the main contract works, and the claimant had failed to establish any such link; (b) in any event the claimant had failed to establish a link between the delay to the subcontract and the 20 weeks delay to the main contract, in the absence of a detailed analysis. He concluded at [151] that “a proper bona fide estimate could not have concluded that EAG were liable for 20 out of 45 weeks delay” and at [152] that “as such I Decide that ISG has not demonstrated and proved that EAG was responsible for causing 20 weeks delay to the works to be carried out by ISG under the Main/Principal Contract”. (iii) He therefore concluded and decided at [163] that “as at valuation No 35 ISG did not provide a bona fide estimate of any loss or damages consequent upon any breach of contract. Accordingly, ISG must repay EAG the amount deducted”. (iv) Under the concluding section headed “Relief” he decided that: “173.1 A fair and reasonable date for completion of the EAG Sub-Contract works is22 October 2018 . 173.2 ISG has not demonstrated and proved that EAG was responsible for causing 173.2 ISG has not demonstrated and proved that EAG was responsible for causing 20. Contract and therefore I set aside the bona fide estimate by ISG in relation to application for payment no 35. 173.3. ISG shall pay EAG the sum of£137,434.53 immediately.”
“The Court’s power to make declarations is derived from section 19 of the Senior Courts Act. The power to make declarations is discretionary.CPR 40.20 provides that the Court may make binding declarations whether or not any other remedy is claimed. ISG has to satisfy the court that declaratory relief should be granted as a matter of discretion. The exercise of the discretion involves considering justice to the claimant, justice to the defendant, whether the declaration would serve a useful purpose and whether there are any other special reasons why or why not the court should grant the declaration: see CIP Property (AIPT) Ltd v Transport for London[2012] EWHC 259 (Ch) ;[2012] BLR 202 at [24-26], Network Rail Infrastructure Ltd v ABC Electrification Ltd[2019] EWHC 1769 (TCC) ;[2019] BLR 522 at [10-11] and Pfizer Ltd v F. Hoffman-La Roche AG[2019] EWHC 1520 (Pat) at [61-67].”