“any cost due to negligence or default on the part of the Contractor in his compliance with any of his obligations under the Contract and/or due to any negligence or default on the part of the Contractor’s employees, agents, sub-contractors or suppliers in their compliance with any of their respective obligations under their contracts with the Contractor”
“The term ‘Disallowed Cost’ in the Contract includes any cost incurred due to default on the part of the Contractor if, and only insofar as, the default constitutes a wilfuland deliberate failure to comply with his obligations under the Contract”
“… if the Employer’s Representative certifies in writing to the Employer with a copy to the Contractor that in his opinion the Contractor (e) has abandoned the Contract without due cause or (f) without reasonable excuse has failed to commence the Works in accordance with Clause 41 or (g) has suspended the progress of the Works without due cause for 14 days after receiving from the Employer’s Representative written notice to proceed or (h) has failed to remove goods or materials from the Site or to pull down and replace work for 14 days after receiving from the Employer’s Representative written notice that the said goods materials or work has been condemned and rejected by the Employer’s Representative or (i) despite previous warnings by the Employer’s Representative in writing is failing to proceed with the Works with due diligence or is otherwise persistently or fundamentally in breach of his obligations under the Contract, then the Employer after giving 7 days notice in writing to the Contractor specifying the event relied on may enter on the Works and any other parts of the Site provided by the Employer and expel the Contractor therefrom without thereby avoiding the Contract or releasing the Contractor from any of his obligations under the Contract.”
“(i) the cost of work of repair amendment reconstruction and rectification or making good defects where such work is carried out to parts of the Works supplied or carried out by sub-contractors and is required under the term of the sub-contract to be at the sub-contractor's expense (ii) the cost of repair amendment reconstruction rectification and making good defects after the date of substantial completion which in the opinion of the Employer's Representative is necessary solely due to the use of materials or workmanship not in accordance with the Contract” 34.2 In addition, Mr Sears points out that these clauses make very specific provision for the detailed circumstances in which non-compliance with contractual obligations will give rise to Disallowed Cost. In relation to clause 1(1)(j)(i), only where the cost of such work is required under the term of the sub-contract to be at the sub-contractor’s expense, and in the case of clause 1(1)(j)(ii), which is mirrored in clause 49(3), only where costs are incurred after the date of substantial completion. Accordingly, he says, the parties cannot have intended the words in clause 1(1)(j)(iii) to cover any cost due to any failure on the part of the Contractor to comply with its obligations under the Contract: first because such a reading would render other provisions of the Contract redundant and second because the parties were plainly concerned to identify detailed circumstances which would give rise to Disallowed Cost. 34.3 Mr Sears relies in particular on the following extract from the speech of Lord Neuberger in Arnold v Britton at [17]: “Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in the contract. And again, save in a very unusual case, the parties must have been specifically focussing on the issue covered by the provision when agreeing the wording of that provision”