“The court’s task is to ascertain the objective meaning of the language which the parties have chosen to express their agreement”
“we cannot accept the contract for Heysham in its present format”
“10.0 Liquidated damages payable by CBUK 10.1 Limited to 10% of the agreed subcontract price”
“10.0 Damages payable by CBUK 10.1 Liability for damages shall be limited to 10% of CBUK’s price. (Subcontractor’s damages shall be limited to 10% of the Subcontract Price). Subcontractor’s liability shall only apply if the subcontracted works over-run the Main Contract Programme period of 2 weeks”
“2. Clause 1(c) We are deemed to have knowledge of CBUK contract with Costain and it forms the third item in the order of precedence of the documents after the Appendix and CBUK standard conditions. Have Sarens seen a copy? 3. Clause 1(c) There is an uncapped total liability (mainly insurance would cover this) but a capped amount on liquidated damages at 10%, i.e.£96,363.44 which can be applied. Discussed later. (This reference to “discussed later” is clearly a reference to the fact that the point arises again later in the comments). 15…Part 1 Section 10 Liquidated damages limited to 10% of the agreed subcontract price. I would suggest that each structure is limited if possible with an understanding of how damages are applied (daily rate). This may be clear from the CBUK s/c with Costain.”
“10.0 Liquidated damages payable by CBUK 10.1 Limited to 10% of the agreed subcontract price”
“10.0 Liquidated damages payable by CBUK 10.1 Limited to 10% of the agreed subcontract price”
“Following our discussion on Friday, attached are the clause 10 liquidated damages sections from the Heysham and Thorley Lane projects. To be able to sign the contracts we need a sentence stipulating the rate of application i.e. 1% per week to a maximum of 10%. This should also apply to any other pending contracts.” a. Attached to the email was an extract from the third iteration of the Subcontract and, in particular, Paragraph 10. Next to the wording at 10.1 was written, in hand: “To be applied at 1% per week up to a maximum of 10%”
“Can you confirm the below point about the 60 day damages holiday please. This will allow us to sign the contract here.”
“10.0 Damages payable by CBUK 10.1 Liability for damages shall be limited to 10% of CBUK’s price. (Subcontractor’s damages shall be limited to 10% of the Subcontract Price)”
“In circumstances where works have been carried out, it will usually be implausible to argue that there was no contract. In G Percy Trentham v Archital Luxfer Limited[1993] 1 Lloyds Rep 25 Steyn LJ said: “One must not lose sight of the commercial character of the transaction. It involved the carrying out of work on one side in return for payment by the other side, the performance by both sides being subject to agreed qualifying stipulations…The judge analysed the matter in terms of offer and acceptance. I agree with his conclusion. But I am , in any event, satisfied that in this fully executed transaction a contract came into existence during performance even if it cannot be precisely analysed in terms of offer and acceptance. And it does not matter that a contract came into existence after part of the work had been carried out and paid for”
“Limited to 10% of the agreed subcontract price to be applied at 1% per week up to a maximum of 10%”
“The proper interpretation of that clause in the document is that any liquidated damages payable by CBUK to Costain under the Costain Contract would be capped at 10% of Sarens’ subcontract value if CBUK were to seek to pass down that loss to Sarens. In other words CBUK’s claim against Sarens would be for unliquidated damages for delay up to a cap of 10% of Sarens’ subcontract value, which would be a pass down of CBUK’s liability to Costain for liquidated damages. That is the general agreed cap”
“The Subcontractor shall at all times indemnify CBUK against all liabilities to other persons for bodily injury, or damage to property which may arise in consequence of the execution of the Subcontract Works…”