“Please find attached the updated documents we propose to use for design work. The Terms and Conditions document is merely tidied up as I understand. The Protocol document is intended to be the instrument that creates the Agreement. It will be necessary to agree particular schedules for each contract in addition to these and further minor amendments may still be required. We intend to use the documents for the Wellcome Building works subject to your agreement and we will be providing more details shortly. Accordingly I would be grateful if you could make any comments you may have as soon as possible as we are about to start your works on the above basis on this contract.”
“The Consultant’s liability for defective work under the Agreement shall be limited to whichever is the lesser of the following: (a) The reasonable direct costs of repair, renewal and/or reinstatement of any part or part of the Sub-Contract Works to the extent that the Client incurs such costs and/or is or becomes liable either directly or by way of financial contribution for such costs; or (b) The sum stated in Schedule 1.”
“I understand that discussions between David Shotliff and Stewart Tyler on the Design Services Agreement are well advanced. However, it may still take a little time before this Agreement is formally signed. In the meantime I should be grateful if you would confirm that you would underwrite our fees for the design and drawing work and in order that there is a basis for these, propose the following schedule of rates…”
“Your work done under this instruction is to be on the basis of our instructions from Wates and the conditions and terms detailed in the Protocol Agreement, Design Consultancy Terms and Conditions in your possession at present. It is our intention to enter these Agreements with yourselves in their present form with such minor amendments as maybe mutually agreed and to award you the Design Works on the Wellcome Building Precast Concrete Package in the sum of£55,000 as previously agreed. Pending formalisation of these Agreements, we will pay you for work done under this instruction up to a maximum£10,000 . Once the Agreements are executed their terms and conditions shall supersede this letter and shall govern any work done retrospectively.”
“We are currently preparing our tender for a precast concrete frame and associated works at the above contract and would be pleased to receive your keenest fixed price quotation for the supply of design services as detailed herein…”
“(1) Agreement on the terms and conditions of our appointment for provision of the services (2) Agreement of commencement date and the design programme … (4) Any variations or additional services required to be charged on a time basis at rates to be agreed…”
“We have requested a completed Sub-Contract and will advise in due course of any changes to the Schedules arising. A PI insurance requirement of£5m is identified. Whilst the terms of the Warranty have yet to be agreed, we have attached a Franklin Andrews Consultant / Employer warranty document which we are advised will be applicable. We are, however, unable to confirm this at this stage, as sub-contract details have still to be finalised. In the meantime, you are to continue with work on the basis of the foregoing and our instructions from Wates. Pending finalisation of the Agreement, we will pay you for work done under this and our previous instruction to£40,000 .”
“I believe that the changes made to these documents will provide some comfort in respect of the concerns you have expressed”
“I think Clause 24 of the T’s and C’s needs amending. Suggest the following: ‘the Consultant’s Liability for defective design and excluding amounts for which the Consultant is liable under the terms of the PI insurances provided under the Agreement is limited to the sums stated in Schedule 1’.”
“It was noted that the formal detail design commencement date and Frozen Scheme date are both11 February 2002 and that you wished to commence on that date. I confirm that the start has been made but should be grateful for a formal letter of instruction and limitation of expenditure subject to preparation and signature of the services agreement in due course.”
“Hampshire Centre – Castlepoint Car Park We have received an initial letter of intent for this project. The letter includes an instruction to commence work. Accordingly, we confirm our instructions to yourselves to commence design and detailing work on this project. Your work is to be carried out in accordance to the Protocol Agreement and Terms and Conditions associated that we are currently working under with yourselves, the Design Scope and Deliverables document for Castlepoint Car Park previously provided (copy attached) and your quotation of28 November 2001 in the sum of£285,000 . We also require you to carry out further works as instructed by ourselves under the same terms and conditions. Pending finalisation of the Agreement and our directions on this project, we will pay you for work done under our instructions up to a maximum of£56,000 . Once the Agreement is executed and the Schedules for this project completed, their terms and conditions shall supersede this letter and shall govern any work done retrospectively. Please note where there will be requirements to enter into design warranties on this contract.”
“Design Agreement We wish to formally confirm the basis of our design and detailing work placed with yourselves. We consider that the Protocol Agreement, Terms and Conditions, Contract Schedules and Instructions documents should apply to all work executed for ourselves. Copies of the documents are enclosed. There are some minor amendments, in particular to the limitation of liability clause. We believe that they should be acceptable to yourselves. We trust that you will be able to agree to execution of the Protocol Agreement and would appreciate your confirmation. We consider that a PI insurance level of£5m will generally be suitable but may require a£10m cover if contracts entered into so require. We do not anticipate any requirement for Performance Bonds for presently anticipated work.”
“The limit, if any, on the Consultant’s liability (as referred to in Clause 2A) is£610,515 – 10% of sub-contract package for uninsured losses.”
“2A LIMIT OF LIABILITY (a) The Consultant’s liability in respect of his design shall be no greater than the Client’s liability under the Sub-Contract. (b) The Consultant shall be liable for the reasonable direct costs of repair, renewal and/or reinstatement of any part or parts of the Sub-Contract Works to the extent that the Client incurs such costs and is or becomes liable either directly or by way of financial contribution for such cost due to a breach by the Consultant of his obligations under this Agreement. (c) Where the Consultant is in breach of this Agreement, otherwise than for a failure to use reasonable skill, care and diligence and the Client incurs any costs, losses, expenses or damages other than those indicated in (b) above, the liability of the Consultant shall be limited to the sum stated in Schedule 1.”
“... (1) Appointment and instructions to proceed. We have today received a letter of instruction from David Shotliff, for which I thank you …”
“Thank you for your letter dated6th March 2002 instructing us to commence design and detailing work. Since our original offer dated28 November 2001 , there has been further discussion on the extent of services required and a revised offer, excluding the design element, was made in our letter dated1st February 2002 . It was subsequently decided by C V Buchan that design services were required and a revised Design Scope and Deliverables schedule was issued to us, at the “kick-off” meeting held on 7th February, as per the schedule attached to your letter. Following the meeting, we wrote to you on the12th February 2002 , copy of letter attached, setting out the main points arising. You will note from this that there are variations to our original offer and these have still to be agreed for incorporation into our formal agreement. There have also been discussions and correspondence with Kevin Wrigglesworth regarding additional work that we are doing on the general layout and issues delaying the design and detailing but believe that these can be dealt with under the terms of our Protocol Agreement.”
“The Schedules for particular contracts will be forwarded under separate cover within a few days.”
“45. …It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a precondition to a concluded and legally binding agreement.”
“One must not lose sight of the commercial character of the transaction. It involved the carrying out of work on one side in return for payment by the other side, the performance by both sides being subject to agreed qualifying stipulations. In the negotiations and during the performance of phase 1 of the work all obstacles to the formation of a contract were removed. It is not a case where there was a continuing stipulation that a contract would only come into existence if a written agreement was concluded. Plainly the parties intended to enter into binding contractual relations. The only question is whether they succeeded in doing so…The judge analysed the matter in terms of offer and acceptance. I agree with his conclusion. But I am, in any event, satisfied that in this fully executed transaction a contract came into existence during performance even if it cannot be precisely analysed in terms of offer and acceptance. And it does not matter that a contract came into existence after part of the work had been carried out and paid for.”