“The court may give summary judgment against a claimant or a defendant on the whole of a claim or on a particular issue if— (a) it considers that - (i) that claimant has no real prospect of succeeding on the claim or issue; or (ii) that defendant has no real prospect of successfully defending the claim or issue; and (b) there is no other compelling reason why the case or issue should be disposed of at a trial.”
“…if the respondent’s case is bad in law, he will in truth have no real prospect of succeeding on his claim or successfully defending the claim against him, as the case may be. Similarly, if the applicant’s case is bad in law, the sooner that is determined the better”
“The Dunne Group Limited (Company No.SC255658), whose registered office is at Inchmuir Road, Whitehill Industrial Estate, Bathgate, West Lothian EH48 2EW and GORDON DUNNE of Inchmuir Road, Whitehill Industrial Estate, Bathgate, West Lothian EH48 2EW (jointly and severally referred to as the “Guarantor”).”
"…Quite apart from raising abstruse issues as to who is the proferens (and, in particular, whether the issue turns on the precise facts of the case or hypothetical analysis), "rules" of interpretation such as contra proferentem are rarely decisive as to the meaning of any provisions of a commercial contract. The words used, commercial sense, and the documentary and factual context, are, and should be, normally enough to determine the meaning of a contractual provision."
“The contra proferentem rule requires any ambiguity in an exemption clause to be resolved against the party who put the clause forward and relies upon it. In relation to commercial contracts, negotiated between parties of equal bargaining power, that rule now has a very limited role. Lord Neuberger MR summarised the position succinctly in K/S Victoria Street v House of Fraser (Stores Management) Ltd[2011] EWCA Civ 904 ;[2012] Ch 497 at [68] [he then quoted from the passage above in paragraph 28 of this judgment and continued]. The judgment of Moore-Bick LJ in Transocean Drilling UK Ltd v Providence Resources PLC[2016] EWCA Civ 372 ; [2016] 2 Lloyd's LR 51 at [20] to [21] is to similar effect.”
“First, the reliance placed in some cases on commercial common sense and surrounding circumstances (eg in Chartbrook, paras 16-26) should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most obviously to be gleaned from the language of the provision. Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in a contract. And, again save perhaps in a very unusual case, the parties must have been specifically focussing on the issue covered by the provision when agreeing the wording of that provision.”
“The particular label that the parties apply to the document is not determinative, nor very significant if the wording points in the opposite direction.”
“3.1B The Guarantor irrevocably and unconditionally guarantees, warrants and undertakes jointly and severally to the Contractor that should the Sub-Contractor suffer an event of insolvency (including but not limited to administration, administrative receivership, liquidation, ceasing or threatening to ceasing carrying on its business in the normal course or otherwise) or otherwise not be able to pay back the Advance Payment to the Contractor immediately upon receipt of a written demand from the Contractor, the Guarantor shall immediately be liable to the Contractor for the payment of the Advance Payment and shall indemnify and hold harmless the Contractor against any loss, damage, demands, charges, payments, liability, proceedings, claims, costs and expenses suffered or incurred by the Contractor arising therefrom or in connection therewith.”
“3.1B The obligations of the Guarantor under this deed shall be in addition to and shall be independent of any other security which the Contractor may at any time hold in respect of the Sub-Contractor’s obligations under this deed [which] may be enforced against the Guarantor without first having recourse to any such security.”
“The result of the foregoing brief survey is that, with the parties free to agree whatever terms they choose, there is in this field of law a spectrum of contractual possibilities ranging from the classic contract of guarantee, properly so called, at the one end, where the liability of the guarantor is exclusively secondary and will be discharged if, for example, there is any material variation to the underlying contract between principal and creditor, to the performance or demand bond (or demand guarantee) at the other end, where liability in the giver of the bond may be triggered by mere demand and without proof of default by the principal (and indeed where it may be apparent that the principal is not in default). There may be little to distinguish (and it may not matter) whether the obligation undertaken is in the nature of a guarantee (strictly so called) or an indemnity. Where it does matter, the question is whether the liability to be enforced is secondary (or ancillary) to that of the principal (however qualified that liability may be), in which case the obligation is in the nature of a guarantee, or primary, in which case it will be in the nature of an indemnity and, if the latter, may be enforceable merely on demand (as with a performance or demand bond) or conditional on proof of default by the principal or on satisfaction of some other event or requirement. Where on the spectrum a particular case falls may call for a nice judgment on the part of the court faced with the task of construing the instrument in question.”