“Dear Sirs Brunel University – Running Track We refer to our meeting at the University on20 November 2002 and confirm having received from you various packages referred to as “Contract Documents”
“6 February 2002 The ERDC Group Limited 20 Harvest Road NEWBRIDGE Midlothian EH28 8LW BY POST AND FACSIMILE For the attention of D Reynolds/G Anderson Esq Dear Sirs, Re: Brunel University Sports Facility, Site 3 – Phase 1 (XCC) We write to inform you that your adjusted tender for the above works in the sum of£1,238,635.00 has been recommended for acceptance. However, the University are not in a position to award a contract until certain planning conditions are discharged. In the meantime in order to enable you to deliver the works in line with the Construction Programme of 8 weeks design/mobilisation period and 18 weeks construction, the University is prepared to issue this letter of appointment pending the execution of the Formal Contract subject to the following terms and conditions: The ERDC Group Limited NEWBRIDGE Midlothian EH28 8LW BY POST AND FACSIMILE For the attention of D Reynolds/G Anderson Esq Re: Brunel University Sports Facility, Site 3 – Phase 1 (XCC) 1. You are hereby authorised to carry out design, planning and procurement works as necessary to make a full and proper start to the works once full planning permission has been received subject to satisfactory insurances and liaison with the University Authorities which shall comprise some or all of the following but not restricted to the following:- • Design works in order to gain full planning permission • Submission of samples • Planning and procurement in preparation for a start on site Work shall be paid for in accordance with the normal valuation and certification rules of the JCT Standard Form of Building Contract With Contractor’s Design to a maximum of£15,000.00 until the issue of a further letter of intent and agreed revised sum or signing of the contracts. However such payment will not include any entitlement for loss of profit on any works not carried out. No expense shall be incurred in excess of the above sum or agreed revised sum until such time as the formal Contract Documents have been signed. 2. Your appointment shall be deemed to have commenced as at the date of the initial letter of intent issued on6 February 2002 . 3. Until formal execution of the Contract your appointment will be governed by the terms of this letter and the first letter of intent referred to in item 2. However upon the execution of the Contract performance by you of the works authorised by this letter shall be deemed to have been carried out under the Contract and according to its terms and conditions. 4. In the event that the Contract has not been entered into by the1 April 2002 the appointment conferred by this letter shall terminate with immediate effect. Subject thereto the terms of this letter will apply unless and until either:- 4.1 The appointment pursuant hereto is terminated by Brunel University in accordance with the JCT Standard Form of Building Contract With Contractor’s Design, or 4.2 The Contract is entered into by you and Brunel University. 5. In the event of early termination of the appointment pursuant to this letter in accordance with the provisions of paragraph 4 Brunel University shall pay you a fair and reasonable amount (which shall not exceed fifteen thousand pounds) (£15,000.00 ) taking into account any and all monies as have been provided prior to determination and all disbursements PROVIDED ALWAYS that where your appointment is terminated by Brunel University in accordance with the JCT Standard Form of Building Contract With Contractor’s Design as a result of failure by you to perform and observe any of the terms and conditions hereof the University shall be entitled to deduct from such monies and cost of procuring a replacement Contractor, complete such of the works as remain to be performed. 6. Subject to your acceptance of the foregoing terms and conditions, Brunel University hereby confirms that it will pay you up to the sum of fifteen thousand pounds (£15,000.00 ) in respect of the provision of the works required under the terms of this letter. 7. Please provide us with a copy of your developed Health and Safety Plan as soon as possible, but in any case at least five days prior to any work commencing on site. This letter constitutes an instruction to you to commence work but only as necessary for you to ensure that the agreed construction programme is met. As you are aware planning permission has been granted subject to the finalisation of an S106 Agreement and certain conditions being discharged before full permission is granted and works may commence on site. Details of this are contained in our letter to yourselves dated31 January 2002 . Your reply to this letter dated1 February 2002 confirms that you will be able to submit the relevant information, etc. within 10 working days after the date of this letter. Should planning permission, sufficient to commence works on site, not be received by the planned start on site date Brunel University reserves the right to extend the start on site date through discussion and agreement with yourselves. You shall release no information concerning this interim arrangement publicly without the Employer's prior approval in writing. Please confirm by return that the above terms are acceptable to you by countersigning and returning one copy of this letter. Yours faithfully, Paul Farley DEPUTY DIRECTOR – ESTATES’ 16. The differences between that letter and the later letters are mostly immaterial. However I take as an example the second letter of intent dated30 April 2002 as it referred to the first letter. It read “Dear Sirs Brunel University, Sports Facility. Site 3 – Phase 1 (XCC) We write to inform you that your adjusted tender for the above works in the sum of£1,238,635.00 has been recommended for acceptance. However, the University is not in a position to award a full contract until certain planning conditions are discharged. In the meantime in order to enable you to deliver the Works in line with the Construction Programme of 2 weeks mobilisation commencing from the date of this letter and 18 weeks construction thereafter in the sum of£1,238,635.00 , the University is prepared to issue this letter of appointment pending the execution of the Formal Contract subject to the following terms and conditions: 1. You are hereby authorised to carry out design, planning and procurement works as necessary to make a full and proper start to the Works on15 May 2002 subject to satisfactory insurances and liaison with the University Authorities which shall comprise some or all of the following but not restricted to the following:- • Design works in order to gain full planning permission • Submission of samples • Planning and procurement in preparation for a start on site • Completion of track design and associated works • Sub-contractor design of floodlighting, irrigation and fencing • Track surfacing sub-contractor confirmation • CDM regulations 1994 & QA requirements Work shall be paid for in accordance with the normal valuation and certification rules of the JCT Standard Form of Building Contract With Contractor’s Design to a maximum of£38,000.00 until the issue of a further letter of intent and agreed revised sum or signing of the contracts. However such payment will not include any entitlement for loss of profit on any works not carried out. No expense shall be incurred in excess of the above sum or agreed revised sum until such time as the formal Contract Documents have been signed. 2. Your appointment shall be deemed to have commenced as at the date of the initial letter of intent issued on6 February 2002 . 3. Until formal execution of the Contract your appointment will be governed by the terms of this letter and the first letter of intent referred to in item 2. However upon the execution of the Contract performance by you of the works authorised by this letter shall be deemed to have been carried out under the Contract and according to its terms and conditions. 4. In the event that the Contract has not been entered into by15 May 2002 the appointment conferred by this letter shall terminate with immediate effect. Subject thereto the terms of this letter will apply unless and until either:- 4.1 The appointment pursuant hereto is terminated by Brunel University in accordance with the JCT Standard Form of Building Contract With Contractor’s Design, or 4.2 The Contract is entered into by you and Brunel University. Brunel University, Sports Facility. Site 3 – Phase 1 (XCC) • Design works in order to gain full planning permission • Submission of samples • Planning and procurement in preparation for a start on site • Completion of track design and associated works • Sub-contractor design of floodlighting, irrigation and fencing • Track surfacing sub-contractor confirmation • CDM regulations 1994 & QA requirements Work shall be paid for in accordance with the normal valuation and certification rules of the JCT Standard Form of Building Contract With Contractor’s Design to a maximum of£38,000.00 until the issue of a further letter of intent and agreed revised sum or signing of the contracts. However such payment will not include any entitlement for loss of profit on any works not carried out. No expense shall be incurred in excess of the above sum or agreed revised sum until such time as the formal Contract Documents have been signed. 5. In the event of early termination of the appointment pursuant to this letter in accordance with the provisions of paragraph 4 Brunel University shall pay you a fair and reasonable amount (which shall not exceed thirty eight thousand pounds) (£38,000.00 ) taking into account any and all monies as have been provided prior to determination and all disbursements PROVIDED ALWAYS that where your appointment is terminated by Brunel University in accordance with the JCT Standard Form of Building Contract With Contractor’s Design as a result of failure by you to perform and observe any of the terms and conditions hereof the University shall be entitled to deduct from such monies and cost of procuring a replacement Contractor, complete such of the works as remain to be performed. 6. Subject to your acceptance of the foregoing terms and conditions, Brunel University hereby confirms that it will pay you up to the sum of thirty eight thousand pounds (£30,000.00 ) in respect of the provision of the works required under the terms of this letter. 7. Please provide us with a copy of your developed Health and Safety Plan as soon as possible, but in any case at least five days prior to any work commencing on site. This letter constitutes an instruction to you to procure works to enable a start on site to be made on15 May 2002 to ensure that the agreed construction programme is met. As you are aware planning permission has been granted subject to the finalisation of an S106 Agreement and certain conditions being discharged before full permission is granted and works may commence on site. Should planning permission, sufficient to commence works on site, not be received by the planned start on site date Brunel University reserves the right to extend the start on site date through discussion and agreement with yourselves. You shall release no information concerning this interim arrangement publicly without the Employer's prior approval in writing. Please confirm by return that the above terms are acceptable to you by countersigning and returning one copy of this letter. Yours faithfully Paul Farley DEPUTY DIRECTOR – ESTATES” 17. ERDC’s case was that there was no contract in any form prior to1 September 2002 . Mr Hargreaves contended that essential terms were never agreed; “the Works” was never agreed so there was either no agreement on an essential term or a fundamental uncertainty. Each letter of intent contained a termination provision: “In the event that the Contract has not been entered into by … the appointment conferred by this letter shall terminate with immediate effect.”
“letter of appointment …. subject to the following terms and conditions ..”; “governed by the terms of this letter”; “… works required under the terms of this letter”
“There is no allowance for weather delays”
“The reason why this dispute has arisen is because the work started pursuant to, or following, what the parties have referred to as a letter of intent sent on23 October 1995 . This letter actually set up a contractual relationship, pursuant to which the work started, which is a bilateral contract. A letter of intent is usually a unilateral assurance intended to have contractual effect if acted upon, whereby reasonable expenditure reasonably incurred in reliance upon such a letter will be reimbursed. Such a letter places no obligation on the recipient to act upon it and there is usually no obligation to continue with the work or to undertake any defined parcel of work, the recipient being free to stop work at any time. The effect of such a letter is to promise reasonable reimbursement if the recipient does, in fact, act upon it. However, the letter in question … is one which imposes obligations on both parties. It requires the plaintiff to commence the Works. These Works consist of a defined package of work and contract administration. The plaintiff had an option of whether or not to start work but, having started, the plaintiff was under an obligation to continue with the Works and not to stop, unless the defendant appointed another contractor or gave notice abandoning the work or the contract was superseded by one of the two successor contracts envisaged by the letter … I propose, therefore, to refer to this contract as “the provisional contract” 25. Mr McCall argued that where there was evidence, objectively, of a joint intention to create contractual relations, the court will try to recognise any intended agreement as a contract. He referred to Chitty on Contracts, 28th edition, Vol. 1, para 2-129: “The courts do not expect commercial documents to be drafted with strict legal precision. The cases provide many examples of judicial awareness of the danger that too strict an application of the requirement of certainty would result in the striking down of agreements intended by businessmen to have binding force. The courts are reluctant to reach such a conclusion, particularly where the parties have acted on the agreement. As Lord Wright said in Hillas & Co Ltd v Arcos Ltd(1932) 147 LT 503 at page 514: ‘Businessmen often record the most important agreements in crude and summary fashion, modes of expression sufficient and clear to them in the course of their business may appear to those unfamiliar with the business far from complete or precise. It is accordingly the duty of the court to construe such documents fairly and broadly, without being too astute or subtle in finding defects; but, on the contrary, the court should seek to apply the old maxim of English law, verba ita sunt intelligenda ut res magis valeat quam pereat. That maxim, however, does not mean that the court is to make a contract for the parties, or to go outside the words they have used, except in so far as they are appropriate implications of law.” 26. In support of Brunel’s case Mr McCall added that that policy was also illustrated by the willingness of the courts to imply terms rather than not to recognise an agreement as a contract, especially where the “contract” has been performed. He cited Mamidoil-Jetoil Greek Petroleum Co SA v Okta Crude Oil Refinery[2001] 2 Lloyd’s Rep 76 . In that case Rix LJ said at page 89: “…particularly in commercial dealings between parties who are familiar with the trade in question, and particularly where the parties have acted in the belief that they had a binding contract, the Courts are willing to imply terms, where that is possible, to enable the contract to be carried out. Where a contract has once come into existence, even the expression ‘to be agreed’ in relation to future executory obligations is not necessarily fatal to its continued existence. Particularly in the case of contracts for future performance over a period, where the parties may desire or need to leave matters to be adjusted in the working out of their contract, the Courts will assist the parties to do so, so as to preserve rather than destroy bargains, on the basis that what can be made certain is itself certain. Certum est quod certum reddi potest. This is particularly the case where one party has either already had the advantage of some performance which reflects the parties’ agreement on a long term relationship, or has had to make an investment premised on that agreement.”
“Your appointment shall be deemed to have commenced as at the date of the initial letter of intent issued on6 February 2002 ”
“Provided that no allowance shall be made under clause 12.5 for any effect upon the regular progress of the Works or for any other direct loss and/or expense for which the Contractor would be reimbursed by payment under any other provisions in the Conditions.”
“In my opinion, as a general rule, a ‘fair value’ of work undertaken by X for and at the request of Y on Y’s property (real or personal) ought to recognise an entitlement to a reasonable or normal profit margin over and above the costs actually and properly incurred in carrying out the work in question.”
“A quantum meruit claim may, however, arise in a wide variety of circumstances, across a spectrum which ranges at one end from an express contract to do work at an unquantified price, which expressly or by implication must then be a reasonable one, to work (at the other extreme) done by an uninvited intruder which nevertheless confers on the recipient a benefit which, for some reason, such as estoppel or acquiescence, it is unjust for him to retain without making restitution to the provider… At the first end of the spectrum … the measure should clearly be the reasonable remuneration of the claimant; at the other it should be the value to the defendant. In between there is a borderline, the position of which may be debatable.”
“Assessment of a reasonable sum. The courts have laid down no rules limiting the way in which a reasonable sum is to be assessed. Where a quantum meruit is recoverable for work done outside a contract, it is wrong to regard the work as though it had been performed to any extent under the contract. The contractor should be paid at a fair commercial rate for the work done. Where a quantum meruit is recoverable for work done pursuant to a void contract, it is wrong in principle to apply the provisions of the void contract to the assessment of the quantum meruit… But it is unclear whether, in determining what is a reasonable sum, it is permissible or relevant to consider the plaintiff’s conduct in performing the work and whether by reason of such conduct the defendant has suffered any unnecessary additional costs…”
“If the legitimate interests of a building contractor, such as the plaintiffs, are also to be taken into account then it seems to me that, in principle, as a minimum, all costs reasonably and necessarily incurred in properly carrying out the works ought to be reimbursed… [Recorder’s emphasis] Such a price must be the sum of the costs likely to have been incurred by a reasonably efficient person or organisation and a margin of some sort (e.g. lump sum or percentage addition) over and above those costs, otherwise economic activity of this type would not be worthwhile.”
“The site conditions and other circumstances in which the work was carried out, including the conduct of the other party, are relevant to the assessment of reasonable remuneration. The conduct of the party carrying out the work may be relevant. If the value is being assessed on a ‘costs plus’ basis then deduction should be made for time spent in repairing or repeating defective work or for inefficient working. If the value is being assessed by reference to quantities, such matters are irrelevant to the basic valuation. A deduction should be made on either basis for defects remaining at completion because the work handed over at completion is thereby worth less.”
“If, instead of ascertaining a ‘market value’, it is thought appropriate to calculate a ‘fair value’ from the costs actually incurred by the person or organisation which carried out the works, then the three words highlighted above [these were: “reasonably and necessarily incurred in properly carrying out the works”] would provide the key to the necessary effective control over the level of reimbursable costs if the legitimate interests of the owner are also to be respected. Having established such an objective base figure, a margin of some sort will fall to be calculated and added thereto. If the building contractor works inefficiently and/or if the building contractor leaves defective work then, quite obviously, the actual costs incurred by the building contract must be appropriately adjusted and/or abated to ensure that the owner will not be required to pay more than the goods and services provided are truly (objectively) worth.”
“A building contractor should not be better off as a result of the failure to conclude a contract than he would have been if his offer had been accepted, i.e., in practical terms, in a case such as this, the price which the building contractor thought he was to get for the works (because he thought his offer had been accepted) must be the upper limit of the remuneration to which he could reasonably claim to be entitled, even if at that level of pricing the building contractor would inevitably have ended up showing an overall loss.”
“If a claim in restitution can be sustained, the measure of damages will usually be the reasonable value of the benefit received by the defendant. In most cases this will normally be the market value, in the sense of a sum which would have been agreed on by a willing supplier and buyer, including a profit element. The measure should also have regard to the particular relationship between the parties and any advantages or disadvantages to them which arise out of that relationship. It may also take into account any prior discussions between the parties, and possibly the manner in which the services were performed. And where there is a concluded contract, but it is unenforceable, the contract itself may be good evidence of the value of the services performed.” 40. Mr McCall also referred to Hudson’s Building and Engineering Contracts (11th ed.) 1-264 where the distinction is made between claims on the basis of an implied promise to pay and those based on restitution. In a restitutionary claim such as the present case, the editor says: “The principle of restoration of benefit which is at the heart of true quasi contract means that the resulting obligation of the defendant is not to pay a reasonable price or remuneration based on the cost incurred by the plaintiff, but to reimburse him for the value of the advantage, if any, received by the defendant as a result of the work done or services performed. While, depending on the facts, the value of the work to the defendant may in many cases be equivalent to a reasonable compensatory price or remuneration for the plaintiff, it may on the facts of some cases be less, and sometimes nil.”
“[ERDC’s rates] cannot, therefore, be seen as unreasonable or otherwise prejudicial to ERDC. Similarly, whilst it has been difficult to find comparable rates in Spon’s for some of the more specialist items of work (for instance the track surfacing) it is again apparent from ERDC’s disclosure documentation that the rates in ERDC’s March Tender Estimate are consistent with rates paid to ERDC’s sub-contractors for these works.”
“a price or rate that was reasonable before 1 September, in my opinion, does not become unreasonable after 1 September simply because the authority in the letter of appointment expires”
“A building contractor should not be better off as a result of the failure to conclude a contract than he would have been if his offer had been accepted, i.e., in practical terms, in a case such as this, the price which the building contractor thought he was to get for the works (because he thought his offer had been accepted) must be the upper limit of the remuneration to which he could reasonably claim to be entitled, even if at that level of pricing the building contractor would inevitably have ended up showing an overall loss.”
“…We advised you in our letter of3rd December 2002 Ref. RGM/RK that we are only continuing on the basis that we will be paid on a Quantum Meruit basis. …If we can agree a further certification and payment to account, we would return to site to complete all remedial works at no cost to the University, and any outstanding works unaffected by weather conditions. We would leave site eliminating any further wastage of expenditure and return in the Spring to complete all outstanding works”
“As you are aware the strategy at present is to remove ERDC from the site at the most convenient opportunity. We need to agree by what process and procedure this takes place…”
“In overall summary, it is my opinion that ERDC ought reasonably to have completed the majority of those works which it did eventually complete by22 October 2002 . The lighting installations ought reasonably to have been completed and commissioned by1 November 2002 . Beyond that date only a small number of further items of work (mainly to the fencing and the pedestrian crossing) ought to have remained and almost all of those works were located off the main site. The planting works would always have been required to be carried out after the end of October 2002 but, in themselves, ought not to have involved ERDC in any time-related site establishment and management costs of any significance.”
“I think we are all aware of the main reasons for the delays: (a) delayed start on site; (b) reduced contract period; (c) increased topsoil depth; (d) importation of suitable fill; (e) attenuation tank; (g) no planning consent.”
“The Contractor will be responsible for providing power and water supplies to the scheme and liaising with the Statutory Authorities…”
“The cost shall include for provision of internal lighting, security lighting and providing an electricity supply to the store”
“In addition to the Electrical requirements contained in the tender documents the following is to be allowed for: Make provision in the design and construction of the electrical works for sufficient mains electrical supply and site distribution to suitable locations, for the requirements of all the sports facilities planned to be built in this and subsequent phases in order to avoid any disturbance to the completed Phase 1 works when subsequent phases are built. The intention is not to provide electrical distribution on the site/s of subsequent facilities within this phase.”
“Make allowance for the following additional Provisional Sum Include the Provisional Sum of£100,000 The work is defined as follows Mains electrical connection (including builders work in connection with the mains connection) for entire Site 3 and site distribution to areas of subsequent phases of work as defined in Item 5 of Amendments to Tender Information 1. It is NOT intended that this provisional sum covers for electrical works and site distribution to the Phase 1 works.”
“The Employer shall issue instructions to the Contractor in regard to the expenditure of provisional sums (if any) included in the Employer’s Requirements.”
“We also require to bring power, water and telephone services to the site and will require mechanical and electrical design services to liaise with the local utilities with regards the loading requirements etc from the details supplied by our Sub-Contractors for the mechanical and electrical installations”
“A new 450kVA HV three phase incomer shall be supplied to the site by the Regional Electricity Company Scottish & Southern … The Contractor shall contact the Utility and make all arrangements for this connection to be made to a new substation to be built to the REC requirements to allow for both their equipment and new LV distribution switchgear to be accommodated”
“The contractor shall arrange for the connection of an HV supply from the utility”
“1.03: Follow up and liaise with Electrical Engineer and Southern Electric to progress design, cost finalisation and construction of mains electrical supply as referred to in attached letter from BDP dated22 April 2002 and as shown on the following drawing: Site 3 Sports Facilities Electrical and Ancillary Services Indicative Containment Drawing (9-) LP016 Rev AA”
“The contractor shall arrange for the connection of an HV supply from the utility”
“Mr Don McConnel Connections Designer Scottish and Southern … Dear Sir BRUNEL UNIVERSITY, UXBRIDGE SITE 3 SPORTS DEVELOPMENT Further to our previous telephone conversations regarding the above site for which you provided a budget cost to one of the tendering parties for an LV supply we are writing to formally request a quotation for the supply and installation of a 5004 VA supply to the site. However we require an HV supply complete with meeting circuit breaker. The associated transformer shall be supplied, and installed by our clients’ contractor and owned by the client. An increase in capacity has been allowed to account for all existing LV supplies to the site which shall be re-supplied from the new substation. Please therefore forward a quotation including a timescale of how soon the supply could be available on site. Your specific requirements for civil works including substation construction etc will also be helpful at this stage. We understand you will be extremely busy, however, if you could treat this as a matter of urgency it will be most appreciated by all parties involved. The client, Brunel University are keen to make their new facilities available to their students and local community as soon as possible We have included a copy of a drawing showing the extent of the site which is alongside Kingston Lane. If you require further information, payment or signatures etc please do not hesitate to contact us and we shall endeavour to reply quickly. Yours sincerely Stuart Carrick For Building Design Partnership Ltd”
“With reference to Contract Instruction 1.03, attached is a quotation and further information dated21 May 2002 received from S+S for obtaining the electrical connection and supply onto the above site.”
“We refer to your Contract Instruction No. 02 regarding the quotation for the new electricity connection from S&S. For the avoidance of doubt can you please confirm that this is an instruction to: Accept their quotation on behalf of the Client. Complete the quotation acceptance on behalf of the Client. Pay the connection charge of£69,074.00 in advance. If so can you provide the name of the Client’s proposed electricity supplier and their meter operator. Can you also issue an additional instruction to undertake the civil works that S&S have excluded. As this is quite a large sum we would be grateful if an Interim Payment could be made to cover this amount plus initial design costs and site establishment. We will phone you on your return from holiday to discuss the above”
“In reply to your letter dated31 May 2002 we confirm that the 3 points you raise in relation to the Contract Instruction are correct. Please liaise directly with Bob Stiff, the University’s Energy Manager, (01895 274 000), Brunel University Estates Department, Cleveland Road, UXBRIDGE, UB8 3PH, bob.stiff@brunel.ac.uk) for details of the electricity supplier & mater operator. He does have a copy of the quote given by S+S. Can you please provide your cost for the building and civil works in connection with the mains supply cable and substation. Please liaise with Martin Jones of BDP regarding any specific requirements he may have for the substation enclosure. We will issue an instruction for this work in due course. As requested, you may submit an interim payment claim for the works completed thus far. The University will pay the cost of the connection charge in this claim provided that evidence is given that S+S have been paid. We trust the above answers your queries.”
“Chris I have met with Lawrie Tattersall of Scottish & Southern Electrical on Site yesterday. From the quote, Ref J103780, they shall only install an 11KV ring main cable. This cable is to be installed in a 4m x 4m approved building/box and a transformer must be installed in a separate compartment to give a low voltage supply suitable for the site. Other than the ring main the quote covers none of the other works. i.e. building and transformer by the developer. S+S Electrical anticipate installing the cable mid September. In order to progress the works details of the building and slab are required.”
“John With regard to your fax on the above. The work involved in the electrical supply relating to ERDC’s work and that covered by S+S’s quote is covered in Contract instructions 1 & 2. The letter from BDP (StuartCarrick) requesting the quote was also included together with the relevant drawing. As requested in the CI’s please liaise with Stuart Carrick firstly or secondly Kevin Featherstone of IDP regarding any requirements relating to the electrical works which are unclear or for which you need further information to complete the design. The substation needs to have sufficient capacity to be able to supply the remainder of the site when these phases are built. Please also refer to the Amendments to Tender, information for certain specific requirements on the electrical supply (this has been covered in the electrical drawing that was issued). We are writing to them to request if there are any special requirements relating to the substation enclosure. Although the design and size of this part of your design there may be special requirements placed on the design due to planning requirements. Is mid September the earliest they will be able to commence their works? We believe that a meeting needs to be held with ourselves and the design team to ensure clarity on the requirements, please advise when this can be held.”
“The design of the Substation enclosure is for ERDC to do. However, we need to forward to them any special requirements relating to the design, which we assume would really only relate to aesthetics and any planning constraints. As previously requested can you please urgently confirm to ERDC what the requirements are for this enclosure. Please liaise with GVA Grimley as necessary.”
“If the substation could be relocated or the design simplified then the electrical supply would ae available sooner and would improve hand over date”
“No floodlighting or other form of external lighting (including security lighting) shall be installed unless it is in accordance with details which have previously been submitted to and approved in writing by the Local Planning Authority. Such details shall include location, height, type and direction of light sources, intensity of illumination and shielding to eliminate vertical and horizontal light spillage….”
“4.2.1 The contractor is entirely responsible for the design and development of all lighting systems to be installed in the external areas … The design development shall take cognisance of the performance requirements … and of all mandatory and legislative requirements 4.5.2 In consideration to the footpath network to be illuminated the lamp types to be proposed should be indicative of the ‘white light’ source as proposed in the floodlight scheme” 75. The “floodlighting scheme” may be taken to be BDP’s “University Site 3 Lighting Report” which was incorporated into the invitation to tender. That report said: “Colour Appearance and Rendition” … “Light sources will be selected from the ‘white’ light lamp types producing good colour rendering properties and colour appearance to suit the surfaces being illuminated. Typically lamps will include metal halide, high pressure sodium de-luxe or ‘white sodium’ and fluorescent (triphospher). The selected colour appearance will depend upon the areas being illuminated. In the areas outside of the sports arenas, i.e. footpaths, it is intended to utilise ‘white’ light sources of different colour temperature to accent the varying priorities, e.g. pedestrian, vehicular, planting and landscape. Similarly, luminaire mounting heights will differ in changing areas from the transition of public highways to sports facilities. This change accents the social and leisure nature of the complex – differentiating and enhancing its socialness from the surrounding areas. These changes integrate the facilities into the environs in a considered manner such that when completed they will fit as a cohesive part.”
“We confirm that if awarded the … contract we would be able to progress the items… and forward the information required to those concerned within 10 working days” 76. This part of the case is concerned with when ERDC produced a satisfactory lamp type. The Employer’s Requirements were not particularly clear. There was debate between BDP and ERDC as to what was likely to be acceptable. ERDC’s case in part maintained that there were variations. If it is material, I disagree. In my view the objective was that the lighting would meet the planning conditions, as a matter of common sense as well as “legislative requirements”
“Lorne Stewart advised that they would approach the Clients Specified footpath luminaire supplier to produce a drawing showing the lux levels to the footpath. THIS IS URGENTLY REQUIRED FOR PLANNING.”
“Karl The floodlighting design is much improved and should not present a problem but I think we should reserve the right to require any additional shielding or lantern adjustments if we judge there to be a problem. The footpath lighting proposals SOX is not acceptable due to light pollution and the Council’s responsibilities under section 17 of the Crime and Disorder Act. BS5489 part 3 recommends the use of high pressure sodium lighting where “pedestrian activities predominate” or “areas that are environmentally sensitive”
“… With regards to the planning officers concern on light pollution, would you please consider Thorn ‘Decostreet’ luminaries on 4.00m post tops for the footpath lighting. We would advise the small dia. Decostreet 1 type (458mm dia.) with flat glass to eliminate any upward light. The lamp to be as Employers Requirements which from memory is 70w CDM-T metal halide (white light) All to be mounted on 4.00m tubular (or conical if preferred) columns. We need revised calculations to submit to planners. With regard to the repositioned floodlight columns, we need to see revised lighting calculations confirming light levels are compliant. Would you please ask Lorne Stewart to confirm what light levels will apply to the field event areas outside the perimeter of the track.…” 79. ERDC submitted details of Thorlux lighting, which was the incorrect type, (although that type had been previously contemplated). ERDC sent BDP’s suggestion to Lorne Stewart (on 4 September) and quickly received details (on 9 September). It seems that they lay in ERDC’s office for a month before being sent to BDP on 9 October. Mr Thompson could offer no real explanation and ERDC accept responsibility for the delay. However BDP could not immediately use the material as the fax copy was poor and not properly presented for the site. Nonetheless Hillingdon approved these details so on 19 November ERDC was able to instruct Lorne Stewart to go ahead with the erection of floodlights and the procurement of the footpath lights. They could not be delivered until the week commencing6 January 2003 . Work to the lighting equipment could therefore not start on site until the week commencing13 January 2003 . Installation was completed during the week of 27 January. The footpath lights were finally commissioned on12 February 2003 . 80. But for the fact that ERDC did however get paid as if there had been a change resulting from BDP’s request 29 August, I would not have said that there was an instruction to ERDC or a variation. It was a suggestion as to how ERDC might comply with its obligations. 81. It is clear that the delays to the footpath lighting are subsumed in the delay to the electrical connection. If examined separately, it is in my view plain it was not until the end of August (or early September, taking account of the change) that ERDC had the details and information necessary to satisfy the planning condition. Had it then been submitted I see no reason why it would not have reached Hillingdon and been approved by it in September (taking a generous view of the time needed). From what actually happened from mid-November it seems that that it would then have taken Lorne Stewart some six weeks thereafter to have obtained the fittings and two weeks (based on the actual period in January 2003) to have installed and, subject to supply, to have commissioned the lights, i.e. by the beginning of December 2002 at the latest. So leaving aside the question of supply Brunel would not be responsible for any period thereafter but ERDC would be entitled to time-related costs up to1 December 2002 . To that extent my conclusion is not the same as Mr Robinson’s. Other Matters Relating to Delay 82. The next question is: are there any other matters beyond those allowed by Brunel in reliance on Mr Robinson’s reports, i.e. beyond22 October 2002 or1 November 2002 ? Mr Robinson accepted that progress was retarded by matters such as increased topsoil depth, importation of suitable fill and the attenuation tank. It is clear that ERDC’s work changed and took longer as a result. Mr Binnie agreed that, from27 May 2002 until26 July 2002 , ERDC had been carrying out variations and that progress on footpaths, fencing and drainage had not been as expected during that period. For example, fencing did not start until around the end of August 2002, when ERDC had planned to start it on1 July 2002 . Footpaths were to have begun by8 July 2002 but did not start until the end of July 2002. It is however necessary briefly to consider events which are accepted to have had some impact or which might have done so. Attenuation Tank 83. The attenuation tank (or storm water retention tank) was a variation (ERDC’s Delay Event No 3). It was also built off-site. It was ordered at the outset. Its construction started on 24 June and was completed around21 July 2002 . It obviously delayed the start of outfield drainage and the main outfall. ERDC accepted Mr Robinson’s conclusions in para 3.82 and 3.83 of his Report (as put to Mr Binnie for his agreement): “Delay Event No 3 3.82 ERDC’s claimed Delay Event No 3 relates to the construction of the storm water retention tank. There is no dispute between the parties as to the fact that this was a significant additional item of work. Neither is there a dispute as to when this work was carried out and completed. Excavation work appears to have commenced during week commencing24 June 2002 . Construction of the tank itself was completed by21 July 2002 and the construction of the outfield drains commenced on25 July 2002 . This represents a delay to the commencement of the outfield drainage of almost 5 weeks when compared to ERDC’s Original Programme. In the event the outfield drainage was substantially completed (with the exception of kerb channels and gullies) by16 August 2002 . Again this was some 5 weeks later than indicated on ERDC’s Original Programme. 3.83 The effect of the instruction to construct the attenuation tank, therefore, was to delay the commencement and substantial completion of the outfield drainage by approximately 5 weeks. Substantial completion of the main out fall drain was also delayed by some 6 weeks compared to ERDC’s Original Programme. However, I do not consider that these delays to the drainage activities would themselves have delayed overall completion of the track and other works beyond the planned completion date of28 September 2002 .”
“We have considered deploying extra labour on-site but at the time of writing we have only two or three days' work in hand. My information from site tells me that the line of fencing at the rear of the houses still has to be defined and then tree roots have to be cleared from this line. We appreciate your efforts that went into having us appointed as fencing contractors.”
“4.08 – “The progress of the fencing and the footpaths have been particularly slow. ERDC say they are experiencing difficulty obtaining labour to complete these and other works.”
“4.0 Programme was discussed and agreed as follows: Start on Site ASAP Completion date28 September 2002 7.1 The Sub-Contractor indicated that the anticipated labour force would be 2-4 men 7.2 The Sub-Contractor confirmed that the required labour resources could be increased or decreased to suit the site requirements. 16.1 Normal site working hours …. 16.2 Overtime may be worked by the Sub-Contractor by prior arrangement with ERDC provided there are no additional costs to ERDC”
“We are disappointed to record that your fencers failed to show up again today. From commencement on site, your rate of production has been insufficient to finish your works within the programme period and your numerous recorded absences from site have only exacerbated the situation. We seek your assurance by return that additional resources will be brought to site to make up for the time you have lost on this and other occasions.”
“3.1.6 Equipment Store The Contractor shall design and construct an equipment store of approximately 100m 2 in accordance with Drawing No. SKS3A001 Rev A. The cost shall include for provision of internal lighting, security lighting and providing an electricity supply to the store.”
“We confirm that the design for the Equipment Store has been carried out to comply with Approved documents L2 to maintain an internal design temperature of 10 0C …”
“6.03 Approval of the storage building design is required urgently. Concern was expressed at the long term maintenance and repair difficulties that the non standard type insulated roller shutter door being proposed would pose. Alternative door to be looked at.” 96. In early July 2002 ERDC got a list of manufacturers of insulated roller shutter and sectional overhead doors but it did not then send details to CAP or BDP. On14 August 2002 ERDC told CAP that it was dealing with getting details of the roller doors but the details had still not been provided by Site Meeting No 4 on21 August 2002 : “5.13 A proposed roller shutter door for the store building was discussed. This to be formally proposed along with details being sent: ERDC”
“Further to the message I left on your mobile can we arrange a meeting for early in the new year. In order to reduce your mounting costs might I suggest the possibility of omitting the infield works, store building, extension of paving etc from your Works this would then enable you to concentrate on the extensive snagging list remedial works with a view to handing over the track by the13th January 2003 and in turn enable us to release further monies. Obviously this approach would then enable you to cease incurring further site set up costs, particularly when we do not know yet when the weather will allow the infield works to commence.”
“The level [of profit] should be that prevailing in the market during the period immediately following the original date for completion … it might, therefore, be higher or lower than that contemplated in the contract sum.”
“(e) In any event it is averred that the assessment of a reasonable sum needs to take into account the following: (i) The Claimant is entitled to payment for works necessarily, properly and reasonably carried out at the Defendant’s request and for the Defendant’s benefit. (ii) The Claimant is not entitled to payment for defective work or for time spent in carrying out defective work. (iii) The Claimant is not entitled to payment for rectifying defective work or for time spent in rectifying defective work (iv) The Claimant is not entitled to payment for inefficiencies and/or delays in its works. (v) A reasonable sum must reflect the value or worth of the works objectively and/or to the Defendant.” (i) The Claimant is entitled to payment for works necessarily, properly and reasonably carried out at the Defendant’s request and for the Defendant’s benefit. (ii) The Claimant is not entitled to payment for defective work or for time spent in carrying out defective work. (iii) The Claimant is not entitled to payment for rectifying defective work or for time spent in rectifying defective work (iv) The Claimant is not entitled to payment for inefficiencies and/or delays in its works. (v) A reasonable sum must reflect the value or worth of the works objectively and/or to the Defendant.”
“By reason of the above breaches, the Defendant has suffered loss and damage, namely the costs of remedial works, as set out in Schedule 3. Further or in the alternative, the Defendant is entitled to abate the Claimant’s claims by the remedial costs set out in Schedule 3. In my judgment, should it be necessary, Brunel cannot maintain a claim for breach of contract since the defects are in the work left by ERDC on its departure from the site at the end of March 2003. There was no contract at that stage. There can therefore be no counterclaim in the classic sense – hence this section is termed “counterclaim”. 124. Brunel’s position was well put by Mr McCall. He pointed out that if ERDC was right in saying that there could be no adjustment or abatement then a contractor, who is not carrying out work under a contract but to fulfil an employer’s requirements and does so in such a way that some of the work was of benefit because it was good work but other work was not, might rely on a restitutionary remedy to give it the benefit of the good work but not to bear the consequences of the bad. That would be contrary to the restitutionary principles of quantum meruit. In such a situation only the contractor benefits. What if the value of the defective work was higher than the value of the good work? Was the employer to suffer a net loss? He referred to Crown House and to Serck at paras 55-59: “55. What emerges from the authorities, in my view, is that distinctions needs to be drawn. If the value is being assessed on a “costs plus” basis, for example from time sheets and hourly rates for labour, then deductions should be made for time spent in repairing or repeating defective work, and for inefficient working or (as is one of the allegations here) excessive tea-breaks and the like. If the value is being assessed by reference to quantities the claimant stands to gain nothing from such activities or inactivities and, if attributable to the claimant or his sub-contractors, they are irrelevant to the basic valuation; extra time and expense enter into the picture at this stage only if relied upon by the claimant as arising without fault on his part, as discussed in paragraphs 47 to 51 above. If such a claimant makes a claim based on extra time or expense which was in truth his own fault he should fail, but that is simply an issue of fact; Serck says that it has excluded such elements from its valuations. 56. A second distinction is that between defects made good during the course of the work, which are covered by the discussion in the last paragraph, and those remaining at completion. There should clearly be a deduction for the latter, if pleaded and proved, whatever the mode of valuation, simply because the work as handed over is thereby worth less, but no such plea is advanced here. 57. The third distinction is between what I have called “the basic valuation”, which is the subject of the last two paragraphs, and matters which, even if expressed in terms of a “reduction” or “diminution” of the valuation, are in essence “cross-claims”, in the words of Bingham LJ in Crown House. They are in essence cross-claims because what the defendant seeks is in truth compensation for loss or expense suffered or liabilities incurred by reason of the claimant’s conduct. The examples given in the above extracts are “tardy performance” and “unsatisfactory performance”, but there may be others. It is, as I understand it, only to this last category that the extracts from Crown House and the last sentence of that from Lachhani above apply. 58. If that is the nature of such claims they must depend upon breach of some duty by the claimant, so the first question is as to the nature and extent of the duties owed, in the absence of express terms, when carrying out such work, and in particular duties as to progress and co-operation with other trades, for no breach of any other duty seems to be at all relevant here. There is clearly no duty to adhere to any particular contractual programme, for there is no contract, and indeed in the present case it was precisely inability to agree upon a programme which was one of the reasons for failure to enter into a contract. 59. In fact no duty of any relevant kind, nor any breach of such a duty, is pleaded or relied upon by DS (except in relation to the separate point dealt with in paragraph 84 below), nor do I understand from Mr Burr’s closing submissions on the law that any cross-claim of the kind now under discussion is in the end pursued; his contention is simply that DS should not be “penalised” by inefficient working or inadequate supervision on Serck’s part, or be required to pay for hours spent in rectifying defective work. These are all matters within the scope of the principles discussed in paragraphs 55 and 56 above and do not involve the issue left open in the Crown House case. I do not therefore have to decide that issue. 125. On the submissions the following questions were likely to arise where the person liable to pay maintained that the quality or fitness of what was done or performed should be taken into account: 1. What standard or standards was the work or service to attain? 2. If it did not meet that standard then how was the value of the resulting work or service to be measured: by valuing as if it had been met the requisite standard (i.e it had been done properly) but adjusting that value by the actual or notional cost of what reasonably required to meet the required standard or by valuing the work or service in the condition in which it had been left? On standards, I understood it to be common ground that the standard of the work would have to be examined in order that it could be valued. There was a difference in approach between the parties. If the remedy being granted was restitutionary then the standard would be that attaching to the request. By complying with the request there was accession to that standard. If the remedy was contractual then the standard would be that set by the agreement. In practical terms there is in my view no material difference between the two approaches and none at all on the facts of this case where the standards were the contractual standards that had applied prior to1 September 2002 and which continued to be applied thereafter. In the case of additional work they were set by the instruction or request. In the absence of a specification the usual standards would apply – the design and work would have to be a reasonably good quality and, in the case of work designed by ERDC, reasonably fit for its purpose. 126. The two approaches differ materially when it comes to valuation. Mr Hargreaves argued forcefully that since there was no contract the question was one of valuing the benefit conferred. If the work was so far short of the required standard as to be valueless then the value of the benefit would be nought. It could not however be less than nought as could happen if Brunel were right. If the costs of putting the work right exceeded its value then Brunel’s case required ERDC to compensate Brunel. He said that there would be recovery where there had been “free acceptance” and an “incontrovertible benefit”
“Again, it is sufficient, in our view, that the benefit is realisable; it should not be necessary to demonstrate that it has been realised”
“In our view, the fact that the defendant may have suffered loss in consequence of the plaintiff’s acts or inaction should not be taken into account in determining the quantum meruit award.”
“33. The alternative basis of restitutionary recovery on which Coys rely is “incontrovertible benefit”
“It is said that the principle of respect for the subjectivity of value would be subverted if this were accepted. But it may not be unreasonable, in some circumstances, to compel a person to sell an asset which another has mistakenly improved”
“Break out kerbs to existing Long Jump run-up and 1 No. sandpit and relay in accordance with MSC drawing to be issued16 June 2003 .”
“Soil levels will be adjusted to produce a smooth surface with regular gradients to levels suitable for the appropriate finished level as indicated on the drawing, filling to be consolidated in consecutive layers not exceeding 225mm deep by heavy roller. Trim to uniform true surface leaving free of noticeable ruts and depressions” “Prepare all areas to be seeded by cultivating the area to a minimum of depth of 300 mm and levelling the area to specified levels. Bring the areas to a fine tilth by raking or harrowing and light rolling to achieve soil particles not in excess of 6mm. All stones above 10mm in any dimension should be removed from the surface to the approved contract’s tip”
“the drains will need to be lifted in stone aggregate to within 150mm of pitch level and blinded with 150 sand..”
“I have spoken with Inturf and told them that the only drainage that we require is reinstatement work after the final grading. This assumes that the infield drainage is compliant. We will request some exploratory pits whilst they are on site to assess in what condition ERDC have left the infield drains…. What we need is for Inturf to be appointed as soon as possible…”
“The Contractor shall provide cable ducts beneath the athletics track at 4 No. positions near the tangent points, to permit the passage of power and control cables, photofinish cables, public address cables, etc., terminating in chambers with covers at ground level. Thechambers are to be adequately drained. At each position there shall be 2 No. ducts, of minimum 150mm diameter, each fitted with 2 No. draw cords. With his tender, the Contractor shall provide a drawing showing the proposed construction and exact locations of these ducts.”
“ERDC had been topping up the concrete to the fence posts. This has not been successful and the concrete had not keyed to the original concrete. A number of posts are unstable, particularly along the southern boundary”
“Circuit width:- sufficient to ensure that the outer white line is marked entirely on the synthetic surfaces, as required by the IAAF and UKA Rules”