“26. The Adjudicator may open up, review and revise any certificate, decision, direction, instruction, notice, opinion, requirement or valuation made in relation to the Contract. 28. The Adjudicator may, within 5 days of delivery of the decision to the Parties, correct his decision so as to remove any error arising from an accidental error or omission or to clarify or remove any ambiguity.”
“(i) whether Completion of the works has been achieved and if so the date of Completion (ii) Whether the first moiety of retention of 1.5% has fallen due for payment and if so when and (iii) The amount of LAD’s Celtic are entitled to deduct from interim payment certificates 12 and 15 and subsequent payment certificates together with a decision as to the amount to be paid by Celtic in respect of LAD’s wrongfully deducted and payment certificates 12 and 15.”
“a. Completion of the Works was achieved on8 June 2009 and a certificate of Completion is deemed to have been issued on the relevant date in accordance with clause 30.2 of the Contract; and that b. The first moiety of retention is due and the sum of£34,962.86 should be paid by Celtic to Rok forthwith, together with interest for late payment in the sum of£519.65 to the date of this decision; and that c. The amount of LADs (delay damages) that Celtic are entitled to the deduct from interim payment certificate 12, certificate 15 and subsequent payment certificates is£47,000.00 ; and that d. Celtic shall forthwith pay the sum of£32,500.00 to Rok in respect of LADs wrongfully deducted from payment certificates 12 and 15 together with interest for late payment in the sum of£483.05 (being£287.16 plus£195.89 ); and that e. Celtic shall pay interest on any sum awarded or paid late at the rate of 2% per annum above the average base rate…as calculated above to the date of my decision and which will continue to accrue at a daily rate of£4.62 until judgement or sooner payment; and that f. Celtic shall forthwith pay the Adjudicator’s costs and expenses.”
“11.14 I have found the witness evidence helpful in varying degrees. It is voluminous and in some places more relevant than others. In this adjudication there has not been an opportunity for the witnesses to be cross-examined and that in my opinion places some limitation on the witness evidence. Much of the witness evidence provided takes the form of a relatively partisan rebuttal of the other party’s position. 11.15 However, each party has provided a substantial amount of contemporaneous evidence in support of the statements made and the positions adopted. 11.21 I am faced in the written submissions and evidence before me with completely opposing views as to the achievement of, or proximity to, the achievement of Completion, in particular through the witness evidence of Mr Bunting for Rok and Mr Trickey for Celtic. 11.22 As well as written witness evidence from Mr Bunting and Mr Trickey, I have also been presented with considerable contemporaneous evidence within their statements. It is the contemporaneous evidence which is, in my view, most telling.” (e) He analysed, largely but not entirely from the contemporaneous documents, what happened from21 May 2009 , when Mr Bunting e-mailed Mr Trickey that substantial completion was expected to be substantially complete on5 June 2009 , until August 2009. Mr Bunting’s e-mail attached a list of outstanding work activities headed "substantial completion list”
“the amount of LADs…that Celtic are entitled to deduct from interim payment certificate 12 is£13,000 and the amount of LADs…that Celtic are entitled to deduct from interim payment certificate 15 and subsequent payment certificates is£47,000 …”
“It is inherent in the [adjudication] scheme that injustices will occur, because from time to time, adjudicators will make mistakes. Sometimes those mistakes will be glaringly obvious and disastrous in their consequences for the losing parties. The victims of mistakes will usually be able to recoup their losses by subsequent arbitration or litigation, and possibly even by a subsequent adjudication…”