“The above rates are fixed for the duration of our works. Valuations will be weekly and subject to 5% retention for a period of six weeks from your Commencement Date and will then be twice monthly, subject to 5% retention.”
“2. The Contract provided for the deduction and retention at 5%. There was no express provision for the release of such retention. 3. PCH have failed to repay any or all or the retention. As a consequence, a dispute exists as to the method and timing in which the retention should have been repaid… 6. The Adjudicator is asked to decide that the retention should have been repaid by reason of an implied term and what that term shall be. 7. The Adjudicator is asked to decide the final dates or date that the retention should have been repaid. 8. The Adjudicator is asked to decide that the total retention of£66,628.50 or such other sum as the Adjudicator shall decide is to be repaid forthwith.”
“2.3 The contract at the bottom of the first page provides for the deduction of 5% retention. In fact retention was deducted at 3%. Tyroddy aver that consequently a term must be implied for such repayment. Tyroddy further aver that the correct term to be so implied should be based on normal trade custom and practice. Such normal trade custom and practice requires the payment of ½ of the sum withheld upon completion of the contract and the balance 12 months thereafter or upon making good defects, whichever is the later… 4.1 The Adjudicator is asked to decide that the retention should have been repaid by reason of an implied term and that that term should be as described in paragraph 2.3 above or such other implied term as the Adjudicator shall decide. 4.2 The Adjudicator is asked to decide the final dates or date that the retention should have been repaid.. 4.3 The Adjudicator is asked to decide that the total retention of£66,628.50 , or such other sum as the Adjudicator shall decide, is to be repaid forthwith…”
“1.3. PCH have at several times during the course of this adjudication referred to their alleged claim to recover substantial sums on other contracts with Tyroddy, on the grounds that their valuations have been found to be incorrect and that as a consequence Tyroddy have been over paid. It is now claimed that a similar error has been made on this contract. That this error should have been made at this time, some 5½ years after PCH’s last valuation, may be regarded with suspicion. It is Tyroddy’s contention that this claim is both out of time and defectively calculated and as a consequence the Adjudicator should find the claim unfounded. 1.4. PCH have incorporated three witness statements from the team which on their own case jointly and severally have so mismanaged their valuations of Tyroddy’s work that PCH now considers that Tyroddy has been over paid on not one but four contracts to a value in excess of£600,000 . The Adjudicator may view with considerable scepticism the reliability of statements made by witnesses who can claim to have performed so poorly in the past. Further if the first valuation was wrong then the Adjudicator should place little or no reliance in a revised one. 2.3… By the express wording of the contract PCH undertook to value the work. To the extent they claim that their certificates were not accurate valuations of the work they were in breach of contract and may not now benefit from their breach by claiming that their certificates were not proper valuations of the work as carried out in all circumstances. It is also correct to say that Tyroddy did not make formal applications for payment. However PCH are incorrect in stating that they could not base valuations on the actual quantity of reinforcement. PCH with a site quantity surveyor was in fact much better placed and better qualified to value the work, both as to reinforcement delivered and that actually fixed than was Tyroddy’s visiting director… 5.3. It is to be inferred from paragraph 16 that PCH issued 111 certificates without once checking that the total being certified was correct. These 111 presumably were prepared by Mr McGann and authorised by Mr Wood …if this is correct then it would appear that PCH are author of their own misfortune by reason of their mismanagement and incompetence … 5.10 Two possible conclusions may be drawn from Mr McGann’s statement:- 1. That he has been either grossly negligent or grossly incompetent having overvalued the work on the Wembley contract by over £¼ million at 2005 values. Or 2. That his revaluation is a complete fabrication. Whichever of the above is correct and Mr McGann having been employed by PCH for 8 years suggests that he is not regarded as being incompetent, the Adjudicator must find Mr McGann’s evidence unreliable and reject it.”
“2(d)(iii) It is clearly established that an interim certificate is no more than a provisional estimate of the amount to which a contractor (or in this case a subcontractor) is entitled by way of instalment…Tyroddy’s attempt to escalate an interim (and "on account") valuation to the status of a final certificate is contrary to established authority… 2(d)(v) in relation to the timing issue the facts of Cantrell v Wright & Fuller… makes it clear that slippage where there is a prescribed timetable for the issue of certificates is not conclusive. Tyroddy cannot rely on slippage as evidence of complicity, all the more so when the owners of taking the next step (submission of its final account claim) rested with Tyroddy. 2(d)(vi) As a matter of fact, the last in time certificates cannot be the final account in circumstances where PC Harrington has now established that Tyroddy has been overpaid in respect of its work, and Tyroddy has failed to show that the certificate in question accurately reflects the correct value (and indeed suggest in its Reply, at paragraph 2.2, that the last certificate is wrong)…: Both Tyroddy and the Adjudicator have now been given the information required to assess PC Harrington’s valuation of the final account. PC Harrington’s evidence on the point is unchallenged.: Ultimately, the Adjudicator should not lose sight of the fact that this is, to all intents and purposes, a claim for "money due". Subject to the fact that Tyroddy has not sought to refer to the Adjudicator its entitlement to a certificate relating to final account/retention issues, the exercise the adjudicator is being asked to undertake is to determine whether the amount claimed by Tyroddy is due to it. PC Harrington says it is not due, for the reasons set out in the evidence it has submitted. But, far from PC Harrington benefiting from its breach (as Tyroddy claims), the reality is that Tyroddy is seeking to be unjustly enriched, that is to be paid a sum to which, on the taking of the final account, it is not due. The Adjudicator should not go down that path.. If, as a matter of taking a proper account between the parties, retention (or the amount of retention apparently withheld under earlier certificates) is not due because there has been an overvaluation of Tyroddy’s account during the course of the contract, then as a matter of fact, that amount cannot have been withheld from Tyroddy’s account and cannot therefore be due for repayment.”
“93. A proper ascertainment for works completed at the Wembley National Stadium by Tyroddy after9 June 2003 will show an entitlement to a final account value in the sum of£1,929,235.53 as set out above. 94. As a result, Tyroddy had been overpaid the sum of£225,085.97 , which is now due and owing to PCH.”
“THE DISPUTE 8. The Notice of Adjudication states that:- “ PCH have failed to repay any or all of the retention withheld. As a consequence a dispute exists as to the method and timing in which the retention should have been repaid. ” 9. The Referral specifically request my decision(s) on the implied term governing when a. retention should be paid; b. The final date(s) of payment; c. the sum that is payable forthwith; d. the interest due; and e. that the Responding Party is liable for my fees and expenses… MY DECISION 14. I decide that the retention should have been repaid in accordance with an implied term of half of the retention monies should have been paid at completion of the subcontract works and the remainder 12 months later. 15. I decide that the final dates of payment were:14 June 2006 for the first moiety; and14 June 2007 for the remainder. 16. I decide that the total retention of£66,628.50 is to be paid forthwith by PCH to TCL… REASONS 22…My reasons follow. 23. The matters to be considered in my Decision included:- • Does a Dispute exist? • What's the matter resolved by a Settlement Agreement? • What is the Dispute?... • What is the correct quantification of Retention? • To whom does the Retention along? • What is the purpose of Retention? • When is retention due for release?... • Is set-off allowed under this contract claims on another contract?... 27. The dispute, as described in the ‘Notice of intention to refer a dispute to adjudication’ concerns the release mechanism for the retention monies held on this contract in the sum of "…£66,628.50 . The directions requested from the Adjudicator, in my opinion, merely categorise the stages in the release of that retention, or such other sum-if it is considered due. 28. The alternative arguments put forward by the parties do not alter this basic premise. There is only one dispute. This involves the release of the retention certified by PCH on Certificate 9171 for work up to28th May 2006 which remains unpaid. TCL requesting my directions for "… method and timing in which the retention should have been repaid” are no more than highlighting the steps I must investigate, review and then decide upon before making my Decision. ”
‘83. Reliance was placed upon my observations in Cantillon Ltd v Urvasco Ltd[2008] BLR 250 at Paragraph 57: “From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases: (a) it must first be established that the adjudicator failed to apply the rules of natural justice; (b) any breach of the rules must be more than peripheral; they must be material breaches; (c) breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant. (d) whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in the case such as this. (e) it is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case can be Balfour Beatty Construction Company Limited v The London Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation to thereto.” The Cantillon case was concerned with an allegation that the adjudicator had made his decision upon the factual or legal basis not argued or put forward by either side without giving the parties opportunity to comment or address. That is not the case here… 85. As to whether the breach was a material one, on analysis the only point put forward by CJP is that the Adjudicator's decision in the second adjudication demonstrates that the Adjudicator would probably have found against Verry even if he had considered the Response in the first adjudication. CJP argues that the onus of proof must be on Verry to show that the breach was a material one and that the adjudicator would have reached a different decision. I am satisfied that the breach here was a material breach: (a) In itself, the failure to disregard the whole of Verry's response both as to argument and as to evidence was and must have been material. There comes a point when a breach of the rules of natural justice is so pervasive that the only proper conclusion to come to is that the breach is material. (b) It is not necessary for the Court to go so far as having to investigate the facts to determine whether the adjudicator would have reached a different decision in substance if he had considered the Response. All one need say (and I do) is that there was a real possibility that the adjudicator could have reached a different decision. I am satisfied that there is a real (as opposed to fanciful) possibility in this case. (c) Because Verry decided to stop participating in the second adjudication part way through, there is no telling what the adjudicator would have decided if Verry had pressed its case with force and logic throughout the remainder of the adjudication.’
“22. As a matter of principle, therefore, it seems to me that the law on this topic can be summarised as follows: 22.1. The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable: see Carillion v Devonport. 22.2. If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice: see Ballast, Broadwell, and Thermal Energy.”
“20. The next ground relied on by the defendant is that of breach of natural justice. The position is that neither the claimant nor the defendant in the adjudication had suggested that any withholding notice was necessary before the question of defective work or the deduction of liquidated damages could be taken into account. It is clear that the point about the need for a withholding notice was a point taken by the adjudicator himself. The adjudicator during the adjudication did not raise the point with the parties and it is clear that the defendant did not have any opportunity to make submissions to the adjudicator on his rejection or proposed rejection of the defendant’s claims for defects and liquidated damages. If a court had acted in this way and decided issues on a ground which had not been raised before it and where the parties had not been given an opportunity to make submissions on the point, there is little doubt but that the decision would be open to challenge on the grounds of breach of natural justice. The issue in the present case is how far the principles which a court would be expected to follow apply to an adjudication… 25. In my judgment what the adjudicator has done was manifestly and seriously unfair to the defendant. The defendant’s claims that the claimant’s work was defective was an important part of its defence. The defendant claimed the defects amounted to£135,916.48 and if that was correct the amount of any award in favour of the claimant would have been very significantly reduced. The adjudicator however rejected this claim (and any balance of the claim for liquidated damages) without considering it upon its merits as in my judgment he should have done. The defendant has been deprived of any opportunity of persuading the adjudicator that his view of the law was incorrect and the consequence is that the adjudicator has excluded a very substantial part of the defence without any consideration of its merits for reasons which are wrong in law. There is nothing to suggest that the defendant should have realised that the adjudicator might be of the view that a withholding notice was necessary before he could consider these claims. In my judgment the failure of the adjudicator to raise the point with the parties and to invite their comments before issuing his decision was so unfair to the defendant that the court should not enforce the decision summarily. It would be a strong thing to hold a party to a decision which is obviously wrong on an important part of the defendant’s case when the defendant has not had any opportunity to address the adjudicator on the point. There is nothing in Carillion which compels such a result. It cannot in my judgment be said that the defendant at trial would not have a reasonable prospect of establishing its defence that the adjudicator had reached his decision in serious breach of the rules of natural justice and that in the circumstances the decision is not binding.”
“I do not accept the abatement to value exercise carried out by PCH primarily because it is not agreed, but also contractually flawed and outwith this dispute.”
“TCL dispute this final account and, as such, I consider that any eventual final account dispute is another dispute and outwith this matter.”
“On a true and proper construction of the contracts, Tyroddy’s claims for release of retention monies allegedly due from PCH could legitimately be met by PCH relying on any cross-claim amounting to a set-off permissible under the contract and/or any right of retainer which could be levied against the retention fund and Tyroddy’s right that the former could not and cannot be determined without resolving the latter.”